11 MAC Pt. 7, R. 2.9
State Well Reports
Cite as 11 Miss. Admin. Code Pt. 7, R. 2.9
State Well Reports. The State Well Report will include sections for a driller’s log, a
well completion report, and a well modification report. The driller’s log portion of the report shall
be completed by the licensed contractor and submitted to MDEQ for all drilled wells and boreholes
that penetrate water bearing strata. Water well contractors drilling irrigation wells into the
Mississippi River Valley Alluvial Aquifer (MRVA) shall furnish a copy of the driller’s log to the
YMD Joint Water Management District (YMD) at the same time the original report is submitted to
MDEQ. Driller’s logs will not be required for geotechnical boreholes less than twenty-five (25)
feet in depth that do not encounter water bearing strata; environmental monitoring wells less than
twenty-five (25) in depth that are regulated under other state and federal environmental programs;
or small diameter wells or sampling holes less than fifty (50) feet in depth that are established with
direct push (geo-probe) equipment. If a water well is developed and completed by a water well
contractor immediately upon completion of drilling, both sections of the form shall be completed
by the contractor and the report submitted to MDEQ within thirty (30) days after completion of the
well. If for any reason a well is not developed and completed immediately upon completion of
drilling, the following procedure shall be followed:
A.
The driller’s log section of the well report form provided by MDEQ shall be completed
by the water well contractor who constructed the well or borehole and submitted to
MDEQ within thirty (30) days after completion of drilling. For all water wells and
boreholes, the driller’s log section of the report must be signed by an appropriately
licensed water well contractor. The driller’s log entries on the report form shall be
true, accurate, and complete. Portions of the form that may not be applicable shall
contain an entry to that effect. Incomplete or inaccurate submittals will be returned to
the licensee for completion or correction, but the 30-day filing period will not be
extended. If the properly-executed form is not on file with MDEQ by the end of the 30-
day period, the licensee will be deemed to be in non-compliance and may be subject to
penalties as prescribed by statute and this regulation. The water well contractor filing the
report shall keep a copy of the submittal and provide a copy to the owner of the well or
borehole. For geotechnical investigations, the licensee may submit boring logs generated
for a site report in lieu of the MDEQ form, provided the logs include all required
information.
B.
If a water well is completed by someone other than the water well contractor who
constructed the well, the owner of the well shall be responsible for providing a copy of
the state well report form containing the previously completed driller’s log to the licensee
responsible for completion of the well.
C.
The licensee who develops and completes the well shall fill out the well completion
section of the well report on the copy of the form containing the previously submitted
driller’s log and submit the completed report to MDEQ within thirty (30) days after
completion of the well. For all water wells, the well completion section of the report
must be signed by an appropriately licensed water well contractor. The entries on the
report form relating to well completion shall be true, accurate, and complete. Portions of
the form that may not be applicable shall contain an entry to that effect. Incomplete or
inaccurate submittals will be returned to the responsible licensee for completion or
correction, but the 30-day filing period will not be extended. If the properly-executed
form is not on file with MDEQ by the end of the 30-day period, the licensee will be
deemed to be in non-compliance and may be subject to penalties as prescribed by statute
and this regulation. The water well contractor filing the report shall keep a copy of the
submittal and provide a copy to the owner of the well.
D.
The well modification report shall be filed with MDEQ by the licensed water well
contractor within thirty (30) days after any major modification to, or rehabilitation of, an
existing well six (6) inches or greater in diameter. The report shall include the water use
permit number associated with the well and a detailed description of the work performed.
When a well that does not comply with current construction standards requires major
modifications or rehabilitation, the work shall include items necessary to bring the well
up to current minimum standards set forth in Rule 2.12.A.1.b., c. and d.