250-RICR-120-05-24
250-RICR-120-05-24. Removal of Lead Based Paint from Exterior Surfaces (version Technical Revision, 07/19/2007 to 07/19/2007)
24.1 Purpose
The purpose of this
regulation is to specify appropriate procedures for the removal of
lead based paint from exterior surfaces.
24.2 Authority
These regulations are
authorized pursuant to R.I. Gen. Laws § 42-17.1-2(19) and Chapter
23-23, and have been promulgated pursuant to the procedures set forth
in the R.I. Administrative Procedures Act, R.I. Gen. Laws Chapter
42-35.
24.3 Application
The terms and provisions of
this regulation shall be liberally construed to permit the Department
to effectuate the purposes of state laws, goals and policies.
24.4 Severability
If any provision of this
regulation or the application thereof to any person or circumstance,
is held invalid by a court of competent jurisdiction, the validity of
the remainder of the regulation shall not be affected thereby.
24.5 Definitions
A. Unless otherwise expressly
defined in this section, the terms used in this regulation shall be
defined by reference to Part 0 of this Subchapter (General
Definitions). As used in this regulation, the following terms shall,
where the context permits, be construed as follows:
1. "Abrasive blasting"
means the procedure of removing paint from a surface by forcefully
applying an abrasive material to the paint containing surface.
2. "HEPA" or "high
efficiency particulate air" means a filter capable of filtering
out particles of 0.3 microns or greater from a body of air at 99.97
percent efficiency or greater.
3. "Hydroblasting"
means any abrasive blasting using high pressure liquid as the
propelling force.
4. "Impenetrable
material" means a material that will not allow any spent
abrasives, paint, dust and/or other debris, including all residues
generated by wet paint removal operations, to penetrate through it.
5. "Lead-based substance"
means any paint or other surface coating material containing more
than 0.05 percent lead by weight calculated as lead metal in the
dried solid.
6. "Lead based paint"
means any surface coating material that contains more than 0.05
percent lead by weight calculated as lead metal in the dried solid.
7. "Mechanical paint
removal" means the use of any force, including but not limited
to manual, mechanical, electrical or other power, applied to a device
to remove paint from a surface.
8. "Paint" means any
surface coating material.
9. "Paint stripper"
means any chemical and/or caustic substance applied to a surface for
the purpose of removing paint.
10. "Representative
sample" means a sample of any paint, including a sample of each
layer of paint which is on a structure, that may and/or will be
removed from a structure.
11. "Sandblasting"
means abrasive blasting.
12. "Vacuum blasting"
means any abrasive blasting in which the spent abrasive, paint, dust
and/or other debris are immediately collected by a vacuum device.
13. "Wet abrasive
blasting" means any abrasive blasting using compressed air as
the propelling force in combination with water to contain the spent
abrasive, paint, particulate, dust and/or other debris generated by
the operations.
24.6 Applicability and Exemptions
24.6.1 Applicability
The provisions of this
regulation shall apply to all persons engaging in the removal of a
lead based substance from exterior surfaces of buildings and/or other
structures, unless exempted below.
24.6.2 Exemptions
Removal of paint, that is not
a lead based substance, from a surface shall be exempted from this
regulation. To qualify for this exemption, a representative sample
of any paint, which is to be removed from any surface, must be tested
prior to the initiation of paint removal and must contain no more
than 0.05% lead by weight calculated as lead metal in the dried
solid. The person performing the paint removal operation is
responsible for determining if lead paint is present on the
structure. Paint removal operations which are exempt from the
requirements of this regulation must comply with the requirements of
Part 5 of this Subchapter (Fugitive Dust).
24.7 Notification Requirements
A. The following persons shall
be notified in writing, by the person conducting the removal
operation, at least five days prior to the beginning of any lead
paint removal from the exterior surface of any structure:
1. Adults residing in the
structure from which the lead paint is being removed and/or residing
within 50 feet of the structure from which lead paint is being
removed, and,
2. The owner, agent, and/or
property manager of the structure from which the lead paint is being
removed and/or of any building located within 50 feet of the
structure from which lead paint is being removed, and,
3. The owner, agent or manager
of any business or organization located in the structure from which
the lead paint is being removed and/or within 50 feet of the
structure from which lead paint is being removed, and,
4. The principal of every
school and the chief administrative officer of every school within 50
feet of the structure from which lead paint is being removed.
B. The notification shall
include, at a minimum, the following information:
1. The location of the
structure from which the lead paint is to be removed,
2. The expected start and
completion dates for the lead paint removal project,
3. The lead paint removal
procedure to be used, and,
4. The name, address and
telephone number of the individual or company responsible for the
lead paint removal.
C. In addition, the
notification shall include the following statement: "The paint
which will be removed from this structure contains lead. Exposure to
lead is unhealthful, particularly to young children. Contact the
Department of Environmental Management, Office of Air Resources, at
222-2808 for more information."
D. Any and all parties
identified in § 24.7(A) of this Part must be notified in writing of
any changes in the information included in the original notice.
24.8 Requirements for Preparation
of Work Area:
A. The following procedures
must be followed prior to the initiation of lead paint removal from
any exterior surfaces of buildings:
1. Remove or cover with an
impenetrable material all toys, play equipment and furnishings within
a minimum of 50 feet, and/or any other distance which spent abrasive,
paint, particulate, dust and/or other debris generated by the removal
operations may travel, from a surface from which lead based paint is
being removed.
2. Place an impenetrable
material on the ground, at the paint removal worksite, to keep any
and all spent abrasive, paint, particulate, dust and/or other debris
generated by the paint removal operation from being deposited on the
ground. If a wet removal system is to be used, procedures must be
employed to contain any and all residues generated by the wet
abrasive blasting operations.
3. The ground sheeting must be
attached to ground by staking, weighing down or any other method to
insure that it remains in place during the paint removal operation.
4. If abrasive blasting,
machine sanding or machine scraping is to be employed, close all
doors and windows on the walls to be blasted or sanded and securely
seal them from the outside. Air conditioning units on these and
adjacent walls must be turned off and covered.
5. Erect vertical containment
shrouds if there is visible movement of abrasive material, paint,
dust and/or other debris beyond ground sheeting.
6. If a wet removal procedure
is to be used, a system must be in place prior to initiation of the
removal which allows liquid waste to be collected from the ground
containment and placed into appropriate containers for proper
disposal.
B. Site preparation for
exterior paint removal from structures other than buildings must be
adequate to prevent spent abrasive material, paint, particulate, dust
and/or other debris from being deposited on the ground or in water or
travelling offsite. Prior to removing paint from structures other
than buildings, the person performing the paint removal work and/or
the contractor responsible for the removal operation must submit a
plan, that describes the procedure to be employed, to the Office of
Air Resources for approval. The paint removal operation must not be
initiated until written approval is issued by the Department.
24.9 Requirements for Removal of
Lead Paint Using Heat Based Methods
A. Open flame burning shall
not be used to remove paint from exterior surfaces.
B. Heat guns and/or any other
device used for removal of paint from exterior surfaces must be
operated such that the temperature of the gun and/or other device
does not exceed 1000 o F.
24.10 Requirements for Removal of
Lead Paint Using Chemical Based Methods
A. Flammable paint strippers
and paint strippers containing methylene chloride shall not be used
to remove paint from exterior surfaces.
B. Non-flammable paint
strippers which do not contain methylene chloride may be used for the
removal of exterior paint provided that the manufacturer's
instructions for use of the paint stripper are followed.
24.11 Requirements for Removal of
Lead Paint Using Mechanical Methods
A. Machine sanding and/or
machine scraping shall be allowed only if the unit is controlled by a
HEPA vacuum unit which immediately collects any and all spent
abrasive, paint, particulate, dust and/or other debris generated by
the operations. The sanding and/or scraping disk must not be wider
than the direct surface upon which it is being applied.
B. Exterior surfaces must be
misted with water prior to manual scraping. Dry scraping is not
allowed.
24.12 Requirements for Removal of
Lead Paint Using Abrasive Blasting
A. Dry abrasive blasting shall
be allowed only if any and all spent abrasive, paint, particulate,
dust and/or other debris generated by the blasting is immediately
collected by a HEPA vacuum unit. Any person using a vacuum blast
system must comply with the manufacturers' guidelines when using the
system.
B. Hydroblasting or wet
abrasive blasting may be used for exterior lead paint removal
provided that a vertical containment system is employed that prevents
any and all fallout generated by the operation from travelling beyond
the ground containment. Additionally, any and all liquid waste
generated by the operation must be adequately contained and handled
in accordance with applicable waste disposal regulations.
24.13 Alternative Procedures for
Removal of Paint Containing Lead
The Department may, on a case
by case basis, allow an alternative procedure for removing paint
containing lead provided that the person who uses this procedure
shall submit to the Office of Air Resources, in writing, a
description of the procedure which demonstrates to the satisfaction
of the Department that the proposed alternative provides an
equivalent control efficiency to the methods which are contained in
§§ 24.9, 24.10, 24.11 and 24.12 of this Part. Use of an
alternative procedure shall not begin until a written approval is
issued by the Department.
24.14 Requirements for Site
Cleanup
A. At the end of each workday,
the following procedures must be followed:
1. If a dry removal procedure
was used, spray any and all spent abrasive, paint, particulate, dust
and/or other debris present on ground sheeting and/or other
containments with a fine mist of water and collect the residue and
place it in an appropriate container.
2. Visually inspect all areas,
including areas that extend beyond the sheeted area, to determine
whether any spent abrasive, paint, particulate, dust and/or other
debris has escaped containment. If any spent abrasive, paint,
particulate, dust and/or other debris generated by the lead paint
removal operation is observed it must be collected and placed in
single 6-mil or double 4-mil plastic bags or another appropriate
container.
3. If bags are used they must
not be overloaded. Bags must be securely sealed and stored in such a
way that they are not easily accessible to the public.
4. Liquid waste must be
collected and stored in appropriate containers. Containers must be
securely sealed and stored in a manner such that they are not easily
accessible to the public.
5. Plastic sheets used for
exterior containments, such as ground sheeting and vertical shrouds,
must be removed and stored in a manner such that they are not easily
accessible to the public.
B. At the completion of a lead
paint removal project, or at the time when all lead paint that is to
be removed from a structure has been removed, the following
procedures must be implemented:
1. Spray the ground sheeting
as specified in § 24.14(A)(1) of this Part. Any and all residue
must be collected and placed in an appropriate container. Ground
sheeting should then be folded from the ends to the middle and placed
into single 6-mil or double 4-mil plastic bags for disposal.
2. Collect any and all liquid
waste in appropriate containers.
3. As specified in §
24.14(A)(2) of this Part the area must be inspected for any spent
abrasive, paint, particulate, dust and/or other debris which may have
escaped containment and any and all such debris must be collected and
placed in single 6-mil or double 4-mil plastic bags or an appropriate
container.
4. Any and all bags and
containers must be securely sealed. Removal and disposal must be in
accordance with applicable solid and hazardous waste regulations.