19 MAC Pt. 8, Ch. 1, R. 1.28

Plan Review – New Equipment

Year: 2026Length: 141 wordsOfficial source

Cite as 19 Miss. Admin. Code Pt. 8, Ch. 1, R. 1.28

Plan Review – New Equipment (1) A contractor must submit for review an application and plans for the installation of new equipment. (2) To apply for a plan review for the installation of new equipment, a contractor must: (a) submit a completed application on a department-approved form; (b) pay the fee required by this Regulation; and (c) submit layout drawings as specified in this Regulation for the specific type of equipment to be installed. These layout drawings shall also include: (i) the rated speed of the equipment in feet per minute; (ii) the rated capacity of the equipment in pound; (iii) the total travel of the equipment in feet and inches; (iv) elevation drawings of the hoistway, runway, or wellway; and (v) plan drawings indicating the arrangement of the equipment in a machine room, machine space, control room, or control space.