OAC 252:626-3-6
Engineering report
Cite as Okla. Admin. Code § 252:626-3-6
(a) Copies and timing. Submit 3 copies of an approvable engineering report as required in
OAC 252:626-3-2 for proposed new construction or modifications to PWS systems, at least 30
days prior to the submission of the application for a permit to construct.
(b) Purpose. The purpose of the report is to present the Engineer's findings with enough
attention given to detail(s) to allow adequate review of the project by the owner and applicable
regulatory agencies.
(c) Requirements. The report must include all information necessary for a comprehensive
evaluation of the proposed construction. The report must present, at a minimum, the following:
(1) General information. Include the following:
(A) a description of existing water works and wastewater facilities,
(B) identification of the municipality or area served,
(C) name and mailing addresses of the owner and official custodian,
(D) a statement as to whether the project will be constructed in phases. If the project is to
be constructed in phases, the statement will include the number of phases necessary to
complete the project and which portions of the project will be completed in each phase,
(E) a demonstration that adequate capacity, treatment and compliance with the primary
drinking water standards are maintained during construction,
(F) a letter from the permittee approving the contents contained in the engineering report
as submitted,
(G) a map showing legal and natural boundaries of entire service area, and
(H) a map showing new service areas or annexed areas.
(2) Extent of water works system. Include the following:
(A) a description of the area to be served,
(B) provisions for extending the waterworks system,
(C) establish the anticipated design average and peak flows for existing and potential
industrial, commercial, institutional and other water supply needs for both the current
service area and potential future service areas,
(D) a hydraulic analysis that demonstrates that a minimum of 25 psi shall be met at all
times throughout the distribution system, and
(E) a site plan and schematic layout of treatment facilities.
(3) Alternate plan. Where feasible and practical, provide a minimum of 3 alternative
solutions and discuss the alternatives, including cost estimates and reasons for selecting the
one recommended.
(4) Soil, ground water conditions, and foundation problems. The report must include a
description of the following:
(A) the character of the soil where water mains are to be laid,
(B) soil conditions, which might affect foundations of proposed structures, and
(C) the approximate elevation of ground water in relation to subsurface structures.
(5) Water use data. Provide the following water use data:
(A) a description of the population trends as indicated by available records, and the
estimated population which will be served by the proposed water supply system or
expanded system,
(B) present water consumption of existing systems and the projected average and
maximum daily demands that were used as the basis of the design, and
(C) present or estimated yield of supply source(s) along with a copy of the water rights
verification form and/or the purchase water contract.
(6) Fire flow requirements. Demonstrate that the plans meet the requirements regarding
fire flows pursuant to the International Fire Code, published by the International Code
Council, Inc., 2003 Edition, Distribution System Requirements for Fire Protection, M 31,
published by the AWWA, 3rd Edition or other recommendations of similar organizations for
the fire service area.
(7) Sewer system available. Describe the methods of disposal for sanitary and all other
wastewater from the treatment plant.
(8) Sources of water supply. For the alternative chosen, the report must describe the
proposed source or sources of water supply to be developed, the reasons for their selection,
and provide information required by OAC 252:626-7 and the following:
(A) surface water sources, including:
(i) hydrological data, stream flow and weather records,
(ii) safe yield, including all factors that may affect it,
(iii)maximum flood or pool elevation,
(iv) description of watershed, noting any existing or potential sources of
contamination which may affect water quality, and
(v) quality of the raw water with special reference to fluctuations.
(B) ground water sources, including:
(i) sites considered,
(ii) advantages of the site selected,
(iii)elevations with respect to surroundings,
(iv) character of formations through which the source is to be developed,
(v) geologic conditions affecting the site,
(vi) summary of exploration; test well depth and method of construction; placement of
liners or screen; test pumping rates and duration; water levels and specific capacity;
chemical and radiological quality of the water,
(vii) sources of possible contamination including but not limited to wastewater
collection and treatment facilities, landfills, outcroppings of consolidated water-
bearing formations, waste disposal wells, slush pits, irrigation wells and abandoned
wells, and
(viii) industrial and other private water supply. Where pertinent, use significant
ground water developments within a 1 mile radius of the proposed ground water
source, giving depths, size, protective casing depth, capacity, location, type and any
available information pertaining thereto.
(9) Proposed treatment processes. Summarize and determine the adequacy of proposed
processes and unit parameters for the treatment of the water under consideration. Pilot
studies may be required for innovative design. Post treatment for membrane systems shall be
in accordance with OAC 252:626-9-9 (f)(6).
(10) Residuals management. Submit a Residuals Management Plan that discusses the
wastes and volume generated by existing and proposed water treatment processes, their
volume, proposed treatment of waste products, points of discharge or method of disposal or
land application.
(11) Project sites. Address the following in the report:
(A) discussion of various sites considered and advantages of those recommended,
(B) the proximity of residences, industries, and other establishments, and
(C) any potential sources of pollution that may influence the quality of the supply or
interfere with effective operation of the water works system, including but not limited to,
absorption systems, septic tanks, privies, sink holes, sanitary landfills, refuse and garbage
dumps.
(12) Cost estimates. Address the following in the report:
(A) estimated cost of integral parts of the system,
(B) detailed estimated annual cost of operation, and
(C) proposed methods to finance both capital charges and operating expenses.
(13) Future extensions. Summarize future needs and services.
(14) Design-build. Authorized design-build projects may use the flexible construction
permitting process as approved in the engineering report, including:
(A) Label cover documents prominently as “Design-build”;
(B) Completed attestation form from applicant certifying that project is design-build;
(C) Description of design packages, including the number (maximum of six), scope of each
package, expected schedule of each package, and expected schedule of completion for major
construction items;
(D) The engineering report will address the entire scope of the project at 100% completion.