NDAC 43-05-01-05.1
Area of review and corrective action
Cite as N.D. Admin. Code ยง 43-05-01-05.1
1.
The storage operator shall prepare, maintain, and comply with a plan to delineate the area of
review for a proposed geologic sequestration project, periodically reevaluate the delineation,
and perform corrective action that meets the requirements of this section and is acceptable to
the commission. The requirement to maintain and implement a commission-approved plan is
directly enforceable regardless of whether the requirement is a condition of the permit. As a
part of the storage facility permit application, the storage operator shall submit an area of
review and corrective action plan that includes the following:
a.
The method for delineating the area of review, including the model to be used,
assumptions that will be made, and the site characterization data on which the model will
be based;
b.
A description of:
(1)
The reevaluation date, not to exceed five years, at which time the storage operator
shall reevaluate the area of review;
(2)
The monitoring and operational conditions that would warrant a reevaluation of the
area of review prior to the next scheduled reevaluation date;
(3)
How monitoring and operational data (e.g., injection rate and pressure) will be used
to inform an area of review reevaluation; and
(4)
How corrective action will be conducted to meet the requirements of this section,
including what corrective action will be performed prior to injection and what, if any,
portions of the area of review will have corrective action addressed on a phased
basis and how the phasing will be determined; how corrective action will be adjusted
if there are changes in the area of review; and how site access will be guaranteed
for future corrective action.
2.
The storage operator shall perform the following actions to delineate the area of review and
identify all wells that require corrective action:
a.
Predict, using existing site characterization, monitoring and operational data, and
computational modeling, the projected lateral and vertical migration of the carbon dioxide
plume and its associated pressure front in the subsurface from the commencement of
injection activities until the plume movement ceases, or until the end of a fixed time
period as determined by the commission. The model must:
(1)
Be based on detailed geologic data collected to characterize the injection zone,
confining zone, and any additional zones; and anticipated operating data, including
injection pressures, rates, and total volumes over the proposed life of the geologic
sequestration project;
(2)
Take into account any geologic heterogeneities, other discontinuities, data quality,
and their possible impact on model predictions; and
(3)
Consider potential migration through faults, fractures, and artificial penetrations.
b.
Using methods approved by the commission, identify all penetrations, including active
and abandoned wells and underground mines, in the area of review that may penetrate
the confining zone. Provide a description of each well's type, construction, date drilled,
location, depth, record of plugging and completion, and any additional information the
commission may require; and
c.
Determine which abandoned wells have been plugged or operating wells have been
constructed in the area of review in a manner that prevents the movement of the injected
carbon dioxide or other fluids that may endanger underground sources of drinking water,
including use of materials compatible with the carbon dioxide stream.
3.
The storage operator shall perform corrective action on all wells in the area of review that are
determined to need corrective action, using methods designed to prevent the movement of
fluid into or between underground sources of drinking water, including use of materials
compatible with the carbon dioxide stream, where appropriate.
4.
At the reevaluation date, not to exceed five years, as specified in the area of review and
corrective action plan, or when monitoring and operational conditions warrant, the storage
operator shall:
a.
Reevaluate the area of review in the same manner specified in subdivision a of
subsection 2;
b.
Identify all wells in the reevaluated area of review that require corrective action in the
same manner specified in subsection 2;
c.
Perform corrective action on wells requiring corrective action in the reevaluated area of
review in the same manner specified in subsection 3; and
d.
Submit an amended area of review and corrective action plan or demonstrate to the
commission through monitoring data and modeling results that no amendment to the plan
is needed. Any amendments to the plan are subject to the commission's approval, must
be incorporated into the permit, and are subject to the permit modification requirements.
5.
The emergency and remedial response plan and the demonstration of financial responsibility
must account for the area of review, regardless of whether or not corrective action in the area
of review is phased.
6.
All modeling inputs and data used to support area of review delineations and reevaluations
must be retained until project completion. Upon project completion, the storage operator shall
deliver the records to the commission.