20 CSR 4240-22.020
Definitions
PURPOSE: This rule defines terms used in
the rules comprising 4 CSR 240-22—Electric
Utility Resource Planning.
(1) Acknowledgment is an action the commission may take with respect to the officially adopted resource acquisition strategy or
any element of the resource acquisition strategy including the preferred resource plan.
Acknowledgement means that the commission finds the preferred resource plan,
resource acquisition strategy, or the specified
element of the resource acquisition strategy
to be reasonable at a specific date, typically
the date of the filing of the utility’s Chapter
22 compliance filing or the date that acknowledgment is given. Acknowledgment may be
given in whole, in part, or not at all.
Acknowledgment shall not be construed to
mean or constitute a finding as to the prudence, pre-approval, or prior commission
authorization of any specific project or group
of projects.
(2) Annual update filing means the annual
update report prepared by the utility in
advance of the annual update workshop and
the summary report prepared by the utility
following the workshop as referenced in 4
CSR 240-22.080(3).
(3) Candidate resource options are the potential demand-side resource options pursuant to
4 CSR 240-22.050(6) and the potential supply-side resource options pursuant to 4 CSR
240-22.040(4) that advance to be included in
one (1) or more alternative resource plans.
(4) Capacity means the maximum capability
to continuously produce and deliver electric
power via supply-side resources or the avoidance of the need for this capability by
demand-side resources.
(5) Coincident demand means the hourly
demand of a component of system load at the
hour of system peak demand within a specified interval of time.
(6) Concern means concerns with the electric
utility’s compliance with the provisions of
this chapter, any major concerns with the
methodologies or analyses required to be performed by this chapter, and anything that,
while not rising to the level of a deficiency,
may prevent the electric utility’s resource
acquisition strategy from effectively fulfilling
the objectives of Chapter 22.
(7) Contingency resource plan means an
alternative resource plan designed to enhance
the utility’s ability to respond quickly and
appropriately to events or circumstances that
would render the preferred resource plan
obsolete.
(8) Critical uncertain factor is any uncertain
factor that is likely to materially affect the
outcome of the resource planning decision.
(9) Deficiency means deficiencies in the electric utility’s compliance with the provisions
of this chapter, any major deficiencies in the
methodologies or analyses required to be performed by this chapter, and anything that
would cause the electric utility’s resource
acquisition strategy to fail to meet the
requirements identified in Chapter 22.
(10) Demand means the rate of electric power
use measured in kilowatts (kW).
(11) Demand-side program means an organized process for packaging and delivering to
a particular market segment a portfolio of
end-use measures that is broad enough to
include at least some measures that are
appropriate for most members of the target
market segment.
(12) Demand-side rate means a rate structure
for retail electric service designed to reduce
the net consumption or modify the time of
consumption of a customer rate class.
(13) Demand-side resource is a demand-side
program or a demand-side rate conducted by
the utility to modify the net consumption of
electricity on the retail customer’s side of the
meter. A load-building program or rate is not
a demand-side resource.
(14) Describe and document refers to the
demonstration of compliance with each provision of this chapter. Describe means the
provision of information in the technical volume(s) of the triennial compliance filing, in
sufficient detail to inform the stakeholders
how the utility complied with each applicable
requirement of Chapter 22, why that
approach was chosen, and the results of its
approach. The description in the technical
volume(s), including narrative text, graphs,
tables, and other pertinent information, shall
be written in a manner that would allow a
stakeholder to thoroughly assess the utility’s
resource acquisition strategy and each of its
components. Document means the provision
of all of the supporting information relating to
the filed resource acquisition strategy pursuant to 4 CSR 240-22.080(11).
(15) Distributed generation means a gridconnected electric generation system that is
sized based on local load requirements and
distributed primarily to the local load.
(16) Electric utility or utility means any electrical corporation as defined in section
386.020, RSMo, which is subject to the jurisdiction of the commission.
(17) End-use energy service or energy service means the specific need that is served by
the final use of energy, such as lighting,
cooking, space heating, air conditioning,
refrigeration, water heating, or motive power.
(18) End-use measure means an energy-efficiency measure or an energy-management
measure.
(19) Energy means the total amount of electric power that is generated or used over a
specified interval of time measured in kilowatt-hours (kWh).
(20) Energy-efficiency measure means any
device, technology, or operating procedure
that makes it possible to deliver an adequate
level and quality of end-use energy service
while using less energy than would otherwise
be required.
(21) Energy-management measure means any
device, technology, or operating procedure
that makes it possible to alter the time pattern
of electricity usage so as to require less generating capacity or to allow the electric power
to be supplied from more fuel-efficient generating units. Energy-management measures
are sometimes referred to as demandresponse measures.
(22) Expected cost of an alternative resource
plan is the statistical expectation of the cost of
implementing that plan, contingent upon the
uncertain factors and associated probabilities.
The utility shall consider probable environmental costs as well as direct utility costs in
its assessment of alternative resource plans.
(23) Expected unserved hours means the statistical expectation of the number of hours
per year that a utility will be unable to supply
its native load without importing emergency
power.
(24) Historical period shall be the ten (10)
most recent years or the period of time used
as the basis of the utility’s forecast, whichever is longer.
(25) Implementation period means the time
interval between the triennial compliance filings required of each utility pursuant to 4
CSR 240-22.080.
(26) Implementation plan means descriptions
and schedules for the major tasks necessary
to implement the preferred resource plan over
the implementation period.
(27) Information means any fact, relationship, insight, estimate, or expert judgment
that narrows the range of uncertainty surrounding key decision variables or has the
potential to substantially influence or alter
resource-planning decisions.
(28) Legal mandates include applicable state
and federal executive orders, legislation,
court decisions, and applicable state and federal administrative agency orders, rules, and
regulations affecting electric utility cost
recovery mechanisms, loads, resources, or
resource plans.
(29) Levelized cost means the dollar amount
of a fixed annual payment for which a stream
of those payments over a specified period of
time is equal to a specified present value
based on a specified rate of interest.
(30) Life-cycle cost means the present worth
of costs over the lifetime of any device or
means for delivering end-use energy service.
(31) Load-building program means an organized promotional effort by the utility to persuade energy-related decision-makers to
choose electricity instead of other forms of
energy for the provision of energy service or
to persuade existing customers to increase
their use of electricity, either by substituting
electricity for other forms of energy or by
increasing the level or variety of energy services used. This term is not intended to
include the provision of technical or engineering assistance, information about filed
rates and tariffs, or other forms of routine
customer service.
(32) Load impact means the change in energy usage and the change in diversified
demand during a specified interval of time
due to the implementation of a demand-side
resource.
(33) Load profile means a plot of hourly
demand versus chronological hour of the day
from the hour ending 1:00 a.m. to the hour
ending 12:00 midnight.
(34) Load-research data means major class
level average hourly demands (kWhs per
hour) derived from the metered instantaneous
demand for each customer in the loadresearch sample.
(35) Long run means an analytical framework
within which all factors of production are
variable.
(36) Lost revenues means the reduction
between rate cases in billed demand (kW)
and energy (kWh) due to installed end-use
measures, multiplied by the fixed-cost margin
of the appropriate rate component.
(37) Major class is a cost-of-service class of
the utility.
(38) Market imperfection means any factor or
situation that contributes to inefficient energy-related choices by decision-makers,
including at least:
(A) Inadequate information about costs,
performance, and benefits of end-use measures;
(B) Inadequate marketing infrastructure or
delivery channels for end-use measures;
(C) Inadequate financing options for enduse measures;
(D) Mismatched economic incentives
resulting from situations where the person
who pays the initial cost of an efficiency
investment is different from the person who
pays the operating costs associated with the
chosen efficiency level;
(E) Ineffective economic incentives when
decision-makers give low priority to energyrelated choices because they have a shortterm ownership perspective or because energy costs are a relatively small share of the
total cost structure (for businesses) or of the
total budget (for households); or
(F) Inefficient pricing of energy supplies.
(39) Market segment means any subgroup of
utility customers (or other energy-related
decision-makers) which has some or all of the
following characteristics in common: they
have a similar mix of end-use energy service
needs, they are subject to a similar array of
market imperfections that tend to inhibit efficient energy-related choices, they have similar values and priorities concerning energyrelated choices, or the utility has access to
them through similar channels or modes of
communication.
(40) Maximum achievable potential means
energy savings and demand savings relative to
a utility’s baseline energy forecast and baseline demand forecast, respectively, resulting
from expected program participation and
ideal implementation conditions. Maximum
achievable potential establishes a maximum
target for demand-side savings that a utility
can expect to achieve through its demand-side
programs and involves incentives that represent a very high portion of total program
costs and very short customer payback periods. Maximum achievable potential is considered the hypothetical upper-boundary of
achievable demand-side savings potential,
because it presumes conditions that are ideal
and are not typically observed.
(41) Nominal dollars means future or thencurrent dollar values that are not adjusted to
remove the effects of anticipated inflation.
(42) Participant means an energy-related
decision-maker who implements one (1) or
more end-use measures as a direct result of a
demand-side program.
(43) Planning horizon means a future time
period of at least twenty (20) years’ duration
over which the costs and benefits of alternative resource plans are evaluated.
(44) Plot means a graphical representation to
present data. Each plot shall be labeled as a
stand-alone figure, whose axes shall be
labeled with units. The data presented in each
plot also shall be provided in tabular form in
the technical volumes and in workpapers.
Data tables will be labeled, including the
identification of the corresponding plot. The
plots and data tables shall be numbered, referenced, and explained in the text of the technical volumes and in workpapers.
(45) Potential resource options are all of the
resources in the comprehensive set of
demand-side resources that shall be considered pursuant to 4 CSR 240-22.050(1) and in
the comprehensive set of supply-side
resources that shall be considered pursuant to
4 CSR 240-22.040(1).
(46) Preferred resource plan means the
resource plan that is contained in the resource
acquisition strategy that has most recently
been adopted by the utility decision-maker(s)
for implementation by the electric utility.
(47) Probable environmental cost means the
expected cost to the utility of complying with
new or additional environmental legal mandates, taxes, or other requirements that, in
the judgment of the utility decision-makers,
may be imposed at some point within the
planning horizon which would result in compliance costs that could have a significant
impact on utility rates.
(48) Public counsel means the public counsel
of the state of Missouri or their designated
representative.
(49) Realistic achievable potential means
energy savings and demand savings relative to
a utility’s baseline energy forecast and baseline demand forecast, respectively, resulting
from expected program participation and
realistic implementation conditions. Realistic
achievable potential establishes a realistic target for demand-side savings that a utility can
expect to achieve through its demand-side
programs and involves incentives that represent a moderate portion of total program
costs and longer customer payback periods
when compared to those associated with
maximum achievable potential.
(50) Renewable energy means electricity generated from a source that is classified as a
renewable energy source under a state or federal renewable energy standard to which the
utility is subject.
(51) Resource acquisition strategy means a
preferred resource plan, an implementation
plan, a set of contingency resource plans, and
the events or circumstances that would result
in the utility moving to each contingency
resource plan. It includes the type, estimated
size, and timing of resources that the utility
plans to achieve in its preferred resource
plan.
(52) Resource plan means a particular combination of demand-side and supply-side
resources to be acquired according to a specified schedule over the planning horizon.
(53) Resource planning means the process by
which an electric utility evaluates and chooses the appropriate mix and schedule of supply-side, demand-side, and distribution and
transmission resource additions and retirements to provide the public with an adequate
level, quality, and variety of end-use energy
services.
(54) RTO/ISO means Regional Transmission
Organization or independent transmission
system operator as defined in the Federal
Energy Regulatory Commission (FERC)
Order 200 and subsequent FERC orders.
(55) Special contemporary issues means a
written list of issues contained in a commission order with input from staff, public counsel, and intervenors that are evolving new
issues, which may not otherwise have been
addressed by the utility or are continuations
of unresolved issues from the preceding triennial compliance filing or annual update filing. Each utility shall evaluate and incorporate special contemporary issues in its next
triennial compliance filing or annual update
filing.
(56) Stakeholder group means—
(A) Staff, public counsel, and any person
or entity granted intervention in a prior
Chapter 22 proceeding of the electric utility.
Such persons or entities shall be a party to
any subsequent related Chapter 22 proceeding of the electric utility without the necessity of applying to the commission for intervention; and
(B) Any person or entity granted intervention in a current Chapter 22 proceeding of the
electric utility.
(57) Subjective probability means the judgmental likelihood that the outcome will actually occur.
(58) Supply-side resource or supply resource
means any device or method by which the
electric utility can provide to its customers an
adequate level and quality of electric power
supply.
(59) Technical potential means energy savings and demand savings relative to a utility’s
baseline energy forecast and baseline demand
forecast, respectively, resulting from a theoretical construct that assumes all feasible
measures are adopted by customers of the
utility regardless of cost or customer preference.
(60) Total resource cost test is a test of the
cost-effectiveness of demand-side programs
or demand-side rates that compares the sum
of avoided utility costs plus avoided probable
environmental costs to the sum of all incremental costs related to the end-use measures
that are implemented due to the program or
related to the rates (including both utility and
participant contributions), plus utility costs to
administer, deliver, and evaluate each
demand-side program or demand-side rate to
quantify the net savings obtained by substituting the demand-side program or demand-side
rate for supply-side resources.
(61) Uncertain factor means any event, circumstance, situation, relationship, causal
linkage, price, cost, value, response, or other
relevant quantity which can materially affect
the outcome of resource planning decisions,
about which utility planners and decisionmakers have incomplete or inadequate information at the time a decision must be made.
(62) Utility costs are the costs of operating
the utility system and developing and implementing a resource plan that are incurred and
paid by the utility. On an annual basis, utility
cost is synonymous with utility revenue
requirement.
(63) The utility cost test is a test of the costeffectiveness of demand-side programs or
demand-side rates that compares the avoided
utility costs to the sum of all utility incentive
payments, plus utility costs to administer,
deliver, and evaluate each demand-side program or demand-side rate to quantify the net
savings obtained by substituting the demandside program or demand-side rate for supplyside resources.
(64) Utility discount rate means the post-tax
rate of return on net investment used to calculate the utility’s annual revenue requirements.
(65) Weather measure means a function of
daily temperature data that reflects the
observed relationship between electric load
and temperature.
AUTHORITY: sections 386.040, 386.250,
386.610, and 393.140, RSMo 2000.* This
rule originally filed as 4 CSR 240-22.020.
Original rule filed June 12, 1992, effective
May 6, 1993. Amended: Filed Oct. 25, 2010,
effective June 30, 2011. Moved to 20 CSR
4240-22.020, effective Aug. 28, 2019.
*Original authority: 386.040, RSMo 1939; 386.250,
RSMo 1939, amended 1963, 1967, 1977, 1980, 1987,
1988, 1991, 1993, 1995, 1996; 386.610, RSMo 1939; and
393.140, RSMo 1939, amended 1949, 1967.