10 CSR 40-3.020
Requirements for Casing and Sealing of Drilled Holes
PURPOSE: This rule sets forth the requirements for casing and sealing of drilled holes
pursuant
to
sections
444.810
and
444.855.2(10)(iii), RSMo.
Editor’s Note: The secretary of state has
determined that the publication of this rule in
its entirety would be unduly cumbersome or
expensive. The entire text of the material referenced has been filed with the secretary of
state. This material may be found at the
Office of the Secretary of State or at the headquarters of the agency and is available to any
interested person at a cost established by
state law.
(1) General Requirements. Each exploration
hole, other drill or borehole, well or other
exposed underground opening shall be cased,
sealed or otherwise managed, as approved in
the permit and plan, to prevent acid or other
toxic drainage from entering ground or surface waters, to minimize disturbance to the
prevailing hydrologic balance and to ensure
the safety of people, livestock, fish and
wildlife, and machinery in the mine plan and
adjacent area. If these openings are uncovered or exposed by surface mining activities
within the permit area, they shall be permanently closed, unless approved for water
monitoring or otherwise managed in a manner approved in the permit and plan. Use of
a drilled hole or borehole or monitoring well
as a water well must meet the provisions of
10 CSR 40-3.040(14) and those of the
Wellhead Protection Section, Division of
Geology and Land Survey, at 10 CSR 23,
Chapter 6. This section does not apply to
holes solely drilled and used for blasting.
(2) Temporary Casing and Sealing. Each
exploration hole, other drill or boreholes,
wells and other exposed underground openings which have been identified in the
approved permit application to be used to
monitor the groundwater conditions shall be
temporarily sealed before use and protected
during use by barricades, fences or other protective devices approved in the permit and
plan. These devices shall be inspected periodically and maintained in good operating
condition by the person who conducts the
surface mining activities.
(3) Permanent Casing and Sealing. When no
longer needed for monitoring or other use
approved in the permit and plan, upon a finding of no adverse environmental or health or
safety effect, or unless approved for transfer
as a water well under 10 CSR 40-3.040(14)
and those of the Wellhead Protection Section,
Division of Geology and Land Survey, at 10
CSR 23, Chapter 6, each exploration hole,
other drilled hole or borehole, well and other
exposed underground opening shall be
capped, sealed, backfilled or otherwise properly managed, as required in the permit and
plan under section (1) of this rule and consistent with 30 CFR 75.1711. Permanent closure measures shall be designed to prevent
access to the mine workings by people, livestock, fish and wildlife and machinery and to
keep acid or other toxic drainage from entering ground or surface waters.
AUTHORITY: section 444.530, RSMo Supp.
1999.* Original rule filed Oct. 12, 1979,
effective Feb. 11, 1980. Amended: Filed
March 21, 2000, effective Oct. 30, 2000.
*Original authority: 444.530, RSMo 1971, amended 1983,
1990, 1993, 1995.