10 CSR 60-15.090
Monitoring Requirements for Lead and Copper in Source Water
PURPOSE: This rule establishes monitoring
requirements for lead and copper in source
waters.
(1) Sample Location, Collection Methods,
and Number of Samples.
(A) A water system that fails to meet the
lead or copper action level on the basis of tap
samples collected in accordance with 10 CSR
60-15.070 shall collect lead and copper
source water samples in accordance with the
following requirements regarding sample
location, number of samples, and collection
methods:
1. Ground water systems shall take a
minimum of one (1) sample at every entry
point to the distribution system which is representative of each well after treatment (hereafter called a sampling point). The system
shall take one (1) sample at the same sampling point unless conditions make another
sampling point more representative of each
source or treatment plant;
2. Surface water systems shall take a
minimum of one (1) sample at every entry
point to the distribution system after any
application of treatment or in the distribution
system at a point which is representative of
each source after treatment (hereafter called a
sampling point). The system shall take each
sample at the same sampling point unless
conditions make another sampling point more
representative of each source or treatment
plant (Note: For the purposes of this requirement, surface water systems include systems
with a combination of surface and ground
sources);
3. If a system draws water from more
than one (1) source and the sources are combined before distribution, the system must
sample at an entry point to the distribution
system during periods of normal operating
conditions (that is, when water is representative of all sources being used); and
4. The department may reduce the total
number of samples which must be analyzed
by allowing the use of compositing.
Compositing of samples must be done by certified laboratory personnel. Composite samples from a maximum of five (5) samples are
allowed, provided that if the lead concentration in the composite sample is greater than
or equal to 0.001 mg/L or the copper concentration is greater than or equal to 0.160
mg/L, then either:
A. A follow-up sample shall be taken
and analyzed within fourteen (14) days at
each sampling point included in the composite; or
B. If duplicates of or sufficient quantities from the original samples from each
sampling point used in the composite are
available, the system may use these instead of
resampling.
(B) Where the results of sampling indicate
an exceedance of maximum permissible
source water levels established under 10 CSR
60-5.040(2)(C), the department may require
that one (1) additional sample be collected as
soon as possible after the initial sample was
taken (but not to exceed two (2) weeks) at the
same sampling point. If the departmentrequired confirmation sample is taken for
lead or copper, then the results of the initial
and confirmation sample shall be averaged in
determining compliance with maximum permissible levels. Any sample value below the
detection limit shall be considered to be zero
(0). Any value above the detection limit but
below the practical quantification level (PQL)
shall be as the measured value or be considered one-half (1/2) PQL.
(2) Monitoring Frequency After System
Exceeds Tap Water Action Level. Any system
which exceeds the lead or copper action level
at the tap shall collect one (1) source water
sample from each entry point to the distribution system no later than six (6) months after
the end of the monitoring period during
which the lead or copper action level was
exceeded. For monitoring periods that are
annual or less frequent, the end of the monitoring period is September 30 of the calendar
year in which the sampling occurs, or if the
department has established an alternate monitoring period, the last day of that period.
(3) Monitoring Frequency After Installation
of Source Water Treatment. Any system
which installs source water treatment pursuant to 10 CSR 60-15.040 shall collect an
additional source water sample from each
entry point to the distribution system during
two (2) consecutive six- (6-) month monitoring periods by the deadline specified in 10
CSR 60-15.040(1)(D).
(4)
Monitoring
Frequency
After
the
Department Specifies Maximum Permissible
Source Water Levels or Determines that
Source Water Treatment is not Needed.
(A) A system shall monitor at the following specified frequency in cases where the
department specifies maximum permissible
source water levels under 10 CSR 6015.040(2)(C) or determines that the system is
not required to install source water treatment
under 10 CSR 60-15.040(2)(A):
1. A water system using only ground
water shall collect samples once during the
three- (3-) year compliance period in effect
when the applicable department determination under subsection (4)(A) of this rule is
made. Those systems shall collect samples
once during each subsequent compliance
period. Triennial samples shall be collected
every third calendar year; and
2. A water system using surface water
(or a combination of surface and ground
water) shall collect samples once during each
calendar year, the first annual monitoring
period to begin during the year in which the
applicable department determination is made
under subsection (4)(A) of this rule.
(B) A system is not required to conduct
source water sampling for lead, copper, or
both, if the system meets the action level for
the specific contaminant in tap water samples
during the entire source water sampling period applicable to the system under subsection
(4)(A) of this rule.
(5) Reduced Monitoring Frequency.
(A) A water system using only ground
water may reduce the monitoring frequency
for lead and copper in source water to once
during each nine- (9-) year compliance cycle
(as that term is defined in 10 CSR 60-2.015)
provided that the samples are collected no
later than every ninth calendar year and if
the system meets any one (1) of the following
criteria:
1. The system demonstrates that finished
drinking water entering the distribution
system has been maintained below the
maximum permissible lead and copper
concentrations specified in 10 CSR 6015.040(2)(C) during at least three (3)
consecutive compliance periods under
subsection (4)(A) of this rule; or
2. The department has determined that
source water treatment is not needed and the
system demonstrates that, during at least
three (3) consecutive compliance periods in
which sampling was conducted under
subsection
(4)(A)
of
this
rule,
the
concentration of lead in source water was less
than or equal to 0.005 mg/L and the
concentration of copper in source water was
less than or equal to 0.65 mg/L.
(B) A water system using surface water (or
a combination of surface and ground waters)
may reduce the monitoring frequency in
paragraph (4)(A)2. of this rule to once during
each nine- (9-) year compliance cycle (as that
term is defined in 10 CSR 60-2.015) provided that the samples are collected no later than
every ninth calendar year and if the system
meets one (1) of the following criteria:
1. The system demonstrates that finished
drinking water entering the distribution
system has been maintained below the
maximum permissible lead and copper
concentrations specified in 10 CSR 6015.040(2)(C)
for
at
least
three
(3)
consecutive years; or
2. The department has determined that
source water treatment is not needed and the
system demonstrates that, during at least
three (3) consecutive years, the concentration
of lead in source water was less than or equal
to 0.005 mg/L and the concentration of copper in source water was less than or equal to
0.65 mg/L.
(C) A water system that uses a new source
of water is not eligible for reduced monitoring for lead, copper, or both, until concentrations in samples collected from the new
source during three (3) consecutive monitoring periods are below the maximum permissible lead and copper concentrations.
AUTHORITY: section 640.100, RSMo Supp.
2011.* Original rule filed Aug. 4, 1992, effective May 6, 1993. Amended: Filed Aug. 14,
2001, effective April 30, 2002. Amended:
Filed Oct. 17, 2011, effective May 30, 2012.
*Original authority: 640.100, RSMo 1939, amended 1978,
1981, 1982, 1988, 1989, 1992, 1993, 1995, 1996, 1998,
1999, 2002, 2006.