10 CSR 26-2.074
Initial Site Characterization
PURPOSE: This rule describes the steps for
investigation of a release.
(1) Unless directed to do otherwise by the
department, owners and operators must
assemble information about the site and the
nature of the release, including information
gained while confirming the release or completing the initial abatement measures in 10
CSR 26-2.070, 10 CSR 26-2.071, and 10
CSR 26-2.072. This information must
include, but is not necessarily limited to, the
following:
(A) Data on the nature and estimated quantity of release;
(B) Data from available sources or site
investigations concerning the following factors: surrounding populations, water quality,
use and approximate locations of wells potentially affected by the release, subsurface soil
conditions, locations of subsurface sewers,
climatological conditions, and land use;
(C) Results of the site check required
under 10 CSR 26-2.072(1)(E); and
(D) Results of the free product investigations required under 10 CSR 26-2.072(1)(F)
to be used by owners and operators to determine whether free product must be recovered
under 10 CSR 26-2.075.
(2) Within forty-five (45) days of release confirmation, owners and operators must submit
the information collected in compliance with
section (1) of this rule to the department or in
a format and according to the schedule
required by the department.
AUTHORITY: sections 319.109 and 319.137,
RSMo Supp. 2010.* This rule originally filed
as 10 CSR 20-10.063. Original rule filed
April 2, 1990, effective Sept. 28, 1990.
Moved and amended: Filed April 15, 2011,
effective Dec. 30, 2011.
*Original authority: 319.109, RSMo 1989, amended 1995,
2004, 2008 and 319.137, RSMo 1989, amended 1993,
1995, 2004.