Why define a project?
(1) Each ITS Express Products List (EPL) specifies a maximum spending limit per project. For
projects costing up to the designated amount, ITS has delegated to the purchasing entity the
authority and responsibility for selecting the lowest and best vendor for the specific project from
among the offerings on the EPL. Projects with total project lifecycle costs above the EPL limit
are beyond the scope of this delegated process and are subject to full ITS review and authorization.
See Handbook Section 005-400 for the definition of lifecycle cost. [Note: with ITS participation
and approval, EPLs can be utilized as the procurement instrument for projects above the EPL
spending limit via the Planned Purchases process (Handbook Section 013-080) or by submitting a
Competitive Procurement Request for ITS to issue a Letter of Configuration based on the
appropriate EPL.
(2) For information technology projects involving the expenditure of funds above a specified limit,
state law generally requires: (a) that the acquisition be based upon competitive specifications; (b)
that the acquisition be publicly advertised; and (c) that sealed proposals be received and evaluated
to determine the lowest and best respondent [Mississippi Code Annotated, Section 25-53-5 (o)].
State law further specifies that it is unlawful to split purchases in order to circumvent the
requirements for advertising [Mississippi Code Annotated, Section 31-7-13 (o)]. ITS policies and
procedures use the total project lifecycle cost to determine whether a given acquisition is above
the bid threshold and to further determine the procurement mechanisms that can legally be used
for that acquisition. See Handbook Section 005-400 for the definition of total project lifecycle
cost and ITS Procurement Limits Policies in Section 015-010 (State Agencies) and Section 015-
020 (IHLs) for an overview of procurement mechanisms by lifecycle cost range. Note: The current
bid threshold is the expenditure of funds in excess of the dollar amount established in Section 31-
7-13(c).
(3) Mississippi Code Annotated, Section 25-53-5 (k) requires that contracts for information
technology purchases be approved by the ITS Board. The Board is authorized to delegate this
approval to the ITS Executive Director for projects costing less than a specified amount. See
Handbook Section 018-030 for current Executive Director thresholds and Board Approval
requirements. The total project lifecycle cost is used to determine whether a contract can be
approved by the ITS Executive Director or must be submitted to the ITS Board for approval.
(4) Mississippi Code Annotated, Section 31-3-21 requires that any contractor submitting a bid for
a public project that (a) involves erection, building, construction, reconstruction, repair,
maintenance or related work and (b) will cost in excess of $50,000, possess a Certificate of
Responsibility issued by the Mississippi Board of Contractors. This section of the code also
requires that all bids submitted for such projects contain, on the exterior of the bid envelope,
contractor’s current certificate number. Projects involving inside or outside cabling fall within
this category and are under the purview of ITS. The total project lifecycle cost is used to
determine whether the project requires a certificate of responsibility, which in turn determines who
can bid on the project and whether the bid must have the certificate number on the exterior of the
bid envelope to be accepted.
Guidelines for defining a project:
A project has a specific objective or desired accomplishment and defined starting and ending dates
(even if these are rather flexible!). A project is not “business as usual,” but a process that is outside
the normal flow of work. Projects have a defined scope and a predefined budget and are often
executed by contractors or by staff members who are acting outside their everyday work roles.
ITS gives our customers some flexibility in defining a “project,” based on the customer’s
procurement process and guidelines from their auditors. ITS does not make a final ruling but has
developed the guidelines below for determining whether expenditures should be considered a
single project. The primary “rule of thumb” is that the purchaser document and consistently apply
a valid and defensible methodology for defining a project and that the purchaser look at each
project separately in regards to vendor selection. ITS suggests the following factors that may
determine the definition of an information technology project:
1. A project might be defined by the time frame of the purchases (e.g. all agency workstation
procurements for a fiscal year might be a single project; a technology training class would
typically be a single project). Note: The 2-way radio EPL specifically defines a "project" for
the purpose of the EPL purchase limit as the total expenditures for equipment and services
made by an agency from this EPL per fiscal year.
2. Funding source might define a project (e.g. if the funding sources place different requirements
on the purchasing entity, separate projects might be needed to accommodate these
requirements).
3. In some cases, location of equipment might determine a project (e.g. if each district office can
consider a different vendor and/or a different technical solution, these acquisitions could be
considered separate projects.)
4. Technical requirements can define a project (e.g. acquisition of several variations of desktop
workstations for an agency might be a single project, while the acquisition of desktop
workstations for the central office and of ruggedized laptops for the same agency’s mobile
units might be separate projects).
5. Potential for volume discount can define a project (i.e. Will aggregating requirements for
hardware, software, or services across time, locations, or funding sources potentially result in
significant cost savings to the state? Will using a competitive process potentially result in
better pricing? Note that the instructions for EPLs specify that published prices are not-to-
exceed amounts based on a quantity of one. Customers are encouraged to aggregate purchases
in order to negotiate for volume discounts from EPL vendors where applicable.)
6. Business functionality and proposed utilization of hardware, software, and services can define
a project. (e.g. multiple scanners purchased for general use across an agency might be a stand-
alone project; a scanner purchase for a specific application system for which other hardware,
software, and services are also being procured should probably be considered a part of the
larger project.)