11 MAC Pt. 7, R. 2.13
Maintenance and Service Criteria for Public Water Wells
Cite as 11 Miss. Admin. Code Pt. 7, R. 2.13
Maintenance and Service Criteria for Public Water Wells.
A.
General – Installation of pumps and well equipment shall be in accordance with
the manufacturer's recommendation and this regulation. All pumps and well
equipment shall be designed and installed so as to prevent contamination of the
well.
(1)
Licensing – Pump installation shall be performed either by a Water Well
Contractor holding an unrestricted license or by a restricted licensee who
specializes in pump installation and well service.
(2)
Location of pressure tanks and switches – Pressure tanks and switches
located above ground shall be on a concrete slab or preformed pad or
blocks. Tanks and switches installed below grade shall be in a concrete pit
or basement designed to be adequately drained, unless approved for direct
burial. A pressure tank may be buried provided the tank is designed for
that type installation. Tanks to be installed inside the bore of a water well
must be designed for that purpose and approved by the Commission.
(3)
Temporary seal – If the pump and well equipment are not installed immediately
upon completion of drilling, all openings to the well must be closed to prevent
pollution or vandalism. After pump installation, all open spaces must be sealed
off to prevent contamination of the ground water.
(4)
Drop pipe, wire, etc. – All drop pipe, wire, pumps, and other pumping equipment
to be installed in the well shall either be new or be disinfected with a solution of
at least 50 mg/l free chlorine; and it shall be installed in such a manner as to
permit removal and repair of all equipment. If equipment or tools are lost in the
well and not recovered, a statement describing the item or items lost shall be
attached to the well completion report submitted to MDEQ.
(5)
Prevention of contamination – Pumping equipment shall be installed in
such a manner as to prevent the entrance of contamination into the ground
water. Discharge pipes shall be fitted with devices which will prevent the
entrance of small animals.
(6)
Check valves – Pumping equipment installed and used in conjunction with
Chemigation, which is the practice of injecting agricultural chemicals into
irrigation lines in order to mix and distribute the chemicals with the water flowing
through the irrigation system, shall have either two check valves, or other means
of backflow prevention as may be approved by MDEQ, installed between the well
head and the point of introduction of any chemicals.
B.
Submersible pump installation
(1)
Check valves – Submersible Pumps shall have no less than 2 check valves
installed. One check valve must be installed above ground.
(2)
Wire -- Wire shall be secured to the drop pipe in a manner which will
support the weight of the wire and keep the wire close to the pipe.
(3)
Clamps -- All clamps used shall be all stainless steel.
C.
Jet pump installation
(1)
Check valves -- Jet Pumps shall have a check valve installed on the discharge
side of the pressure tank.
(2)
Clamps - All clamps used shall be all stainless steel.
D.
Turbine pump installation
(1)
Steel column pipe for line shaft turbine pumps – Steel column pipe for
turbine pump irrigation wells shall be standard weight flanged or threaded
steel pipe.
(2)
Plastic column pipe may be used for turbine pump installation provided
the pipe is designed and manufactured for that purpose.
E.
Pressure systems – All pressure systems will have a pressure relief valve installed
between the well seal and pressure switch.
F.
Power and control wiring - Licensees may run power and control wiring from a
disconnect box to water well equipment. A license issued pursuant to this
regulation does not authorize the licensee to alter the existing electrical service to
any building or structure or perform any other electrical work covered by the
National Electric Code (NEC) or local building codes.