10 CSR 40-3.080
Requirements for the Disposal of Coal Processing Waste
PURPOSE: This rule sets forth the requirements for disposal of coal processing waste
pursuant to sections 444.810, 444.855.2(13)
and (22) and 444.860.2(5), RSMo.
Editor’s Note: The secretary of state has
determined that the publication of this rule in
its entirety would be unduly cumbersome or
expensive. The entire text of the rule has been
filed with the secretary of state. AASHTO
T99-74 is incorporated by reference as it
exists on the date of adoption of this rule. The
entire text of this rule may be found at the
headquarters of the agency and is available to
any interested person at a cost established by
state law.
(1) General Requirements.
(A) All coal processing waste disposed of
in an area other than the mine workings or
excavations shall be hauled or conveyed and
placed for final placement in new or existing
disposal areas approved in the permit and
plan for this purpose. These areas shall be
within a permit area. The disposal area shall
be designed, constructed and maintained—
1. In accordance with 10 CSR 403.060(1) and (2) and sections (1)–(7) of this
rule; and
2. To prevent combustion.
(B) Coal processing waste materials from
activities located outside a permit area, such
as those activities at other mines or abandoned mine waste piles, may be disposed of
in the permit area only if approved in the permit and plan. Approval shall be based on a
showing by the person who conducts surface
mining activities in the permit area, using
hydrologic, geotechnical, physical and chemical analysis, that disposal of these materials
does not—
1. Adversely affect water quality, water
flow or vegetation;
2. Create public health hazards; or
3. Cause instability in the disposal
areas.
(C) Refuse piles shall meet the requirements of 10 CSR 40-3.080, 30 CFR 77.214
and 30 CFR 77.215.
(2) Site Inspection.
(A) All coal processing waste banks shall
be inspected, on behalf of the person conducting surface mining activities, by a qualified registered professional engineer or other
qualified professional specialist under the
direction of the professional engineer
approved in the permit and plan. The professional engineer or specialist shall be experienced in the construction of similar earth and
waste structures.
1. Inspections shall occur at least quarterly, beginning within seven (7) days after
preparation of the disposal area begins. The
permit and plan may require more frequent
inspections based upon an evaluation of the
potential danger to the health or safety of the
public and the potential harm to land, air and
water resources. Inspections may terminate
when the coal processing waste bank has
been graded, covered in accordance with section (4) of this rule, topsoil has been distributed on the bank in accordance with 10
CSR 40-3.030(4), or at a later time as the
permit and plan may require.
2. Inspections shall include observations
and tests as may be necessary to evaluate the
potential hazard to human life and property,
to ensure that all organic material and topsoil
have been removed and that proper construction and maintenance are occurring in accordance with the plan submitted under 10 CSR
40-6.050(11) and approved in the permit and
plan.
3. The engineer or other approved
inspector shall consider steepness of slopes,
seepage and other visible factors which could
indicate potential failure, and the results of
failure with respect to the threat to human life
and property.
4. The certified report on the drainage
system and protective filters shall include
color photographs taken during and after construction, but before underdrains are covered
with coal mine waste. If the underdrain system is constructed in phases, each phase shall
be certified separately. The photographs
accompanying each certified report shall be
taken in adequate size and number with
enough terrain or other physical features of
the site shown to provide a relative scale to
the photographs and to specifically and clearly identify the site.
5. Copies of the inspection findings shall
be maintained at the mine site.
(B) If any inspection discloses that a potential hazard exists, the director shall be
promptly informed of the finding and of the
emergency procedures formulated for public
protection and remedial action. If adequate
procedures cannot be formulated or implemented, the director shall be notified immediately. The director shall then notify the
appropriate emergency agencies that other
emergency procedures are required to protect
the public from the coal processing waste
area.
(3) Water Control Measures.
(A) Unless the operator satisfactorily
demonstrates to the director that a subdrainage system is not required to ensure the structural integrity of a coal processing waste bank
and the protection of the surface water and
groundwater quality in the immediate vicinity
of the disposal area, a properly designed
subdrainage system shall be provided, which
shall—
1. Intercept all groundwater sources;
2. Be protected by an adequate filter;
and
3. Be covered so as to protect against the
entrance of surface water or leachate from the
coal processing waste.
(B) All surface drainage from the area
above the coal processing waste bank and
from the crest and face of the waste disposal
area shall be diverted, in accordance with 10
CSR 40-3.060(2)(D).
(C) Slope protection shall be provided to
minimize surface erosion at the site. All disturbed areas, including diversion ditches that
are not riprapped, shall be vegetated upon
completion of construction.
(D) All water discharged from a coal processing waste bank shall comply with 10 CSR
40-3.040(1), (2), (5), (6) and (16).
(4) Construction Requirements.
(A) The disposal facility shall be designed
using current, prudent engineering practices
and shall meet any design criteria established
by the director. A qualified registered professional engineer experienced in the design of
similar earth and waste structures shall certify the design of the disposal facilities.
(B) Coal processing waste banks shall be
constructed in compliance with 10 CSR 403.060(1) and (2), except to the extent that the
requirements of those sections are covered in
this section.
(C) Coal processing waste banks shall have
a minimum static safety factor of one and five
tenths (1.5).
(D) Compaction requirements during construction or modification of all coal processing waste banks shall meet the requirements
of this subsection, instead of those specified
in 10 CSR 40-3.060(2)(C). The coal processing waste shall be—
1. Spread in layers no more than twentyfour inches (24") in thickness; and
2. Compacted to attain ninety percent
(90%) of the maximum dry density to prevent
spontaneous combustion and to provide the
strength required for stability of the coal processing waste bank. Dry densities shall be
determined in accordance with the American
Association of State Highway and Trans -
portation Officials (AASHTO) Specifications
T99-74 (Twelfth Edition) (July 1978) or an
equivalent method;
(E) Following grading of the coal processing waste bank, the site shall be covered with
a minimum of four feet (4') of the best available nontoxic and noncombustible material,
in accordance with 10 CSR 40-3.030(2)(E),
and in a manner that does not impede flow
from subdrainage systems. The coal processing waste bank shall be revegetated in accordance with 10 CSR 40-3.120(1)–(7). The
permit or plan may allow less than four feet
(4') of cover material based on physical and
chemical analyses which show that the
requirements of 10 CSR 40-3.120(1)–(7) will
be met.
(5) Burning. Coal processing waste fires shall
be extinguished by the person who conducts
the surface mining activities, in accordance
with a plan allowed by the permit and plan
and approved by the Mine Safety and Health
Administration (MSHA). The plan shall contain, at a minimum, provisions to ensure that
only those persons authorized by the operator
and who have an understanding of the procedures to be used shall be involved in the
extinguishing operations.
(6) Burned Waste Utilization. Before any
burned coal processing waste, other materials
or refuse is removed from a disposal area,
approval shall be obtained from the director.
A plan for the method of removal, with maps
and appropriate drawings to illustrate the proposed sequence of the operation and method
of compliance with this chapter, shall be submitted to the director. Consideration shall be
given in the plan to potential hazards, which
may be created by removal, to persons working or living in the vicinity of the structure.
The plan shall be certified by a qualified registered professional engineer.
(7) Return to Underground Workings. Solid
coal processing waste may be returned to
underground mine workings only in accordance with the waste disposal program
approved in the permit and plan and the
MSHA under 10 CSR 40-6.120(16).
(8) Disposal of Noncoal Wastes.
(A) Noncoal wastes including, but not limited to, grease, lubricants, paints, flammable
liquids, garbage, abandoned mining machinery, lumber and other combustibles generated
during surface mining activities shall be
placed and stored in a controlled manner in a
designated
portion of the permit area.
Placement and storage shall ensure that
leachate and surface runoff do not degrade
surface or ground water, fires are prevented
and that the area remains stable and suitable
for reclamation and revegetation compatible
with the natural surroundings.
(B) Final disposal of noncoal wastes should
be in accordance with all applicable requirements of sections 260.200–260.430, RSMo
and any other federal, state and local law
applicable to disposal. The place of final disposal of noncoal waste, if in the permit area,
shall be designated in the permit. Permit area
disposal sites shall be designed and constructed with appropriate water barriers on the bottom and sides of the designated site. Wastes
shall be routinely compacted and covered to
prevent combustion and windborne waste.
When the disposal is completed, a minimum
of two feet (2') of soil cover shall be placed
over the site, slopes stabilized and revegetation accomplished in accordance with 10
CSR 40-3.120. Operation of the disposal site
shall be conducted in accordance with all
local, state and federal requirements.
(C) At no time shall any solid waste material be deposited at refuse embankments or
impoundment sites nor shall any excavation
for solid waste disposal be located within
eight feet (8') of any coal outcrop or coal
storage area.
(D) Any noncoal mine waste defined as
hazardous under Section 3001 of the
Resource Conservation and Recovery Act
(RCRA)(P.L. 94-580) and 40 CFR part 261
shall be handled in accordance with the
requirements of Subtitle C of RCRA and any
implementing regulations.
(9) Dams and Embankments—General Requirements.
(A) Sections (9)–(11) of this rule apply to
dams and embankments, constructed of coal
processing waste or intended to impound coal
processing waste, whether they were completed before adoption of the regulatory program or are intended to be completed after
that.
(B) Waste shall not be used in the construction of dams and embankments unless it has
been demonstrated that the stability of that
structure conforms with the requirements of
subsection (11)(A) of this rule. It also shall
be demonstrated that the use of waste material shall not have a detrimental effect on
downstream water quality or the environment
due to acid seepage through the dam or
embankment.
(10) Dams and Embankments—Site Preparation. Before coal processing waste is placed
at a dam or embankment site—
(A) All trees, shrubs, grasses and other
organic material shall be cleared and grubbed
from the site, and all combustibles shall be
removed and stockpiled in accordance with
the requirements of this chapter; and
(B) Runoff from areas above the disposal
facility or runoff from the surface of the facility that may cause erosion to the embankment
area or the embankment features, whether
during construction or after completion, shall
be diverted away from the embankment by
diversion ditches that comply with the
requirements of 10 CSR 40-3.040(3).
Adequate outlets for discharge from these
diversions shall be in accordance with section
(7). Diversions that are designed to divert
drainage from the upstream area away from
the impoundment area shall be designed to
carry the peak runoff from a one hundred
(100)-year, twenty-four (24)-hour precipitation event. The diversion shall be maintained
to prevent blockage, and the discharge shall
be in accordance with 10 CSR 40-3.040(7).
Sediment control measures shall be provided
at the discharge of each diversion ditch before
entry into natural watercourses in accordance
with 10 CSR 40-3.040(1)–(7).
(11) Dams and Embankments—Design and
Construction.
(A) The design of each dam and embankment constructed of coal processing waste
or intended to impound waste shall
comply with the requirements of 10
CSR 40-3.040(10)(A)5. and 10 CSR 403.040(10)(E)–(K), modified as follows:
1. The design freeboard between the
lowest point on the embankment crest and the
maximum water elevation shall be at least
three feet (3'). The maximum water elevation
shall be that determined by the freeboard
hydrograph criteria contained in the United
States Soil Conservation Service criteria referenced in 10 CSR 40-3.040(10);
2. The dam and embankment shall have
a minimum safety factor of one and fivetenths (1.5) for the partial pool with steady
seepage saturation conditions and the seismic
safety factor shall be at least one and twotenths (1.2); and
3. The dam or embankment foundation
and abutments shall be designed to be stable
under all conditions of construction and operation of the impoundment. Sufficient foundation investigations and laboratory testing
shall be performed to determine the safety
factors of the dam or embankment for all
loading conditions appearing in paragraph
(11)(A)2. of this rule or the publications
referred to in 10 CSR 40-3.040(10) and for
all increments of construction.
(B) Spillways and outlet works shall be
designed to provide adequate protection
against erosion and corrosion. Inlets shall be
protected against blockage.
(C) Dams or embankments constructed of,
or impounding, waste materials shall be
designed so that at least ninety percent (90%)
of the water stored during the design precipitation event is removed within a ten (10)-day
period.
(D) Dams or embankments constructed of,
or impounding, waste materials may not be
retained permanently as part of the approved
Surface Coal Mining and Related Activities
postmining land use.
AUTHORITY: sections 444.530 and 444.810,
RSMo Supp. 1999.* Original rule filed Oct.
12, 1979, effective Feb. 11, 1980. Amended:
Filed Aug. 8, 1980, effective Dec. 11, 1980.
Amended: Filed Dec. 10, 1980, effective
April 11, 1981. Amended: Filed Sept. 15,
1988, effective Jan. 15, 1989. Amended:
Filed July 3, 1990, effective Nov. 30, 1990.
Amended: Filed May 15, 1992, effective Jan.
15, 1993. Amended: Filed Sept. 15, 1994,
effective April 30, 1995. Amended: Filed
March 21, 2000, effective Oct. 30, 2000.
*Original authority: 444.530, RSMo 1971, amended 1983,
1990, 1993, 1995; and 444.810, RSMo 1979, amended
1983, 1993, 1995.