33 MAC Pt. 2, R. 3.6.1
Within the timeframe established in the loan agreement, the loan recipient must
Cite as 33 Miss. Admin. Code Pt. 2, R. 3.6.1
Within the timeframe established in the loan agreement, the loan recipient must
1. Secure Department approval of the plans, specifications and contract documents.
2. For all loan ineligible real property and easements (including power and other utilities),
complete the appropriate requirements of the federal Uniform Relocation Assistance and
Real Property Acquisition Policies Act (The Uniform Act) as implemented by federal
regulation 49 CFR Part 24.101(a)(1) and (2) as applicable and submit certification forms
from both the loan recipient and the title counsel which indicate that all such loan
ineligible real property and easements for the entire project have been secured by clear
title.
3. Secure all local funds necessary for the project and submit proof of such.
4. Upon completion of (1) through (3) above and issuance of any other permits or
clearances required for the project, advertise the project for construction bids. All
procurement actions by the loan recipient must comply with state law and these
regulations.