NDAC 33.1-24-05-178
Monitoring and inspection
Cite as N.D. Admin. Code § 33.1-24-05-178
1.
During construction or installation, the liners (except in the case of existing portions of landfills
exempt from subsection 1 of section 33.1-24-05-177) and cover systems (for example,
membranes, sheets, or coatings) must be inspected for uniformity, damage, and imperfections
(for example, holes, cracks, thin spots, or foreign materials) immediately after construction or
installation:
a.
Synthetic liners and covers must be inspected by a qualified professional (for example, a
registered professional engineer) to ensure tight seams and joints and the absence of
tears, punctures, or blisters; and
b.
Soil based and admixed liners and covers must be inspected by a qualified professional
(for example, a registered professional engineer) for imperfections, including lenses,
cracks, channels, root holes, or other structural nonuniformities that may cause an
increase in the permeability of the liner or cover.
2.
While a landfill is in operation, it must be inspected weekly and after storms to detect evidence
of any of the following:
a.
Deterioration, malfunctions, or improper operation of run-on and runoff control systems;
b.
Proper functioning of wind dispersal control systems, where present; and
c.
The presence of leachate in and proper functioning of leachate collection and removal
systems, where present.
3.
Leak detection system.
a.
An owner or operator required to have a leak detection system under subsection 3 or 4 of
section 33.1-24-05-177 must record the amount of liquids removed from each leak
detection system sump at least once each week during the active life and closure period.
b.
After the final cover is installed, the amount of liquids removed from each leak detection
system sump must be recorded at least monthly. If the liquid level in the sump stays
below the pump operating level for two consecutive months, the amount of liquids in the
sumps must be recorded at least quarterly. If the liquid level in the sump stays below the
pump operating level for two consecutive quarters, the amount of liquids in the sumps
must be recorded at least semiannually. If at any time during the postclosure care period
the pump operating level is exceeded at units on quarterly or semiannual recording
schedules, the owner or operator must return to monthly recording of amounts of liquids
removed from each sump until the liquid level again stays below the pump operating
level for two consecutive months.
c.
"Pump operating level" is a liquid level proposed by the owner or operator and approved
by the department based on pump activation level, sump dimensions, and level that
avoids backup into the drainage layer and minimizes head in the sump.