11 CSR 40-2.025
Installation Permits
PURPOSE: This rule addresses the application requirement, issuing
of permits and installation inspections for the repair, replacement,
or new installation of objects that are subject to the Act and these
rules.
(1) As used in this rule, the term “these rules” is intended to
mean 11 CSR 40-2.010 through 11 CSR 40-2.065.
(2) Effective January 1, 2007, an installation permit shall be
obtained by the installer from the Division of Fire Safety, Boiler
and Pressure Vessel Unit before the start of work for each new,
second hand, or reinstalled boiler, water heater or pressure
vessel. Replacement or relocation of an existing boiler, water
heater, or pressure vessel shall be permitted as a new installation. The requirement to obtain an installation permit prior
to the start of work is waived for an emergency replacement
upon notification to the chief inspector.
(3) An application for an installation permit shall be submitted
to the chief inspector on forms provided by the Division of Fire
Safety, Boiler and Pressure Vessel Unit at least sixty (60) days
prior to the start of the installation.
(A) In the case of an emergency replacement, the application
shall be submitted to the chief inspector as soon as possible
but not more than seven (7) calendar days after the work has
started.
(B) Installation permits for multiple boilers, water heaters, or
pressure vessels may be requested on a single application provided they are all located at the same installation site. In such
cases separate installation permits will be issued and fees will
be charged for each permit.
(C) Upon review of the installation permit, the chief inspector may require a plan review prior to issuing an installation
permit. A separate fee of thirty-five dollars ($35) per hour not
to exceed five hundred dollars ($500) total will be charged for
the plan review.
(D) Upon completion of the review process and payment of
the required fees an installation permit will be issued. The installer shall maintain a legible copy of the installation permit
at the installation site.
(4) Fees.
(A) Plan Review Hourly Fee
$ 35
(B) Installation Permit Fees—
1. Hot Water Heating Boiler—
A. 400,000 BTUH and less
$ 70
B. Greater than 400,000 BTUH
but less than 12,500,000 BTUH
$175
C. 12,500,000 BTUH and above
$245
2. Hot Water Supply Boilers,
Circulating Water Heaters,
and Pool Heaters—
A. 400,000 BTUH and less
$ 70
B. Greater than 400,000 BTUH
but less than 12,500,000 BTUH
$175
C. 12,500,000 BTUH and above
$245
3. Fired Jacketed Steam Kettles
$ 70
4. Power Boilers—
A. 400,000 BTUH and less
$ 70
B. Greater than 400,000 BTUH
but less than 12,500,000 BTUH
$175
C. 12,500,000 BTUH and above
$245
5. Pressure Vessel—
A. 1,000 cu.ft.
(7,500 gallons) or less
$ 70
B. Greater than 1,000 cu. ft.
$175
C. Compressed air receivers including tank
mounted air compressors designed to
operate at 250 psi or less and having
a volume of 250 gallons or less
$ 25
D. Carbon Dioxide Storage Vessels used
solely for carbonated beverage systems
$ 25
6. Steam Heating Boilers—
A. 400,000 BTUH or less
$ 70
B. Above 400,000 BTUH but
less than 12,500,000 BTUH
$175
C. 12,500,000 BTUH and above
$245
7. Fired Storage Water Heaters
(Above 200,000 BTUH or 120 gallons)
$ 70
(5) Upon completion of an installation, the chief inspector or
a deputy inspector shall perform a certificate inspection. After
correcting any deficiencies noted during the certificate inspection and payment of the required fees, the chief inspector will
issue an Inspection Certificate.
(A) The Special Inspectors shall perform a certificate inspection, with an Approved Installation Permit from the Chief
Inspector, on all boilers and pressure vessels insured by their
respective companies, and, when so inspected, the owners and
users of the boilers and pressure vessels shall be exempt from
the payment to the state of the inspection fees provided for in
section 650.275, RSMo. All pressure vessels in which steam is
generated by the application of heat resulting from the combustion of fuel (solid, liquid, or gaseous) or electrical energy for
use external to itself shall be classified as a fired steam boiler.
(6) Any boiler, water heater, or pressure vessel installed on or
after January 1, 2007, without obtaining the required permit
shall obtain an installation permit and correct any deficiencies identified during the certificate inspection before an
Inspection Certificate can be issued. If additional inspections
are required to confirm the adequacy of the required corrective
actions the applicable inspection fees will be charged.
AUTHORITY: section 650.215, RSMo 2016.* Original rule filed
March 23, 2006, effective Dec. 30, 2006. Emergency amendment
filed Dec. 22, 2008, effective Jan. 1, 2009, expired June 29, 2009.
Amended: Filed Dec. 22, 2008, effective June 30, 2009. Amended:
Filed Sept. 13, 2024, effective April 30, 2025.
*Original authority: 650.215, RSMo 1984, amended 1990, 1993, 1995.