10 CSR 40-3.030
Requirements for Topsoil Removal, Storage and Redistribution
PURPOSE: This rule sets forth the requirements for topsoil removal, storage and redistribution pursuant to sections 444.810 and
444.855.2(5), RSMo.
(1) General Requirements.
(A) Topsoil and subsoils to be saved under
section (2) of this rule shall be separately
removed and segregated from other material.
(B) After removal, topsoil shall either be
immediately redistributed as required under
section (4) of this rule or stockpiled pending
redistribution as required under section (3) of
this rule.
(C) Topsoil and subsoils to be saved under
section (2) of this rule shall be removed twenty-five feet (25') in advance of mining unless
otherwise stated in the permit.
(2) Topsoil Removal.
(A) Timing. Topsoil shall be removed after
vegetative cover that would interfere with the
use of the topsoil is cleared from the areas to
be disturbed, but before any drilling, blasting, mining or other surface disturbance
identified and approved in the permit and
plan.
(B) Materials to be Removed. All topsoil
shall be removed in a separate layer from the
areas to be disturbed, unless use of substitute
or supplemental materials is approved in the
permit and plan in accordance with subsection (2)(E) of this rule. If use of substitute or
supplemental materials is approved, all materials to be redistributed shall be removed.
(C) Materials to be Removed in Thin
Topsoil Situations. If the topsoil is less than
six inches (6"), a six-inch (6") layer that
includes the A horizon and the unconsolidated materials immediately below the A horizon or the A horizon and all unconsolidated
material if the total available is less than six
inches (6”) shall be removed and the mixture
segregated and redistributed as the surface
soil layer, unless topsoil substitutes are
approved in the permit and plan pursuant to
subsection (2)(E) of this rule.
(D) Subsoil Segregation. The B horizon
and portions of the C horizon, or other
underlying layers demonstrated to have qualities for comparable root development shall
be segregated and replaced as subsoil, if the
permit and plan requires that either of these
is necessary or desirable to ensure soil productivity consistent with the approved postmining land use.
(E) Topsoil Substitutes and Supplements.
1. Selected overburden materials may be
substituted for or used as a supplement to
topsoil, if in the permit and the plan it is
determined that the resulting soil medium is
equal to or more suitable for sustaining
revegetation than is the available topsoil and
the substitute material is the best available to
support revegetation. This determination
shall be based on—
A. The results of chemical and physical analyses of overburden and topsoil. These
analyses shall include determinations of pH,
net acidity or alkalinity, phosphorus, potassium, texture class and other analyses as
required in the permit and plan. It may also
be required in the permit and plan that results
of field-site trials or greenhouse tests be used
to demonstrate the feasibility of using these
overburden materials; and
B. Results of analyses, trials and tests
submitted to the director. Certification of trials and tests shall be made by a laboratory
approved by the commission or director, stating that the—
(I) Proposed substitute material is
equal to or more suitable for sustaining the
vegetation than is the available topsoil;
(II) Substitute material is the best
available material to support the vegetation;
and
(III) Trials and tests were conducted using standard testing procedures.
2. Substituted or supplemental material
shall be removed, segregated and replaced in
compliance with the requirements for topsoil
under this section.
(F) Limits on Topsoil Removal Area.
These limits shall be addressed and approved
as required to meet 10 CSR 40-3.040, 10
CSR 40-3.090, 10 CSR 40-6.040 and 10
CSR 40-6.050. Where the removal of vegetative material, topsoil or other materials may
result in erosion which may cause air or
water pollution—
1. The size of the area from which topsoil is removed at any one time shall be limited;
2. The surface soil layer shall be redistributed at a time when the physical and
chemical properties of topsoil can be protected and erosion can be minimized; and
3. Other measures shall be taken as
approved or required in the permit and plan
to control erosion.
(3) Topsoil Storage.
(A) Topsoil and other materials removed
under section (2) of this rule shall be stockpiled only when it is impractical to promptly
redistribute this material on regraded areas.
(B) Stockpiled material shall be selectively
placed on a stable area within the permit
area, not disturbed and protected from wind
and water erosion, unnecessary compaction
and contaminants which lessen the capability
of the materials to support vegetation when
redistributed.
1. Protection measures shall be accomplished either by—
A. An effective cover of nonnoxious
quickgrowing annual and perennial plants,
seeded or planted during the first normal
period after removal for favorable planting
conditions; or
B. Other methods demonstrated in
and approved in the permit and plan to provide equal protection.
2. Unless approved in the permit and
plan, stockpiled topsoil and other materials
shall not be moved until required for redistribution on a regraded area.
(4) Topsoil Redistribution.
(A) After final grading and before the
replacement of topsoil and other materials
segregated in accordance with section (3) of
this rule, regraded land shall be scarified or
otherwise treated as required in the permit
and plan to eliminate slippage surfaces and to
promote root penetration. If the person who
conducts the surface mining activities shows
through appropriate tests, and the commission or director approves, that no harm will
be caused to the topsoil and vegetation, scarification may be conducted after topsoiling.
(B) Topsoil and other material shall be
redistributed in a manner that—
1. Achieves an approximate uniform,
stable thickness consistent with the approved
postmining land uses, contours and surface
water drainage system;
2. Prevents excess compaction and/or
contamination of the topsoil; and
3. Protects the topsoil from wind and
water erosion before and after it is seeded and
planted.
(5) Topsoil Nutrients and Soil Amendments.
Nutrients and soil amendments in the
amounts determined by soil tests shall be
applied to the redistributed surface soil layer,
so that it supports the approved postmining
land use and meets the revegetation requirements of 10 CSR 40-3.120. All soil tests
shall be performed by a qualified laboratory
using standard methods approved in the permit and plan.
AUTHORITY: section 444.530, RSMo 1994.*
Original rule filed Oct. 12, 1979, effective
Feb. 11, 1980. Amended: Filed July 3, 1990,
effective Nov. 30, 1990. Amended: Filed
Sept. 15, 1994, effective April 30, 1995.
*Original authority 1971, amended 1983, 1990, 1993.