10 CSR 40-3.040
Requirements for Protection of the Hydrologic Balance
PURPOSE: This rule sets forth the requirements for protection of the hydrologic balance pursuant to sections 444.810 and
444.885.2(10), RSMo.
PUBLISHER’S NOTE: The secretary of state
has determined that the publication of the
entire text of the material which is incorporated by reference as a portion of this rule
would be unduly cumbersome or expensive.
This material as incorporated by reference in
this rule shall be maintained by the agency at
its headquarters and shall be made available
to the public for inspection and copying at no
more than the actual cost of reproduction.
This note applies only to the reference material. The entire text of the rule is printed here.
(1) General Requirements.
(A) Surface mining activities shall be
planned and conducted to minimize changes
to the prevailing hydrologic balance in both
the mine plan and adjacent areas in order to
prevent long-term adverse changes in that
balance that could result from those activities.
(B) Mining and reclamation activities shall
be conducted to prevent material damage to
the hydrologic balance outside the permit
area.
(C) Changes in water quality and quantity,
in the depth to groundwater and in the location of surface water drainage channels shall
be minimized so that the approved postmining land use of the permit area is not adversely affected.
(D) In no case shall federal and state water
quality statutes, regulations, standards, or
effluent limitations be violated.
(E) Operations shall be conducted to minimize water pollution and, where necessary,
treatment methods shall be used to control
water pollution.
1. Each person who conducts surface
mining activities shall emphasize mining and
reclamation practices that prevent or minimize water pollution. Changes in flow of
drainage shall be used in preference to the
use of water treatment facilities.
2. Acceptable practices to control and
minimize water pollution include, but are not
limited to:
A. Stabilizing disturbed areas through
land shaping;
B. Diverting runoff;
C. Achieving quickly germinating and
growing stands of temporary vegetation;
D. Regulating channel velocity of
water;
E. Lining drainage channels with rock
or vegetation;
F. Mulching;
G. Selectively placing and sealing
acid- and toxic-forming materials; and
H. Selectively placing waste materials
in backfill areas.
3. If the practices listed in paragraph
(1)(E)2. of this rule are not adequate to meet
the requirements of this chapter, the person
who conducts surface mining activities shall
operate and maintain the necessary water
treatment facilities for as long as treatment is
required under this chapter.
(2) Water Quality Standards and Effluent
Limitations.
(A) General Limitations.
1. All surface drainage from the disturbed area, including disturbed areas that
have been graded, seeded, or planted, shall
be passed through a siltation structure or a
series of siltation structures before leaving the
permit area.
2. Siltation structures and other treatment facilities shall be maintained until the
disturbed area has been restored and the vegetation requirements of 10 CSR 40-3.120 are
met and the quality of the untreated drainage
from the disturbed area meets the applicable
state and federal water quality standards and
requirements for the receiving stream.
3. Exemptions may be granted in the
permit and plan from these requirements only
when—
A. The disturbed drainage area within
the total disturbed area is small; and
B. The person who conducts the surface mining activities demonstrates that siltation structures and treatment facilities are not
necessary for drainage from the disturbed
drainage areas to meet the effluent limitations
of the applicable state and federal water quality standards for downstream receiving
waters.
4. For the purpose of this section only,
disturbed area shall not include those areas in
which only diversion ditches, siltation structures, or roads are installed in accordance
with this chapter and the upstream area is not
otherwise disturbed by the person who conducts the surface mining activities.
5. Siltation structures required by this
section shall be constructed in accordance
with section (6) of this rule, in appropriate
locations before beginning any surface mining activities in the drainage area to be affected.
6. Where the siltation structure or series
of siltation structures is used so as to result in
the mixing of drainage from the disturbed
areas with drainage from other areas not disturbed by current surface coal mining and
reclamation operations, the permittee shall
achieve the effluent limitations set forth in the
following for all of the mixed drainage when
it leaves the permit area.
(B) Discharges of water from areas disturbed by surface mining activities shall be
made in compliance with all applicable state
and federal water quality laws and regulations
and with the effluent limitations for coal mining promulgated by the Missouri Clean Water
Commission set forth in 10 CSR 20-7.015
and promulgated by the federal government
set forth in the Federal Water Pollution
Control Act, P.L. 92-500, 92nd Congress.
(C) Adequate facilities shall be installed,
operated, and maintained to treat any water
discharged from the disturbed area so that it
complies with all federal and state laws, regulations, and limitations of this section. If the
pH of water to be discharged from the disturbed area is less than 6.0, an automatic
lime feeder or other automatic neutralization
process approved in the permit and plan shall
be installed, operated, and maintained. The
permit and plan may authorize the use of a
manual system, if it is found that—
1. Flow is infrequent and presents small
and infrequent treatment requirements to
meet applicable standards which do not
require use of an automatic neutralization
process; and
2. Timely and consistent treatment is
ensured.
(3) Diversions and Conveyance of Overland
Flow and Shallow Groundwater Flow and
Ephemeral Streams. Overland flow, including
flow through litter and shallow groundwater
flow from undisturbed areas, and flow in
ephemeral streams, may be diverted away
from disturbed areas by means of temporary
or permanent diversions, if required or
approved in the permit and plan as necessary
to minimize erosion, to reduce the volume of
water to be treated and to prevent or remove
water from contact with acid- or toxic-forming materials. The following requirements
shall be met for all diversions and for all collection drains that are used to transport water
into water treatment facilities and for all
diversions of overland and shallow groundwater flow and ephemeral streams:
(A) Temporary diversions shall be constructed to pass safely the peak runoff from a
precipitation event with a two- (2-) year
recurrence interval or a larger event as specified in the permit and plan;
(B) To protect fills and property and to
avoid danger to public health and safety, permanent diversions shall be constructed to
pass safely the peak runoff from a precipitation event with a ten- (10-) year recurrence
interval or a larger event as specified in the
permit and plan. Permanent diversions shall
be constructed with gently sloping banks that
are stabilized by vegetation. Asphalt, concrete, or other similar linings shall be used
only when approved in the permit and plan to
prevent seepage or to provide stability;
(C) Diversions shall be designed, constructed, and maintained in a manner which
prevents additional contributions of suspended solids to streamflow and to runoff outside
the permit area, to the extent possible using
the best technology currently available.
Appropriate sediment control measures for
these diversions may include, but not be limited to, maintenance of appropriate gradients,
Surface Coal Mining and Related Activities
channel lining revegetation, roughness structures, and detention basins;
(D) No diversion shall be located so as to
increase the potential for landslides. No
diversion shall be constructed on existing
landslides, unless approved in the permit and
plan;
(E) When no longer needed, each temporary diversion shall be removed and the
affected land regraded, topsoiled, and revegetated in accordance with 10 CSR 403.030(4) and (5), 10 CSR 40-3.110, and 10
CSR 40-3.120;
(F) Diversion design shall incorporate the
following:
1. Channel lining shall be designed
using standard engineering practices to pass
safely the design velocities. Riprap shall
comply with the applicable requirements of
10 CSR 40-3.060(2)(B)3., except for sand
and gravel;
2. Freeboard shall be no less than 0.3
feet. Protection shall be provided for transition of flows and for critical areas such as
swales and curves. Where the area protected
is a critical area as determined in the permit
and plan, the design freeboard may be
increased;
3. Energy dissipators shall be installed
when necessary at discharge points, where
diversions intersect with natural streams and
exit velocity of the diversion ditch flow is
greater than that of the receiving stream;
4. Excess excavated material not necessary for diversion channel geometry or
regrading of the channel shall be disposed of
in accordance with 10 CSR 40-3.060;
5. Topsoil shall be handled in compliance with 10 CSR 40-3.030; and
6. Diversions shall not be constructed or
operated to divert water into underground
mines; and
(G) All diversions shall be designed to
minimize adverse impacts to the hydrologic
balance within the permit and adjacent areas,
to prevent material damage outside the permit
area and to assure the safety of the public.
(4) Stream Channel Diversions.
(A) Flow from perennial and intermittent
streams within the permit area may be diverted if the diversions—
1. Are approved in the permit and plan
if the requirements in subsection (18)(A) of
this rule are found;
2. Comply with other requirements of
this chapter and 10 CSR 40-4; and
3. Comply with local, state, and federal
statutes and regulations.
(B) When streamflow is allowed to be
diverted, the stream channel diversion shall
be designed, constructed, and removed in
accordance with the following:
1. The longitudinal profile of the stream,
the channel, and the floodplain shall be
designed and constructed to remain stable
and to prevent, to the extent possible using
the best technology currently available, additional contributions of suspended solids to
streamflow or to runoff outside the permit
area. These contributions shall not be in
excess of requirements of state or federal law.
Erosion control structures such as channel
lining structures shall be used in diversions
only when approved in the permit and plan as
being necessary to control erosion. These
structures shall be approved for permanent
diversions only where they are stable and will
require infrequent maintenance;
2. The combination of channel, bank,
and floodplain configurations shall be adequate to safely pass the peak runoff of a ten-
(10-) year, twenty-four- (24-) hour precipitation event for temporary diversions, a one
hundred- (100-) year, twenty-four- (24-) hour
precipitation event for permanent diversions
or larger events required in the permit and
plan. However, the capacity of the channel
itself should be at least equal to the capacity
of the unmodified stream channel immediately upstream and downstream of the diversion;
and
3. The design and construction of all
stream channel diversions of perennial and
intermittent streams shall be certified by a
qualified registered professional engineer as
meeting the performance standards of this
rule and any design criteria set by the director.
(C) When no longer needed to achieve the
purpose for which they were authorized, all
temporary stream channel diversions shall be
removed and the affected land regraded and
revegetated, in accordance with 10 CSR 403.030(4) and (5), 10 CSR 40-3.110, and 10
CSR 40-3.120. At the time diversions are
removed, downstream water treatment facilities previously protected by the diversion
shall be modified or removed to prevent overtopping or failure of the facilities. This
requirement shall not relieve the person who
conducts the surface mining activities from
maintenance of a water treatment facility otherwise required under this chapter or the permit.
(D) When permanent diversions are constructed or stream channels restored, after
temporary diversions, the operator shall—
1. Restore, enhance where practicable,
or maintain natural riparian vegetation on the
banks of the stream;
2. Establish or restore the stream to its
natural meandering shape of an environmentally acceptable gradient, as determined in
the permit and plan; and
3. Establish or restore the stream to a
longitudinal profile and cross-section, including aquatic habitats (usually a pattern of riffles, pools and drops rather than uniform
depth) that approximate premining stream
channel characteristics.
(5) Sediment Control Measures.
(A) Appropriate sediment control measures shall be designed, constructed, and
maintained using the best technology currently available to—
1. Prevent, to the extent possible, additional contributions of sediment to streamflow or to runoff outside the permit area;
2. Meet the more stringent of applicable
state or federal effluent limitations; and
3. Minimize erosion to the extent possible.
(B) Sediment control measures include
practices carried out within, and adjacent to,
the disturbed area. The sedimentation storage
capacity of practices in and downstream from
the disturbed area shall reflect the degree to
which successful mining and reclamation
techniques are applied to reduce erosion and
control sediment. Sediment control measures
consist of the utilization of proper mining and
reclamation methods and sediment control
practices, singly or in combination. Sediment
control methods include:
1. Disturbing the smallest practicable
area at any one (1) time during the mining
operation through progressive backfilling,
grading and prompt revegetation as required
in 10 CSR 40-3.120(1)(B);
2. Stabilizing the backfill material to
promote a reduction in the rate and volume of
runoff, in accordance with the requirements
of 10 CSR 40-3.110(1);
3. Retaining sediment within disturbed
areas;
4. Diverting runoff away from disturbed
areas;
5. Diverting runoff using protected
channels or pipes through disturbed areas so
as not to cause additional erosion;
6. Using straw dikes, riprap, check
dams, mulches, vegetative sediment filters,
dugout ponds, and other measures that reduce
overland flow velocity, reduce runoff volume,
or trap sediment; and
7. Treating with chemicals.
(6) Siltation Structures.
(A) General Requirements. Siltation structures shall be used individually or in series
and shall—
1. Be constructed before any disturbance
of the undisturbed area to be drained into the
structure;
2. Be located as near as possible to the
disturbed area and out of perennial streams,
unless approved in the permit and plan; and
3. Meet all the criteria of this section.
(B) Sediment Storage Volume. Siltation
structures shall provide adequate sediment
storage volume.
(C) Detention Time. Siltation structures
shall provide the required theoretical detention time for the water inflow or runoff entering the pond from a ten- (10-) year, twentyfour- (24-) hour precipitation event (design
event).
(D) Dewatering. The water storage resulting from inflow shall be removed by a nonclogging dewatering device that has been
designed, constructed, and maintained in
accordance with subsection (6)(C) of this rule
or a conduit spillway approved in the permit
and plan. The dewatering device shall not be
located at a lower elevation than the maximum elevation of the sedimentation storage
volume.
(E) Each person who conducts surface
mining activities shall design, construct, and
maintain siltation structures to prevent shortcircuiting to the extent possible.
(F) The design, construction, and maintenance of a siltation structure or other sediment control measures in accordance with
this section shall not relieve the person from
compliance with applicable effluent limitations as contained in section (2) of this rule.
(G) There shall be no outflow through the
emergency spillway during the passage of the
runoff resulting from the ten- (10-) year,
twenty-four- (24-) hour precipitation event or
lesser events through the siltation structure.
(H) Siltation structures shall be designed,
constructed, and maintained to provide periodic sediment removal sufficient to maintain
adequate volume for the design event.
(I) An appropriate combination of principal and emergency spillways shall be provided to safely discharge the runoff from a twenty-five- (25-) year, twenty-four- (24-) hour
precipitation event or larger event required in
the permit and plan. The elevation of the
crest of the emergency spillway shall be a
minimum of one foot (1') above the crest of
the principal spillway. Emergency spillway
grades and allowable velocities shall be
approved in the permit and plan.
(J) The minimum elevation at the top of the
settled embankment shall be one foot (1')
above the water surface in the pond with the
emergency spillway flowing at design depth.
For embankments subject to settlement, this
one foot (1') minimum elevation requirement
shall apply at all times, including the period
after settlement.
(K) The constructed height of the dam
shall be increased a minimum of five percent
(5%) over the design height to allow for settlement, unless it has been demonstrated in
the permit and plan that the material used and
the design will ensure against all settlement.
(L) The minimum top width of the
embankment shall not be less than the quotient of (H+35)/5, where H is the height, in
feet, of the embankment as measured from
the upstream toe of the embankment.
(M) The combined upstream and downstream side slopes of the settled embankment
shall not be less than 1v:5h (20%), with neither slope steeper than 1v:2h (50%). Slopes
shall be designed to be stable in all cases,
even if flatter side slopes are required.
(N) The embankment foundation area shall
be cleared of all organic matter, all surfaces
sloped to no steeper than 1v:1h (100%) and
the entire foundation surface scarified.
(O) The fill material shall be free of sod,
large roots, other large vegetative matter, and
frozen soil, and in no case shall coal-processing waste be used.
(P) The placing and spreading of fill material shall be started at the lowest part of the
foundation. The fill shall be brought up in
horizontal layers of a thickness as is required
to facilitate compaction and meet the design
requirements of this section. Compaction
shall be conducted as specified in the design
approved in the permit and plan.
(Q) If a siltation structure has an embankment that is more than twenty feet (20') in
height, as measured from the upstream toe of
the embankment to the crest of the open
channel emergency spillway, unless the emergency spillway is a pipe, where it is measured
to the lowest point in the toe of the embankment, or has both an embankment that is five
feet (5') or more in height, as measured from
the upstream toe of the embankment to the
crest of the open channel emergency spillway
and a storage volume of twenty (20) acre-feet
or more above the upstream toe of the
embankment,
the
following
additional
requirements shall be met:
1. An appropriate combination of principal and emergency spillways shall be provided to discharge safely the runoff resulting
from a one hundred- (100-) year, twentyfour- (24-) hour precipitation event or a larger event required in the permit and plan;
2. The embankment shall be designed
and constructed with a static safety factor of
at least one and five-tenths (1.5) or a higher
safety factor as required in the permit and
plan to ensure stability;
3. Appropriate barriers shall be provided to control seepage along conduits that
extend through the embankment; and
4. The criteria of the Mine Safety and
Health Administration (MSHA) as published
in 30 CFR 77.216 shall be met.
(R) Each structure shall be designed and
inspected during construction under the
supervision of, and certified after construction by, a registered professional engineer.
(S) The entire embankment including the
surrounding areas disturbed by construction
shall be stabilized with respect to erosion by
a vegetative cover or other means immediately after the embankment is completed. The
active upstream face of the embankment
where water will be impounded may be
riprapped or otherwise stabilized. Areas in
which the vegetation is not successful or
where rills and gullies develop shall be
repaired and revegetated in accordance with
10 CSR 40-3.110(6).
(T) Impoundments meeting the Class B or
C criteria for dams in the U.S. Department of
Agriculture, Soil Conservation Service (now
renamed as the Natural Resources Conservation Service) Technical Release No. 60
(210-VI, TR-60, Revised Oct. 1985), entitled
“Earth Dams and Reservoirs,” hereafter in
these rules referred to as TR-60, or the size
or other criteria of 30 CFR 77.216 must be
examined in accordance with 30 CFR
77.216-3. Impoundments which do not meet
the above criteria shall be examined at least
quarterly by a qualified person designated by
the operator for the appearance of structural
weakness and other hazardous conditions.
(U) Siltation structures shall not be
removed until removal is authorized and until
the disturbed area has been restored and the
vegetation requirements of 10 CSR 40-3.120
are met and the drainage entering the structure has met the applicable state and federal
water quality requirements for the receiving
stream. In no case shall the structure be
removed sooner than two (2) years after the
last augmented seeding. When the siltation
structure is removed, the affected land shall
be regraded and revegetated in accordance
with 10 CSR 40-3.110 and 10 CSR 40-3.120,
unless the structure has been approved in the
permit and plan for retention as being compatible with the approved postmining land use
under 10 CSR 40-3.130. If approved in the
permit and plan, the siltation structure shall
meet all the requirements for permanent
impoundments of sections (10) and (17).
(7) Other Treatment Facilities.
(A) Other treatment facilities shall be
designed to treat the ten- (10-) year, twentyfour- (24-) hour precipitation event unless a
Surface Coal Mining and Related Activities
lesser design event is approved by the director
based on terrain, climate, other site-specific
conditions, and a demonstration by the operator that the effluent limitations of 30 CFR
816.42 will be met.
(B) Other treatment facilities shall be
designed in accordance with the applicable
requirements of section (6) of this rule.
(8) Discharge Structures. Discharge from siltation structures, permanent and temporary
impoundments, coal processing waste dams
and embankments, and diversions shall be
controlled by energy dissipators, riprap channels, and other devices, where necessary, to
reduce erosion, to prevent deepening or
enlargement of stream channels, and to minimize disturbance of the hydrologic balance.
Discharge structures shall be designed
according to standard engineering design procedures.
(9) Acid- and Toxic-Forming Materials.
Drainage from acid- and toxic-forming materials into ground and surface water shall be
avoided by—
(A) Identifying and burying or treating, or
both, when necessary, materials which may
adversely affect water quality or be detrimental to vegetation or to public health and safety
if not buried or treated, or both;
(B) Preventing water from coming into
contact with acid- and toxic-forming materials in accordance with 10 CSR 40-3.110(3)
and other measures as required in the permit
and plan; and
(C) Burying or otherwise treating all acidor toxic-forming materials within thirty (30)
days after it is first exposed on the mine site,
or within a lesser period required in the permit and plan. Temporary storage of the materials may be approved in the permit and plan
upon a finding that burial or treatment within
thirty (30) days is not feasible and will not
result in any materials risk of water pollution
or other environmental damage. Storage shall
be limited to the period until burial or treatment, or both, first becomes feasible. Acidor toxic-forming materials to be stored shall
be placed on impermeable material and protected from erosion and contact with surface
water.
(10) Permanent and Temporary Impoundment.
(A) Impoundments meeting the criteria of
30 CFR 77.216(a) shall comply with the
requirements of 30 CFR 77.216 and this section. The plan required to be submitted to the
district manager of the MSHA under 30 CFR
77.216 shall also be submitted to the director
as part of the permit application. Furthermore, impoundments meeting the Class B or
C criteria for dams in TR-60 shall comply
with the “Minimum Emergency Spillway
Hydrologic Criteria” table in TR-60 and the
requirements of this section.
(B) Permanent impoundments are prohibited unless authorized in the permit and plan
upon the basis of the following demonstration:
1. The quality of the impounded water
shall be suitable on a permanent basis for its
intended use and discharge of water from the
impoundment shall not degrade the quality of
receiving waters to less than the water quality
standards established pursuant to applicable
state and federal laws;
2. The level of water shall be sufficiently stable to support the intended use;
3. Adequate safety and access to the
impounded water shall be provided for proposed water users;
4. Water impoundments shall not result
in the diminution of the quality or quantity of
water used by adjacent or surrounding
landowners for agricultural, industrial, recreational, or domestic uses;
5. The design, construction, and maintenance of structures shall achieve the minimum design requirements applicable to structures constructed and maintained under the
Watershed Protection and Flood Prevention
Act, P. L. 83-566 (U.S.C. 1006). Requirements for impoundments that meet the size or
other criteria of the MSHA, 30 CFR
77.216(a) are contained in United States Soil
Conservation Service Technical Release No.
60, Earth Dams and Reservoirs, July 2005,
incorporated by reference and published by
the USDA, NRCS, Office of the Chief, 1400
Independence Ave., SW, Room 5105-A,
Washington, DC 20250. This rule does not
incorporate any later amendments or additions
to
this
incorporated
material.
Requirements for impoundments that do not
meet the size or other criteria contained in 30
CFR 77.216(a) are contained in United States
Natural Resources Conservation Service,
Conservation Practice Standard, POND, No.
CODE 378, January 2004, incorporated by
reference and published by the Missouri
NRCS State Office, Parkade Center, Suite
250, 601 Business Loop 70 West, Columbia,
MO 65203-2546. This rule does not incorporate any later amendments or additions to this
incorporated material;
6. The size of the impoundment is adequate for its intended purposes; and
7. The impoundment will be suitable for
the approved postmining land use.
(C) Temporary impoundments of water in
which the water is impounded by a dam shall
meet the requirements of subsections (6)(F)–
(V) of this rule.
(D) Excavations that will impound water
during or after the mining operation shall
have perimeter slopes that are stable and shall
not be steeper than 1v:2h (50%). Where surface runoff enters the impoundment area, the
side slope shall be protected against erosion.
(E) Slope protection shall be provided to
minimize surface erosion at the site and protect against sudden drawdown. Sediment control measures shall be required where necessary to reduce the sediment leaving the site.
(F) All embankments of temporary and
permanent impoundments and the surrounding areas and diversion ditches disturbed or
created by construction, shall be graded, fertilized, seeded, and mulched to comply with
the requirements of 10 CSR 40-3.120 immediately after the embankment is completed,
provided that the active, upstream face of the
embankment where water will be impounded
may be riprapped or otherwise stabilized.
Areas in which the vegetation is not successful or where rills and gullies develop shall be
repaired and revegetated to comply with the
requirements of 10 CSR 40-3.110(6) and 10
CSR 40-3.120.
(G) All dams and embankments shall be
routinely inspected by a qualified registered
professional engineer or by someone under
the supervision of a qualified registered professional engineer. The professional engineer
or specialist shall be experienced in the
design and construction of impoundments.
Inspections shall be made regularly during
construction, upon completion of construction and at least yearly until removal of the
structure or release of the performance bond.
(H) All dams and embankments shall be
routinely maintained during the mining operations. Vegetative growth shall be cut where
necessary to facilitate inspection and repairs.
Ditches and spillways shall be cleaned. Any
combustible material present on the surface,
other than material such as mulch or dry vegetation used for surface stability, shall be
removed and all other appropriate maintenance procedures followed.
(I) All dams and embankments subject to
10 CSR 40 shall be certified by a qualified
registered professional engineer during construction immediately after construction and
annually after that as having been constructed, maintained, or both, to comply with the
requirements of 10 CSR 40. All coal-processing waste dams and embankments covered by
10 CSR 40-3.080(9)–(11) shall be certified
by a qualified registered professional engineer. Certification reports shall be provided
certifying that the impoundment has been
constructed and maintained as designed and
in accordance with the approved plan and this
chapter, shall include a discussion on any
appearance of instability, structural weakness, or other hazardous condition and shall
include statements on:
1. Existing and required monitoring procedures and instrumentation;
2. The design depth and elevation of any
impounded waters at the time of the initial
certification report or the average and maximum depth and elevations of any impounded
waters over the past year for the annual certification reports;
3. Existing storage capacity of the dam
or embankment;
4. Any fires occurring in the construction material up to the date of the initial certification or over the past year for the annual
certification reports; and
5. Any other aspects of the dam or
embankment affecting stability, including
structural weakness, erosion, and other hazardous conditions.
(J) If any examination or inspection discloses that a potential hazard exists, the person who examined the impoundment shall
promptly inform the director of the finding
and of the emergency procedures formulated
for public protection and remedial action. If
adequate procedures cannot be formulated or
implemented, the director shall be notified
immediately. The director shall then notify
the appropriate agencies that other emergency
procedures are required to protect the public.
(K) Plans for any enlargement, reduction
in size, reconstruction, or other modification
of dams or impoundments shall be submitted
to the director and shall comply with the
requirements of this section. Except where a
modification is required to eliminate an
emergency condition constituting a hazard to
public health, safety, or the environment, the
plans will be approved before modification
begins.
(L) Stability.
1. An impoundment meeting the Class B
or C criteria for dams in TR-60, or the size
or other criteria of 30 CFR 77.216(a) shall
have a minimum static safety factor of 1.5 for
a normal pool with steady state seepage saturation conditions, and a seismic safety factor
of at least 1.2.
2. Impoundments not included in paragraph 40-3.040(10)(L)1. of this section,
except for a coal mine waste impounding
structure, shall have a minimum static safety
factor of 1.3 for a normal pool with steady
state seepage saturation conditions or meet
the requirements of Natural Resources
Conservation Service, Conservation Practice
Standard, POND No. CODE 378, December 1998, and be less that twenty feet (20')
feet in height.
(M) Freeboard. Impoundments shall have
adequate freeboard to resist overtopping by
waves and by sudden increases in storage volume. Impoundments meeting the Class B or
C criteria for dams in TR-60 shall comply
with the freeboard hydrograph criteria in the
“Minimum Emergency Spillway Hydrologic
Criteria” table in TR-60.
(N) Foundation.
1. Foundations and abutments for an
impounding structure shall be stable during
all phases of construction and operation and
shall be designed based on adequate and
accurate information on the foundation conditions. For an impoundment meeting the Class
B or C criteria for dams in TR-60, or the size
or other criteria of 30 CFR 77.216(a), foundation investigation, as well as any necessary
laboratory testing of foundation material,
shall be performed to determine the design
requirements for foundation stability.
2. All vegetative and organic materials
shall be removed and foundations excavated
and prepared to resist failure. Cutoff trenches
shall be installed if necessary to ensure stability.
(O) Spillways. An impoundment shall have
either a combination of principal and emergency spillways, a single spillway configured
as specified in 10 CSR 40-3.040(10)(O)1. of
this section, or no spillways as specified in 10
CSR 40-3.040(10)(O)3. of this section. The
impoundment shall be designed and constructed to safely pass or contain the applicable design precipitation event specified in 10
CSR 40-3.040(10)(O)2. or 3. of this section.
1. A single open-channel spillway can
be utilized if it is—
A. Of nonerodible construction and
designed to carry sustained flows; or
B. Earth- or grass-lined and designed
to carry short-term, infrequent flows at nonerosive velocities where sustained flows are
not expected.
2. Except as specified in 10 CSR 403.040(10)(O)3. of this section, the required
design precipitation event for an impoundment meeting the spillway requirements of 10
CSR 40-3.040(10)(O) of this section is—
A. For an impoundment meeting the
Class B or C criteria for dams in TR-60, the
emergency spillway hydrograph criteria in the
“Minimum Emergency Spillway Hydrologic
Criteria” table in TR-60;
B. For an impoundment meeting or
exceeding the size or other criteria of 30 CFR
77.216(a), a one hundred- (100-) year twenty-four- (24-) hour event or greater as specified by the director or commission; or
C. For an impoundment not included
in 10 CSR 40-3.040(10)(O)2.A. and B. of
this section, as specified in Table 3 of the
Natural Resources Conservation Service,
Conservation Practice Standard, POND, No.
CODE 378, December 1998.
3. A temporary impoundment that relies
solely on storage capacity to control the
runoff from the design precipitation event
may be utilized with no spillway when it is
demonstrated by the operator and certified by
a qualified registered professional engineer
that the impoundment will safely contain the
design precipitation event, and that the stored
water will be safely removed in accordance
with current, prudent, engineering practices.
Such an impoundment must be located where
failure would not be expected to cause loss of
life or serious property damage.
A.
Impoundments
meeting
the
Natural Resources Conservation Service
Class B or C criteria for dams in TR-60, or
the size or other criteria of 30 CFR 77.216(a)
shall be designed to safely contain the runoff
of the probable maximum precipitation
(PMP) of a six- (6-) hour event.
B. Impoundments not included in subparagraph 10 CSR 40-3.040(10)(O)3.A. of
this section shall be designed to control the
precipitation of the one hundred- (100-) year
twenty-four- (24-) hour event.
(11) Groundwater Protection.
(A) Backfilled materials shall be placed so
as to minimize contamination of groundwater
systems with acid, toxic, or otherwise harmful mine drainage to minimize adverse effects
of mining on groundwater systems outside the
permit area, and to support approved postmining land uses.
(B) To control the effects of mine drainage,
pits, cuts, and other mine excavation or disturbances shall be located, designed, constructed, and utilized in a manner as to prevent or control discharge of acid, toxic, or
otherwise harmful mine drainage waters into
groundwater systems and to prevent adverse
impacts on these groundwater systems or on
approved postmining land uses.
(12) Protection of Groundwater Recharge
Capacity. Surface mining activities shall be
conducted in a manner that facilitates reclamation which will restore approximate premining recharge capacity through restoration
of the capability of the reclaimed areas as a
whole, excluding coal-processing waste and
underground development waste disposal
areas and fills, to transmit water to the
groundwater system. The recharge capacity
shall be restored to a condition which—
(A) Supports the approved postmining land
use;
Surface Coal Mining and Related Activities
(B) Minimizes disturbances to the prevailing hydrologic balance in the mine plan area
and in adjacent areas; and
(C) Provides a rate of recharge that approximates the premining recharge rate.
(13) Surface Water and Groundwater
Monitoring.
(A) Groundwater.
1. Groundwater levels, infiltration rates,
subsurface flow and storage characteristics,
and the quality of groundwater shall be monitored in a manner approved in the permit and
plan, to determine the effects of surface mining activities on the recharge capacity of
reclaimed lands and on the quantity and quality of water in groundwater systems in the
mine plan and adjacent areas.
A. Groundwater monitoring data shall
be submitted every three (3) months to the
director or more frequently as prescribed by
the director. Monitoring reports shall include
analytical results from each sample taken
during the reporting period. When the analysis of any groundwater sample indicates noncompliance with the permit conditions, the
operator shall promptly notify the director
and take remedial measures provided for in
10 CSR 40-6.050(9) and 10 CSR 406.070(14).
B. Groundwater monitoring shall proceed through mining and continue during
reclamation until bond release. Consistent
with the procedures of 10 CSR 40-6.090, the
director may modify the monitoring requirements, including the parameters covered and
the sampling frequency, if the operator
demonstrates, using the monitoring data
obtained under this paragraph, that—
(I) The operation has minimized
disturbance to the prevailing hydrologic balance in the permit and adjacent areas and prevented material damage to the hydrologic balance outside the permit area; water quantity
and quality are suitable to support approved
postmining land uses and the water rights of
other users have been protected or replaced;
or
(II) Monitoring is no longer necessary to achieve the purposes set forth in the
monitoring plan approved under 10 CSR 406.050(9)(C).
2. When surface mining activities may
affect the groundwater systems serving as
aquifers which significantly ensure the hydrologic balance of water use on or off the mine
plan area, groundwater levels and groundwater quality shall be periodically monitored.
Monitoring shall include measurements from
a sufficient number of wells and mineralogical and chemical analyses of aquifer, overburden, and spoil that are adequate to reflect
changes in groundwater quantity and quality
resulting from those activities. Monitoring
shall be adequate to plan for modification of
surface mining activities, if necessary, to
minimize disturbance of the prevailing hydrologic balance.
3. As specified and approved in the permit and plan, the person who conducts surface mining activities shall conduct additional
hydrologic tests, including drilling, infiltration tests, and aquifer tests and shall submit
the results to the director, to demonstrate
compliance with sections (11)–(13) of this
rule.
(B) Surface Water.
1. Surface water monitoring shall be
conducted in accordance with the monitoring
program submitted under 10 CSR 406.050(9)(C)4. and approved in the permit and
plan. The permit and plan shall set forth the
nature of data, frequency of collection, and
reporting requirements. Monitoring shall—
A. Be adequate to accurately measure
and record water quantity and quality of the
discharges from the permit area;
B. Be reported when analytical results
of the sample collections indicate noncompliance with a permit condition or applicable
standard; the person who conducts the surface mining activities shall notify the director
within five (5) days. Where a National
Pollutant Discharge Elimination System
(NPDES) permit effluent limitation noncompliance has occurred, the person who conducts surface mining activities shall forward
the analytic results concurrently with the
written notice of noncompliance; and
C. Result in quarterly reports to the
director, to include analytical results from
each sample taken during the quarter. Any
sample results which indicate a permit violation will be immediately reported to the
director as provided for in 10 CSR 406.050(9) and 10 CSR 40-6.120(5). In those
cases where the discharge for which water
monitoring reports are required is also subject to regulation by an NPDES permit issued
under the Clean Water Act of 1977 (30
U.S.C. Sections 1251–1378) and where the
permit includes provisions for equivalent
reporting requirements and requires filing of
water monitoring reports within ninety (90)
days or less of sample collection, the following alternative procedure shall be used. The
person who conducts the surface mining
activities shall submit to the director on the
same time schedule as required by the
NPDES permit or within ninety (90) days following sample collection, whichever is earlier, either:
(I) A copy of the completed reporting form filed to meet NPDES permit
requirements; or
(II) A letter identifying the state or
federal government official with whom the
reporting form was filed to meet NPDES permit requirements and the date of filing.
2. After disturbed areas have been
regraded and stabilized according to this
chapter, the person who conducts surface
mining activities shall monitor surface water
flow and quality. Data from this monitoring
may be used to demonstrate that the quality
and quantity of runoff without treatment is
consistent with the requirements of this chapter to minimize disturbance to the prevailing
hydrologic balance and to attain the approved
postmining land use. These data may also
provide a basis for approval by the commission or director for removal of water quality
or flow control systems.
3. Equipment, structures and other
devices necessary to accurately measure and
sample the quality and quantity of surface
water discharges from the disturbed area shall
be properly installed, maintained, and operated and shall be removed when no longer
required.
(14) Transfer of Wells.
(A) An exploratory or monitoring well
may only be transferred by the person who
conducts surface mining activities for further
use as a water well with the prior approval of
the commission or director. That person and
the surface owner of the lands where the well
is located shall jointly submit a written
request to the director for that approval.
(B) Upon an approved transfer of a well,
the transferee shall—
1. Assume primary liability for damages
to persons or property from the well;
2. Plug the well when necessary, but in
no case later than abandonment of the well;
and
3. Assume primary responsibility for
compliance with 10 CSR 40-3.020 and those
of the Wellhead Protection Section, Division
of Geology and Land Survey, at 10 CSR 23
Chapter 3 with respect to the well.
(C) Upon an approved transfer of a well,
the transferor shall be secondarily liable for
the transferee’s obligations under subsection
(13)(B) of this rule, until release of the bond
or other equivalent guarantee required by 10
CSR 40-7 for the area in which the well is
located.
(15) Water Rights and Replacement. Any person who conducts surface mining activities
shall replace the water supply of an owner of
interest in real property who obtains all or part
of his/her supply of water for domestic, agricultural, industrial, or other legitimate use
from an underground or surface source,
where the water supply has been affected by
contamination, diminution, or interruption
proximately resulting from the surface mining activities.
(16) Discharge of Water into an Underground
Mine. Surface water shall not be diverted or
otherwise discharged into underground mine
workings, unless allowed by section 577.155,
RSMo, and the person who conducts the surface mining activities demonstrates in the
permit and plan application that this will—
(A) Abate water pollution or otherwise
eliminate public hazards resulting from surface mining activities;
(B) Be discharged as a controlled flow,
meeting the effluent limitations of section (2)
of this rule for pH and total suspended solids;
(C) Not cause, result in, or contribute to,
in any event, a violation of applicable water
quality standards or effluent limitations by
discharging water from underground mines to
surface waters;
(D) Minimize disturbance to the hydrologic balance; and
(E) Meet the approval of the MSHA.
(17) Postmining Rehabilitation of Siltation
Structures, Diversions, Impoundments, and
Treatment Facilities. Before abandoning the
permit area, the person who conducts the surface mining activities shall renovate all permanent siltation structures, diversions,
impoundments, and treatment facilities to
meet criteria specified in the detailed design
plan for the permanent structures and
impoundments.
(18) Stream Buffer Zones.
(A) No land within one hundred feet (100')
of a perennial stream or an intermittent
stream shall be disturbed by surface mining
activities, unless the director specifically
authorizes surface mining activities closer to,
or through, a perennial stream. The director
may authorize these activities only upon finding that—
1. Surface mining activities will not
cause or contribute suspended solids to
stream flow or runoff outside the permit area
in excess of the requirements established by
the Missouri Clean Water Commission,
Department of Natural Resources, set forth in
10 CSR 20-7.015 and promulgated by the
federal government set forth in the Federal
Water Pollution Control Act P.L. 92-500 and
all modifications to these laws and regulations;
2. Surface mining activities will not
adversely affect the water quantity and quality or other environmental resources of the
stream; and
3. If there will be a temporary or permanent stream channel diversion, it will comply
with section (4).
(B) The area not to be disturbed shall be
designated as a buffer zone, and the operator
shall mark it as specified in 10 CSR 403.010.
AUTHORITY: sections 444.530 and 444.810,
RSMo 2000.* Original rule filed Oct. 12,
1979, effective Feb. 11, 1980. Amended:
Filed April 14, 1980, effective Aug. 11, 1980.
Amended: Filed Feb. 9, 1981, effective July
11, 1981. Amended: Filed April 2, 1986,
effective July 26, 1986. Amended: Filed Sept.
15, 1988, effective Jan. 15, 1989. Amended:
Filed July 3, 1990, effective Nov. 30, 1990.
Amended: Filed May 15, 1992, effective Jan.
15, 1993. Amended: Filed Sept. 15, 1994,
effective April 30, 1995. Amended: Filed
March 21, 2000, effective Oct. 30, 2000.
Amended: Filed Dec. 17, 2012, effective July
30, 2013.
*Original authority: 444.530, RSMo 1971, amended 1983,
1990, 1993, 1995; and 444.810, RSMo 1979, amended
1983, 1993, 1995.