Cite as 15 Miss. Admin. Code Pt. 9, R. 6.3

Progress Reports. The CON-holder is required to submit a written progress report every six (6) months from the effective date of the Certificate of Need and upon project completion. Completion means when the approved project is sufficiently complete to be operational for the purpose for which the CON was issued. The holder shall certify each report and submit documentation demonstrating good faith effort to implement the CON by showing substantial progress. A fee of One Thousand Dollars ($1,000.00) shall be assessed for the processing and handling of six-month progress reports associated with extension requests and is payable to the Department by check, money order, or any other manner approved by the Department.