15 MAC Pt. 10, R. 2.3.3
When as a result of external inspection or determination by other objective means it
Cite as 15 Miss. Admin. Code Pt. 10, R. 2.3.3
When as a result of external inspection or determination by other objective means it
is the inspector's opinion that continued operation of the boiler or pressure vessel
constitutes a menace to public safety, the inspector may request an internal
inspection and/or an appropriate pressure test to evaluate conditions. In such
instances, the owner or user shall prepare the boiler or pressure vessel for an internal
inspection and/or appropriate pressure test as the inspector designates.