OAR 860-084-0210

OAR 860-084-0210. Capacity Reservation, Timing, and Duration

Last amended: 2011Length: 95 wordsOfficial source
(1) A capacity reservation expires if a completed interconnection application is not filed within two months of the reservation start date or if the system has not been installed within twelve months of the reservation start date, unless a waiver is granted under OAR 860-084-0000. Any delay resulting from the utility not completing required work to connect the eligible system to the grid will be excluded from this 12-month installation requirement. (2) Once the capacity reservation expires, the retail electricity consumer must newly apply for a capacity reservation and will not be given preferential treatment.
OAR 860-084-0210: OAR 860-084-0210. Capacity Reservation, Timing, and Duration | Justis AI