10 CSR 26-2.013
UST Systems with FieldConstructed Tanks and Airport Hydrant
Fuel Distribution Systems
PURPOSE: This rule contains the new
requirements for the previously deferred fieldconstructed tanks and airport hydrant fuel
distribution systems.
(1) Applicability. This rule applies to owners
and operators of field-constructed tanks and
airport hydrant fuel distribution systems.
(2) Deadline for compliance. Owners and
operators of existing underground storage
tank (UST) systems with field-constructed
tanks or airport hydrant fuel distribution systems must comply with all of the requirements of 10 CSR 26-2.010 through 10 CSR
26-2.083, the financial responsibility requirements in 10 CSR 26-3, and operator training
in 10 CSR 100-6.
(A) Immediately upon installation for any
new UST systems installed after July 1,
2017.
(B) By July 1, 2019, for existing systems,
except where such requirements are specifically excluded or amended by this rule.
(3) Corrosion protection. UST system components that routinely contain product and
are in contact with an electrolyte, including
soil, backfill, or water, must meet one (1) of
the following:
(A) Performance Standards for New UST
Systems, as defined by 10 CSR 26-2.020; or
(B) Be constructed of metal and cathodically protected, with the cathodic protection
system complying with 10 CSR 26-2.031.
Unprotected metal tanks must pass an integrity test, in accordance with 10 CSR 26-2.021
and 10 CSR 26-2.031, prior to the addition of
cathodic protection. Unprotected steel piping
cannot be upgraded and must be replaced.
(4) Spill and overfill prevention equipment.
UST systems must be upgraded with the
installation of spill and overfill prevention, in
accordance with 10 CSR 26-2.020 and 10
CSR 26-2.030, except where “delivery”
occurs through a dedicated pipeline permanently connected to the UST system(s). For
these systems, owners and operators must have
an alarm system and/or an approved plan to
prevent releases due to overfill.
(5) Walkthrough inspections. In addition to
the walkthrough inspections in 10 CSR 262.036, owners and operators must inspect the
following additional areas for airport hydrant
fuel distribution systems at least once every
thirty (30) days if confined space entry
according to the Occupational Safety and
Health Administration under 29 CFR Part
1910 is not required, or at least annually if
confined space entry is required, and must
keep documentation of these walkthrough
inspections in accordance with 10 CSR 262.036:
(A) Hydrant pits—visually check for any
damage, remove any liquid or debris, and
check for any leaks; and
Substance Storage Tanks
(B) Hydrant piping vaults—check for any
hydrant piping leaks.
(6) Applicability of closure requirements to
previously closed UST systems. The department may require that the owner and operator
of a UST system with a field-constructed tank
system or an airport hydrant fuel distribution
system permanently closed before April 30,
2017, assess the excavation zone and close
the UST system in accordance with 10 CSR
26-2.060 through 10 CSR 26-2.064 if releases from the UST system, in the judgment of
the department, pose a current or potential
threat to human health and the environment.
(7) Release detection. Owners and operators
of existing UST systems must comply with
the release detection requirements mandated
in 10 CSR 26-2.040 through 10 CSR 262.048 no later than July 1, 2020.
AUTHORITY: sections 319.100, 319.103,
319.105, 319.107, 319.109, 319.111, 319.114,
319.117, 319.120, 319.123, and 319.137,
RSMo 2016.* Original rule filed Aug. 15,
2016, effective May 30, 2017.
*Original authority: 319.100, RSMo 1989, amended 1991,
1993, 1996, 1998; 319.103, RSMo 1989; 319.105, RSMo
1989; 319.107, RSMo 1989, amended 1994; 319.109,
RSMo 1989, amended 1995, 2004, 2008; 319.111, RSMo
1989; 319.114, RSMo 1989, amended 2016; 319.117,
RSMo 1989; 319.120, RSMo 1989; 319.123, RSMo 1989;
and 319.137, RSMo 1989, amended 1993, 1995, 2004.