7 CSR 10-24.110
Solicitation Procedures for Competitive Proposals
PURPOSE: This rule provides the elements
included in phase one and phase two solicitation procedures.
(1) The first phase consists of a short listing
based on a Request for Qualification (RFQ).
(2) The second phase consists of the receipt
and evaluation of price and technical proposals in response to a Request for Proposal
(RFP).
(3) The commission may include the following items in any phase one solicitation:
(A) The scope of the work;
(B) The cost estimate of the design-build
project;
(C) The project completion date; and
(D) A detailed disadvantaged business
enterprise (DBE) participation plan including:
1. Information describing the experience
of the proposer in meeting DBE participation
goals;
2. How the proposer will meet the commission DBE participation goal; and
3. Such other qualifications that the commission considers to be in the best interest of
the state as stated in the RFQ;
(E) The phase one evaluation factors and
their relative weights, including:
1. Technical approach (but not detailed
design or technical information);
2. Technical qualifications, such as:
A. Specialized experience and technical competence;
B. The capability of proposers to perform, including key personnel; and
C. Past performance of the members
of the proposerโs team, including the architect-engineer and construction members;
3. Other appropriate factors, excluding
cost or price related factors which are not
permitted in phase one; and
(F) Phase two evaluation factors; and
(G) A statement of the maximum number
of proposers that will be short-listed to submit phase two proposals.
(4) The commission will include the requirements for separately submitted sealed technical proposals and price proposals in the phase
two solicitation. All factors and significant
subfactors that will affect contract award and
their relative importance will be stated clearly in the solicitation. The commission will
use its own procedures for the solicitation as
long as it complies with the requirements of
this section.
(5) The commission may allow proposers to
submit alternate technical concepts in their
proposals as long as these alternate concepts
do not conflict with criteria agreed upon in
the environmental decision making process.
Alternate technical concept proposals may
supplement, but not substitute for base proposals that respond to the RFP requirements.
Transportation Commission
Selection procedure
Award criteria options
Standard Design-
Build Selection
Procedures
Lowest price, adjusted low
bid (price per quality point),
meets criteria/low bid,
weighted criteria process,
fixed price/best design,
best value.
Modified
Design-Build
Lowest price technically
acceptable.
AUTHORITY: sections 226.020, 226.030,
and 227.107, RSMo 2016.* Emergency rule
filed Oct. 17, 2005, effective Oct. 27, 2005,
expired April 25, 2006. Original rule filed
Aug. 15, 2005, effective Feb. 28, 2006.
Amended: Filed Dec. 5, 2017, effective July
30, 2018.
*Original authority: 226.020, RSMo 1939; 226.030,
RSMo 1939, amended 1965, 2003, 2004, 2009; and
227.107, RSMo 2002, 2007, 2009, 2011, 2016.