15 MAC Pt. 9, R. 6.13
Documentation of Commencement of Construction and Substantial
Cite as 15 Miss. Admin. Code Pt. 9, R. 6.13
Documentation of Commencement of Construction and Substantial
Progress.
The following documentation may be reviewed to determine whether
commencement of construction or other preparation has been substantially
undertaken during a valid Certificate of Need period and whether the holder is
making a good faith effort to obligate approved expenditures.
A. Commencement of Construction — all of the following must be
demonstrated:
1. A letter from the Director of the Health Facilities Licensure and
Certification Division stating that final plans have been submitted and
approved, prepared by an architect or architectural firm licensed in
Mississippi, and that the site is approved.
2. A copy of a legally binding written contract executed by the holder and
a contractor to construct and complete the project within a reasonable
designated time, stating the specific capital expenditure amount
conforming to the amount previously approved.
3. A copy of the contractor’s Mississippi license.
4. A copy of the building permit issued by the applicable governing
authority, or if no building permit is required, a letter from the applicable
authority stating such.
5. A letter from the applicable governing authority that the proposed
project is in compliance with applicable zoning regulations, or if no
regulations exist, a letter to that effect.
6. A statement in writing that the proposed construction is not in violation
of the Coastal Wetlands Protection Act, Miss. Code Ann. § 49-27-1 et
seq., or any federal law pertaining to construction in a federally
designated wetlands area.
7. Documentary proof that a progress payment of at least one percent (1%)
of the total construction cost stated in the contract has been paid by the
holder to the contractor, exclusive of site preparation costs.
Page 52 — Mississippi State Department of Health
8. A written statement signed by the holder and the contractor that all site
preparation work has been completed.
9. A written statement signed by the holder and the contractor that actual
bona fide construction has commenced and describing the details of such
preliminary construction.
10. A copy of the Proceed to Construction Written Order previously given
to the contractor.
B. Other Preparation Substantially Undertaken During the Valid CON Period
— evidence may include but is not limited to:
For construction projects: acquisition of property (title, evidence of
payment); completion of topographic or boundary surveys; site preparation
(contractor selection, contract, evidence of payment); completion of site
development plan; and architectural plans and drawings (architect selection,
contract, evidence of payment, submission to Health Facilities Licensure and
Certification, and any letter of findings, comments, or approval of
commencement of construction).
For establishment of service: hiring or entering contracts with necessary staff
or medical professionals; submission of a fire/life safety code inspection
request; submission of an application for facility inspection or licensure; and
acquisition of equipment (title, lease, etc.).
C. Good Faith Effort to Obligate Approved Expenditure — documentation may
include, in addition to items under A and B above: documentation of capital
expenditure made to date; evidence that permanent financing has been
obtained if the approved capital expenditure has not been obligated; if
financing has not been obtained, evidence of fund commitment from a
lending institution; and evidence of contractual obligation to expend funds.