36 MAC Pt. 2, R. 203.4
005-400 Lifecycle Cost
Cite as 36 Miss. Admin. Code Pt. 2, R. 203.4
005-400 Lifecycle Cost
The lifecycle cost of an information technology project means the total committed costs of the
project, not just the initial or up-front costs. Lifecycle cost includes all costs associated with
obtaining the item and maintaining and operating it for its projected lifecycle. Initial or one-time
costs might include purchase price, freight, installation, and training. Ongoing costs include such
expenses as post-warranty maintenance; support, including help desk charges, upgrade charges,
and on-site vendor personnel; and any recurring usage charges.
Examples:
(1) An acquisition of equipment with a projected lifecycle of five years, a purchase cost of
$100,000, monthly hardware maintenance of $250, and related annual software fees of $10,000
has a lifecycle cost of $165,000 (($100,000 + ($250 x 60 months) + ($10,000 x 5 years)).
(2) An acquisition of software from the Microsoft Enterprise Agreement is a three-year purchase
commitment. The lifecycle cost is the cost per seat times the number of seats times 3 years.
(3) For a turn-key acquisition of hardware, system software, and consulting services for the
development of an application system, the lifecycle costs consist of: (a) all initial fees for hardware
and software, (b) hardware and software maintenance and support costs over the projected life of
the hardware and system software, (c) all consulting fees, including initial development,
implementation, training, data conversion, and other requested services, and (d) any applicable
ongoing costs for support of the resulting application system.
As part of the procurement request to ITS, the customer is asked to provide an estimate of the
useful life of the acquisition prior to replacement. This estimate is used as the lifecycle term over
which the lifecycle cost is computed.
See the definition of "Project”, Section 005-600, for an explanation of the implications of project
lifecycle costs.