NDAC 33.1-24-05-62
Closure - Time allowed for closure
Cite as N.D. Admin. Code ยง 33.1-24-05-62
1.
Within ninety days after receiving the final volume of hazardous wastes at a hazardous waste
management unit or facility, the owner or operator shall treat, remove from the unit or facility,
or dispose of onsite, all hazardous wastes in accordance with the approved closure plan. The
department may approve a longer period if the owner or operator complies with all applicable
requirements for requesting a modification to the permit and demonstrates that one or both of
the following subdivisions apply:
a.
The activities required to comply with this subsection will, of necessity, take longer than
ninety days to complete; or
b.
All of the following apply:
(1)
The hazardous waste management unit or facility has the capacity to receive
additional hazardous waste;
(2)
There is a reasonable likelihood that the owner or operator or another person will
recommence operation of the hazardous waste management unit or the facility
within one year;
(3)
Closure of the hazardous waste management unit or facility would be incompatible
with continued operation of the site; and
(4)
The owner or operator has taken and will continue to take all steps to prevent
threats to human health and the environment, including compliance with all
applicable permit requirements.
2.
The owner or operator shall complete partial and final closure activities in accordance with the
approved closure plan and within one hundred eighty days after receiving the final volume of
hazardous wastes at the hazardous waste management unit or facility. The department may
approve an extension to the closure period if the owner or operator complies with all
applicable requirements for requesting a modification to the permit and demonstrates that one
or both of the following subdivisions apply:
a.
The partial or final closure activities will, of necessity, take longer than one hundred
eighty days to complete; or
b.
All of the following apply:
(1)
The hazardous waste management unit or facility has the capacity to receive
additional hazardous waste;
(2)
There is reasonable likelihood that the owner or operator or another person will
recommence operation of the hazardous waste management unit or the facility
within one year;
(3)
Closure of the hazardous waste management unit or facility would be incompatible
with continued operation of the site; and
(4)
The owner or operator has taken and will continue to take all steps to prevent
threats to human health and the environment from the unclosed but not operating
hazardous waste management unit or facility, including compliance with all
applicable permit requirements.
3.
The demonstrations referred to in subsections 1 and 2 must be made as follows: The
demonstrations in subsection 1 must be made at least thirty days prior to expiration of the
ninety-day period in subsection 1; and the demonstration in subsection 2 must be made at
least thirty days prior to the expiration of the one hundred eighty-day period in subsection 2.