10 CSR 22-3.050
Safety Permit Requirements
PURPOSE: The purpose of this rule is to
itemize the requirements for a safety permit.
(1) In addition to the basic requirements for
all permits listed in 10 CSR 22-3.020, the
safety permit application for a conventional
dam and reservoir shall include:
(A) Notification of the completion of construction and application for the first safety
permit for the dam and reservoir shall be provided by the owner. The experienced professional engineer or agency engineer who was in
responsible charge of the construction work
shall certify that the construction was substantially in accordance with the approved plans
and specifications. If revisions have been
made which vary considerably from the provisions of the construction permit, it must be
shown that the revisions do not endanger public safety, life or property. This subsection
shall not be construed to excuse any person
from the requirement to notify the council or
chief engineer of modifications or revisions
prior to commencing the actions and to
obtain the required permits or authorization
thereof;
(B) Notification of completion shall be
within two (2)-monthsโ time after completion
of construction; and
(C) As-built drawings shall be submitted.
(2) In addition to the basic requirements for
all permits listed in 10 CSR 22-3.020, the
application for a safety permit for an industrial water retention dam and reservoir shall
include:
(A) Notification of completion of the
starter dam or the initial phase of construction shall be prepared by, or under the supervision of, an experienced professional engineer and shall indicate that construction was
performed in accordance with the provisions
of the construction permit;
(B) Notification of the completion of construction and application for the first safety
permit for the dam and reservoir shall be provided by the owner. The experienced professional engineer who was in responsible
charge of the construction work shall certify
that the construction was substantially in
accordance with the approved plans and specifications. If revisions have been made which
vary considerably from the provisions of the
construction permit, it must be shown that the
revisions do not endanger public safety, life
or property. This subsection shall not be construed to excuse any person from the requirement to notify the council or chief engineer
of modifications or revisions prior to commencing the actions and to obtain the
required permits or authorization therefore;
(C) Notification of completion shall be
within two (2) months time after completion
of construction; and
(D) As-built drawings shall be submitted.
(3) Visits for the purpose of observation of
operation and maintenance procedures may
be made by the council, the chief engineer, or
a member of their staff. Visits will be at any
reasonable time following reasonable notice,
except that in the case of an emergency
threatening public safety, life or property,
inspection may be made at any time.
AUTHORITY: sections 236.400, 236.405,
236.415, 236.420, 236.425, 236.440, and
236.465, RSMo 2016.* Original rule filed
April 14, 1981, effective Aug. 13, 1981.
Amended: Filed June 14, 1984, effective Jan.
1, 1985. Amended: Filed June 27, 2018,
effective Feb. 28, 2019.
*Original authority: 236.400, RSMo 1979; 236.405,
RSMo 1979, amended 1993, 1995; 236.415, RSMo 1979,
amended 1995; 236.420, RSMo 1979; 236.425, RSMo
1979; 236.440, RSMo 1979; and 236.465, RSMo 1979.