1 CSR 30-3.030
Project Design
PURPOSE: This rule sets forth the procedure
for design of projects.
(1) Selection of Designer.
(A) Design by Department/Agency. The
department/agency may recommend in-house
design for those projects within their capability and capacity, provided they have licensed
engineers or architects to seal the prepared
plans and specifications. The director will
concur with this recommendation unless
there appears to be a substantial question of
capability or capacity. The director will be
the determining authority for questions of
department/agency capacity and/or capability
for design of projects.
(B) Design by Division of Facilities
Management, Design and Construction. The
director will examine projects remaining after
selections for in-house department/agency
design. Those projects that are cost prohibitive to be done by consultants or for which
the Division of Facilities Management,
Design and Construction has the capability
and capacity may be selected for in-house
design by that division.
(C) Design by Consultants. Private consultants will be selected by the director for
design of the balance of the projects.
1. The director will maintain a file and
database of consultant firms who have
expressed interest in performing work on projects. This file will include notations of specific areas of experience or expertise as
expressed by each consultant firm and ratings
of previous projects completed and evaluated
by the division.
2. The department/agency may make
recommendations for selections of consultants for design of projects not selected for inhouse design.
3. The selection of consultants will be
based on the factors set forth in section 8.289,
RSMo. The director will approve the selected
consultants after full consideration of the
consultants’ professional and technical competence, experience, special expertise, and
capacity necessary for studies and/or design
of proposed projects.
A. Consideration will be given to providing opportunities for as many competent
consultants as possible. Consultants who have
not been retained for recent state projects will
be given priority consideration in selections
for new projects.
B. In those projects or programs
where continuity is a significant factor, consideration will be given to continued retention of a consultant already engaged for existing projects or programs.
(2) Consultant Firm Design.
(A) Contracts. The division will negotiate
contracts for consultant studies and/or design
in accordance with section 8.291, RSMo.
These contracts will be negotiated for a reasonable fee considering scope, difficulty,
research, disciplines involved, and proposals
by the selected consultant. The director
reserves the right to approve additional consultants retained by the selected consultant for
work on the project or study.
(B) Communications. All official communication and direction to the consultant will
be issued by the director or his/her designee,
and all official communications for all
designs and/or studies by the consultant will
be with the director or his/her designee. This
will include all submissions for approval or
payment, recommendations for modifications
of scope, or other guidance and resolution of
any differences or problems encountered.
This will not limit informal communication
or coordination between consultants and
department/agencies. Informal communication and working conferences between the
department/agency, and the consultant are
essential to successful completion of a project
and are encouraged. Knowledgeable personnel shall be made available by the department/agency for consultations and site visits
by the consultant. The consultant, by prior
arrangement, shall have access to the project
site at reasonable times. Records and conclusions reached at any working conference(s)
between the department/agency and the consultant will be forwarded to the director or
his/her designee by the consultant for review
and approval.
(C) Consultant’s General Responsibilities.
The consultant is responsible for establishing
the concept and planning for the project, as
well as providing completed designs, studies,
or both as indicated in consultant contract. For
project design, the consultant is responsible
for providing plans and specifications to fully
describe the equipment, materials and work
for completion of the project in accordance
with the criteria, funding, and scope provided
by the director. Periodically, as scheduled in
the contract, the consultant will submit work
for review and approval. The submissions will
include estimated costs for all project work.
When estimates for the complete project work
exceed allocated funding, the consultant
immediately shall notify the director, recommending adjustments and requesting further
instructions before proceeding with additional
design and/or study. Acceptance of the contract by the consultant includes acceptance of
the adequacy of allocated funding for the work
and the responsibility for redesign, if necessary, to establish a scope of project work within allocated funding.
(D) Payments. Payment method and/or periods will be as stipulated in the consultant’s
contract. The director is responsible for
review and approval of a consultant’s requests
for payment. Approval of payment to a consultant will be based on review and approval of
work completed to the date of the payment
request. Where there appear to be differences
between the payment request and the demonstrated progress, those differences will be
resolved by decision of the director or his/her
designee.
(3) Design Review. Designs and/or studies will
be submitted to the director or his/her designee
for review and approval in all projects designed
by a department/agency or a consultant. The
director’s review will include examination of
technical adequacy, as well as economy of
materials and construction methods proposed.
In addition, the director will examine estimated costs to assure that projects remain within
funding authorizations. The review will be
commensurate with the scope, complexity, and
cost of the work. In the case of design by a
consultant, review will be coordinated with the
department/agency concerned. One (1) complete copy of each submission will be forwarded by the designer to the department/agency
simultaneously with the submission to the
director or his/her designee. Comments by the
department/agency representative, if any, will
be forwarded to the project manager.
Department/agency comments, along with
comments of the Division of Facilities
Management, Design and Construction, will
be used as the basis for response to the
designer.
(A) Pre-Design Conference. For projects
designed by a consultant, a pre-design conference will be scheduled by the project manager with the consultant and the representative of the department/agency concerned. The
project definitions established in the initial
coordination will be reviewed to confirm or
adjust project criteria, scope, cost, scheduling, and funding allocation. Initial fund distribution for the cost elements of the project
will also be reviewed to confirm or adjust this
fund distribution. Limitations and/or requirements expressed in the appropriation language should be carefully observed to assure
that the project scope, costs, and funding
remain within the authorization of the appropriations. The designer must agree that the
scope of work can be accomplished within
the available funding. When appropriate, the
pre-design conference will be held at the project site to assure that all parties are familiar
with the conditions under which the work
will proceed, and that accommodations necessary to support the work are available. The
design schedule begins with completion of
the pre-design conference. After that, no
changes will be made in the scope or funding
of projects without written approval of the
director.
(B) Design Review Submissions. For projects designed by a consultant, normally, a
minimum of three (3) design review submissions will be made. These submissions will
be made at approximately twenty percent
(20%), fifty percent (50%), and one hundred
percent (100%) of design completion to provide for timely review of technical and economic considerations in the design. For
minor projects, the first two (2) submissions,
with the approval of the project/construction
manager, may be combined to provide design
reviews at fifty percent (50%) and one hundred percent (100%) of design completion.
1. Schematic.
Initial
submission
(approximately twenty percent (20%)) should
provide drawings and an outline of specifications, in sufficient detail to demonstrate the
proposed concept for arrangement, as well as
the criteria and general parameters used for
architectural, electrical, mechanical, and
structural development. Proposed innovative
methods or development should be presented
in sufficient detail to permit a review in
depth. An estimate should be submitted in
sufficient detail to demonstrate the costs of
the various elements of work as well as the
total cost for completion of all project work.
A copy of all items in the schematic submission
will
be
furnished
to
the
department/agency that will occupy or use
the completed project. Comments and/or recommendations of the department/agency will
be forwarded to the project manager. The
project scope and cost estimate should be
reviewed carefully to assure compliance with
requirements and/or limitations of appropriation language. Approval by the director’s representative of schematic submission will indicate acceptance of, or required revisions to,
scope, criteria, design parameters, and cost
estimate.
2. Design Development. The second
submission (approximately fifty percent
(50%)) should provide drawings and outline
specifications to indicate general architectural, electrical, mechanical, and structural
development of the approved concept. The
development should clearly demonstrate
sizes, capacities, and arrangement, and
Design and Construction
include sufficient details to define major elements of architectural and structural work
and to define sizing, location, routing, and
application of mechanical and electrical
equipment and/or work. An estimate should
be submitted in sufficient detail to demonstrate costs of the various elements of work as
well as the total cost for completion of all
project work. The detail should indicate costs
for major items of equipment as well as a
breakdown of labor and material costs for
each trade with significant work on the project. When the first two (2) design review
submissions are combined, a copy of all
items in the design development submission
will be forwarded to the department/agency
that will occupy or use the completed project.
Comments and/or recommendations of the
end user will be forwarded to the project
manager. When a project site is in a city or
county that has adopted codes for regulation
of work involved in a project, the designer
will furnish one (1) courtesy copy of the
design development drawings and specifications to the code review authority of that city
or county. The transmittal shall note that the
plans and specifications are furnished as a
courtesy, for information only, and that the
code review authority, if it desires, may submit comments to the director’s representative
for consideration.
3. Final Review. The final review submission is to contain one hundred percent
(100%) of the completed drawings and specifications, including the documentation
required to solicit bids. Drawings and specifications will be submitted in accordance
with the latest issue of State of Missouri’s
Standard Specification Format as published
by the Division of Facilities Management,
Design and Construction. The documents are
to be complete, and sealed by appropriate
engineering and/or architectural disciplines.
A final construction cost estimate should be
submitted in sufficient detail to demonstrate
costs of the various elements of work as well
as the total cost for completion of all project
work. The detail should indicate costs for
major items of equipment as well as a breakdown of labor and material costs for each
trade with significant work on the project.
The final review documents and a copy of all
previous comments and responses generated
during the design development submission
will be included with the submittal.
Comments and/or recommendations of the
department/agency will be forwarded to the
project manager.
4. Construction Documents. This final
submission shall consist of drawings and
specifications and construction cost estimate.
The documents are to be complete, sealed by
appropriate engineering and/or architectural
disciplines, and ready for issuance for bidding. Upon receipt, the project manager will
finalize the bidding documents. The director’s designee performs an administrative
review of the documents and, if acceptable,
signs the documents as appropriate.
(4) Codes and Standards. The following are
adopted as the codes and standards for work
on state facilities, with the exception of facilities operated and maintained by agencies
exempted from the requirements of this regulation as set forth below. The chief engineer/architect of the division is the authority
for code determinations.
(A) International Building Codes (IBC–
current edition);
(B) The Americans with Disabilities Act
(ADAAG–current edition);
(C) National Fire Code (NFPA 70 -
National Electrical Code and NFPA 101–Life
Safety Code–current editions);
(D) International
Mechanical
Code
(IMC–current edition);
(E) International Plumbing Code (IPC–
current edition);
(F) American
Society
of
Heating,
Refrigerating and Air-Conditioning Engineers
(ASHRAE Standards 90.1 for Energy
Efficient Design of New Buildings except
Low-Rise Residential Buildings–current edition);
(G) American Society of Mechanical
Engineers (ASME–current edition);
(H) American National Standards Institute
(ANSI–current edition);
(I) American Concrete Institute (ACI–current edition);
(J) Sheet Metal and Air Conditioning
Contractor’s National Association (SMACNA–current edition);
(K) Boiler and Pressure Vessel Act of the
State of Missouri– (current edition).
(L) Local Codes. Current codes adopted
by a Missouri city and/or county in which a
project site is located are applicable only to
the extent that they are not in conflict with the
codes listed above or are otherwise required
by statute. The State of Missouri and its contractors are exempt from paying license,
inspection, or similar fees for work on state
premises.
(5) Bidding.
(A) Prospective Bidders. Consultants
retained for design work should assist the
director in establishing a list of prospective
bidders for projects they design. If necessary,
consultants will contact prospective bidders
to determine and/or solicit interest in bidding
for the work. The department/agency will
provide, within its capability, similar assistance.
(B) Bid Review and Recommendations. The
project manager will notify the designer and
the department/agency of scheduled project bid
dates. Immediately following the opening of
bids for a project, the project manager may
coordinate a review of the bids with the
department/agency and, when appropriate,
with the designer. If the bids for the project
are within available funding and there is
agreement on the low responsive bidder, the
department/agency will forward its written
recommendation for award to the director
along with the encumbrance for the amount
of the recommended award. If project bids
are not within available funding or agreement
on the low responsive bidder is not reached,
the department/agency will forward to the
director its written recommendation for subsequent action on the project. When requested by the director, the designer also will forward a recommendation on the bids received
and/or subsequent action on the project.
(6) Exceptions. Exceptions to the requirements of this rule may be granted by the commissioner of administration or his/her
designee upon presentation of satisfactory
justification for those exceptions.
(7) Exemptions. There are specific exemptions from requirements of this rule provided
by the Missouri Constitution and by the
Revised Statutes of Missouri.
(A) Department of Transportation projects
and expenditures for highway construction
and highway maintenance are exempted from
the provisions of this rule by Article IV,
Section 29, Missouri Constitution of 1945.
(B) Institutions of higher learning, community junior colleges, and the Department of
Conservation are exempted by section 8.310,
RSMo from provisions of this rule which
require coordination with or approval by the
commissioner of administration and/or the
director of the Division of Facilities
Management, Design and Construction for
defining projects, determining fund allocation, negotiation or approval of contracts, and
approval of payments.
AUTHORITY: sections 8.310 and 8.320,
RSMo 2016.* Original rule filed July 9,
1981, effective Feb. 15, 1982. Emergency
amendment filed June 14, 1985, effective July
1, 1985, expired Oct. 29, 1985. Amended:
Filed June 14, 1985, effective Aug. 26, 1985.
Rescinded and readopted: Filed Nov. 5, 2007,
effective June 30, 2008. Amended: Filed Oct.
11, 2018, effective May 30, 2019.
*Original authority: 8.310, RSMo 1958, amended 1965,
1984, 1987, 1995, 2014 and 8.320, RSMo 1958, amended 1965, 2014.