ARM 17.74.356

ARM 17.74.356. ASBESTOS PROJECT CONTROL MEASURES

Last amended: 2026Length: 72 wordsOfficial source

Cite as Mont. Admin. R. 17.74.356

(1) An asbestos contractor/supervisor shall: (a) be physically present at the work site when any permitted work is being conducted; (b) be available to all asbestos workers; and (c) ensure the asbestos project complies with the asbestos project permit and the project design. (2) Alternate control measures that are equivalent to those required under this subchapter may be used if written approval is obtained from the department in advance under ARM 17.74.353.
ARM 17.74.356: ARM 17.74.356. ASBESTOS PROJECT CONTROL MEASURES | Justis AI