20 CSR 4240-10.035
Residential Advanced Meter or Hub Meter Opt-Out
PURPOSE: This rule establishes the requirements governing the
residential advanced meter and hub meter opt-out process in
accordance with section 386.820, RSMo.
(1) This rule applies to residential utility service provided by all
electrical corporations, gas corporations, sewer corporations,
and water corporations as those terms are defined in section
386.020, RSMo.
(2) The following definitions shall apply in this rule:
(A) Advanced meter means a meter or metering device
system that is owned or leased by a utility or its agent and that
meets one (1) or more of the following requirements:
1. Measures, records, and sends a customer’s utility usage
or other data by use of radio waves or broadband over power
lines;
2. Allows for two- (2-) way communication between the
meter and the utility or its agent; and
3. Allows for a utility or its agent to control a customer’s
thermostat, appliance, or service;
(B) Billing cycle shall have the same meaning as billing
period as defined in 20 CSR 4240-13.015(1)(C);
(C) Commercially available means a meter that is readily
available for purchase by the utility;
(D) Commercially reasonable means in line with commonly
accepted practices and standards for electric, gas, water, and
sewer utilities as determined by the commission;
(E) Hub meter means an advanced meter that generates
stronger radio waves as a result of the meter serving as a hub
for other advanced meters it communicates with in a given
area;
(F) Inaccurate information means the intentional underreporting of meter data in an effort to not pay for services.
Inaccurate information does not mean minor differences in
readings by less than two percent (2%) to account for variations
based on the time of day that the meter is read and similar
factors;
(G) Meter use fee means a fixed monthly charge designed
to recover the difference between the revenue requirement
associated with metering, reading, and billing a customer
without advanced metering and the revenue requirement to
be recovered through a fixed monthly charge applicable to
customers with similar requirements that are metered, read,
and billed using advanced metering;
AND INSURANCE
(H) Traditional meter means a commercially available meter
that is unable to transmit usage information and is only
intended to be read by an individual through a visual display.
A traditional meter is not designed or capable of transmitting
usage data by using radio waves or broadband over power
lines, allowing two- (2-) way communication between the
meter and the utility or its agents, or allowing a utility or
its agents to control a customer’s thermostat, appliance, or
service. A traditional meter does not include an advanced
meter or hub meter that has certain functionality turned off or
deactivated; and
(I) Utility or utilities mean residential utility service
provided by any electrical corporation, gas corporation, sewer
corporation, or water corporation, as those terms are defined in
section 386.020, RSMo.
(3) All utilities shall file with the commission a tariff that
governs its advanced meter or hub meter opt-out process.
(A) The tariff may include—
1. A one- (1-) time all-inclusive fee, not to exceed one
hundred twenty-five dollars ($125), for removal of an advanced
or hub meter and to provide and install a traditional meter;
2. A monthly meter use fee, not to exceed fifteen dollars
($15), for the use of a traditional meter.
A. The utility may propose a single monthly fee for
all customers using a traditional meter, or it may propose
separate monthly fees for customers who elect to self-read
the traditional meter and for those whose meters are read by
the utility. In no event shall a utility assess more than one (1)
monthly fee per meter for the use of a traditional meter; and
3. An interest charge on any unpaid amount the utility
may assess due to the customer’s failure to report usage or
reporting inaccurate information in any given billing cycle.
Such interest rate shall be no greater than five percent (5%).
(B) The tariff must include—
1. A description of the utility’s meter placement practices,
including location;
2. A commercially reasonable time, in days, the utility
expects to replace an advanced or hub meter with a traditional
meter, following a request;
3. A description of how the customer may supply readings
as further defined in section (5);
4. A list and description of situations that would prevent
the installation of a traditional meter. For example, but not
limited to, a current net-metering arrangement or customer
selection of a rate that requires interval billing; and
5. If the utility’s existing tariffs contain any of the items
in subsections (3)(A) and (3)(B), a reference to that information
shall be included in the advanced or hub meter opt-out tariff.
(4) If a utility seeks to discontinue its advanced or hub meter
opt-out process, it shall include information that is sufficient to
determine traditional meters are not commercially available in
its discontinuance filing.
(5) Customer-supplied readings shall be in accordance with 20
CSR 4240-13.020 and the utility’s commission-approved tariffs.
(A) Each utility shall provide the customer with a detailed
process to report meter readings by telephone or other
commercially reasonable means. A utility may additionally
offer reporting through a secure website.
(B) If a customer elects to supply meter readings, the
customer shall timely report accurate usage to the utility once
per billing cycle.
(C) The utility shall obtain an actual meter reading to verify
accuracy of customer-supplied meter readings at least once
every twelve (12) months.
(6) Each utility shall provide its customers a simple comparison
of the functional differences between the utility’s traditional
and advanced meters, hub meters, or appurtenances that
enable automated or remote meter readings on traditional
meters.
(7) If the utility determines or believes that the commercially
reasonable time, as defined in its tariff, will be exceeded before
the advanced or hub meter replacement date, the utility shall
provide notice to the customer explaining the replacement of
the advanced or hub meter has been extended, with the new
date the utility will replace the advanced or hub meter to a
traditional meter.
(8) Beginning on July 1, 2027, and annually thereafter, the
utility shall submit a non-case related submission that provides
the following information:
(A) Number of customers electing a traditional meter;
(B) Number of advanced meters and hub meters in use by the
utility to serve residential customers;
(C) Cost of offering the advanced and hub meter opt-out
process for the most recent twelve (12) months; and
(D) Fee revenues collected related to the advanced and hub
meter opt-out process for the most recent twelve (12) months.
AUTHORITY: section 386.820, RSMo Supp. 2025.* Original rule
filed Aug. 28, 2025, effective April 30, 2026.
*Original authority: 386.820, RSMo 2025.