NV Bulletin 03-004
Minimum Threshold for Consolidated Insurance Programs
Bulletin No. 03- 004 June 30, 2003
MINIMUM THRESHOLD FOR CONSOLIDATED
INSURANCE PROGRAMS
The eligibility requirements for Consolidated Insurance Programs are defined in Chapter
616B of the Nevada Revised Statutes (NRS). NRS 616B.710 sets the initial minimum estimated
total cost of a construction project to be $150 million for such a program. On June 30 of each
year, the Commissioner is required to adjust the minimum estimated total cost of a construction
project to reflect the present value of that amount with respect to the “construction cost index.”
NRS 616B.710(4)(a) states, “ ‘Construction cost index’ means the construction cost
index published by the Engineering News-Record as a measure of inflation.”
Effective July 1, 2003, the minimum estimated total cost of a construction project must
be $164 million for the project to be eligible for a Consolidated Insurance Program.
____________________________________
ALICE A. MOLASKY-ARMAN