15 MAC Pt. 9, R. 6.11
Good Faith Efforts
Cite as 15 Miss. Admin. Code Pt. 9, R. 6.11
Good Faith Efforts.
In determining whether a CON-holder has made a good faith effort to implement
an approved project and to obligate the approved expenditure, the Department
may consider all relevant circumstances, including but not limited to:
1. Capital expenditures incurred to date;
2. Construction or renovation activities undertaken;
3. Financing commitments obtained or actively pursued;
4. Efforts to acquire land, equipment, or materials;
5. Staffing efforts, including recruitment and contracting;
6. Licensure or certification activities; and
7. Other implementation activities demonstrating intent and ability to complete
the approved project.
No single factor shall be dispositive. The Department shall evaluate the totality
of the circumstances in determining whether a good faith effort has been made.