10 CSR 26-2.072
Initial Abatement Measures and Investigation
PURPOSE: This rule describes the first steps
to stop the spread of the release and finding
the extent of the release.
(1) Unless directed to do otherwise by the
department, owners and operators must perform the following abatement measures upon
confirmation of a release:
(A) Remove as much of the regulated substance from the underground storage tank
(UST) system as is necessary to prevent further release to the environment;
(B) Visually inspect any above-ground
releases or exposed below-ground releases
and prevent further migration of the released
substance into surrounding soils and groundwater;
(C) Continue to monitor and mitigate any
additional fire and safety hazards posed by
vapors or free product that have migrated
from the UST excavation zone and entered
into subsurface structures such as sewers or
basements;
(D) Remedy hazards posed by contaminated soils that are excavated or exposed as a
result of release confirmation, site investigation, abatement or corrective action activities. If these remedies include treatment or
disposal of soils, the owner and operator
must comply with applicable state and local
requirements;
(E) Measure for the presence of a release
where contamination is most likely to be present at the UST site, unless the presence and
source of the release have been confirmed in
accordance with the site check required by 10
CSR 26-2.052(1)(B) or the closure site
assessment of 10 CSR 26-2.062. In selecting
sample types, sample locations, and measurement methods, the owner and operator must
consider the nature of the stored substance,
the type of backfill, depth to groundwater,
and other factors as appropriate for identifying the presence and source of the release;
and
(F) Investigate to determine the possible
presence of free product and begin free product removal as soon as practicable in accordance with 10 CSR 26-2.075.
(2) Within twenty (20) days after release confirmation, owners and operators must submit
a report to the department summarizing the
initial abatement steps taken under section (1)
of this rule and any resulting information.
AUTHORITY: sections 319.109 and 319.137,
RSMo Supp. 2010.* This rule originally filed
as 10 CSR 20-10.062. Original rule filed
April 2, 1990, effective Sept. 28, 1990.
Moved and amended: Filed April 15, 2011,
effective Dec. 30, 2011.
*Original authority: 319.109, RSMo 1989, amended 1995,
2004, 2008 and 319.137, RSMo 1989, amended 1993,
1995, 2004.