10 CSR 26-2.071
Initial Release Response and Corrective Action
PURPOSE: This rule describes the immediate
steps owners and operators of a leaking
underground storage tank must take.
(1) Upon confirmation of a release in 10 CSR
26-2.052, or after a release from the underground storage tank (UST) system is identified in any other manner, owners and operators must perform the following initial
response actions within twenty-four (24)
hours:
(A) Report the release to the department
in accordance with 10 CSR 26-2.050;
(B) Take immediate action to prevent any
further release of the regulated substance into
the environment; and
(C) Identify and mitigate fire, explosion,
and vapor hazards.
AUTHORITY: section 319.109, RSMo Supp.
2010.* This rule originally filed as 10 CSR 2010.061. Original rule filed April 2, 1990,
effective Sept. 28, 1990. Moved and amended:
Filed April 15, 2011, effective Dec. 30, 2011.
*Original authority: 319.109, RSMo 1989, amended 1995,
2004, 2008.