NDAC 43-02-02.2-60
Restoration sampling procedure
Cite as N.D. Admin. Code ยง 43-02-02.2-60
After notifying the department that mining in a production area is complete and that ground water
restoration has begun, the operator shall sample and complete an analysis of the baseline wells in the
mine production area or as directed by the department. The samples and analysis must be done
monthly and are to be conducted to assess the restoration values listed in the permit restoration table.
If this analysis indicates that approved restoration values have been achieved, the operator shall
submit to the department a written report of the results. After submitting the report, restoration sampling
shall be conducted every two months. The department is to receive copies of all analyses.