33 MAC Pt. 2, R. 3.6.2

Upon receipt of construction bids, the loan recipient must then submit a) the

Year: 2026Length: 40 wordsOfficial source

Cite as 33 Miss. Admin. Code Pt. 2, R. 3.6.2

Upon receipt of construction bids, the loan recipient must then submit a) the completed DBE MBE/WBE documentation as required by Appendix E of these regulations, b) the completed bid package, c) all necessary executed contracts and amendments as described in