20 CSR 4240-22.010
Policy Objectives
PURPOSE: This rule states the public policy
goal that this chapter is designed to achieve
and identifies the objectives that the electric
utility resource planning process must serve.
(1) The commission’s policy goal in promulgating this chapter is to set minimum standards to govern the scope and objectives of
the resource planning process that is required
of electric utilities subject to its jurisdiction
in order to ensure that the public interest is
adequately served. Compliance with these
rules shall not be construed to result in commission approval of the utility’s resource
plans, resource acquisition strategies, or
investment decisions.
(2) The fundamental objective of the resource
planning process at electric utilities shall be
to provide the public with energy services
that are safe, reliable, and efficient, at just
and reasonable rates, in compliance with all
legal mandates, and in a manner that serves
the public interest and is consistent with state
energy and environmental policies. The fundamental objective requires that the utility
shall—
(A) Consider and analyze demand-side
resources, renewable energy, and supply-side
resources on an equivalent basis, subject to
compliance with all legal mandates that may
affect the selection of utility electric energy
resources, in the resource planning process;
(B) Use minimization of the present worth
of long-run utility costs as the primary selection criterion in choosing the preferred
resource plan, subject to the constraints in
subsection (2)(C); and
(C) Explicitly identify and, where possible, quantitatively analyze any other considerations which are critical to meeting the fundamental objective of the resource planning
process, but which may constrain or limit the
minimization of the present worth of expected utility costs. The utility shall describe and
document the process and rationale used by
decision-makers to assess the tradeoffs and
determine the appropriate balance between
minimization of expected utility costs and
these other considerations in selecting the
preferred resource plan and developing the
resource acquisition strategy. These considerations shall include, but are not necessarily
limited to, mitigation of:
1. Risks associated with critical uncertain factors that will affect the actual costs
associated with alternative resource plans;
2. Risks associated with new or more
stringent legal mandates that may be imposed
at some point within the planning horizon;
and
3. Rate increases associated with alternative resource plans.
AUTHORITY: sections 386.040, 386.250,
386.610, and 393.140, RSMo 2000.* This
rule originally filed as 4 CSR 240-22.010.
Original rule filed June 12, 1992, effective
May 6, 1993. Amended: Filed Oct. 25, 2010,
effective June 30, 2011. Moved to 20 CSR
4240-22.010, effective Aug. 28, 2019.
*Original authority: 386.040, RSMo 1939; 386.250,
RSMo 1939, amended 1963, 1967, 1977, 1980, 1987,
1988, 1991, 1993, 1995, 1996; 386.610, RSMo 1939; and
393.140, RSMo 1939, amended 1949, 1967.