250-RICR-120-05-24
250-RICR-120-05-24. Removal of Lead Based Paint from Exterior Surfaces (version Technical Revision, 07/19/2007 to 07/19/2007)
250-RICR-120-05-24
TITLE 250 - DEPARTMENT OF ENVIRONMENTAL MANAGEMENT
CHAPTER 120 - AIR RESOURCES
SUBCHAPTER 05 - AIR POLLUTION CONTROL
PART 24 - Removal of Lead Based Paint from Exterior Surfaces
24.1 Purpose
The purpose of this regulation is to specify appropriate procedures for the removal of
lead based paint from exterior surfaces.
24.2 Authority
These regulations are authorized pursuant to R.I. Gen. Laws § 42-17.1-2(19) and
Chapter 23-23, and have been promulgated pursuant to the procedures set forth in the
R.I. Administrative Procedures Act, R.I. Gen. Laws Chapter 42-35.
24.3 Application
The terms and provisions of this regulation shall be liberally construed to permit the
Department to effectuate the purposes of state laws, goals and policies.
24.4 Severability
If any provision of this regulation or the application thereof to any person or
circumstance, is held invalid by a court of competent jurisdiction, the validity of the
remainder of the regulation shall not be affected thereby.
24.5 Definitions
Unless otherwise expressly defined in this section, the terms used in this regulation
shall be defined by reference to Part 0 of this Subchapter (General Definitions). As used
in this regulation, the following terms shall, where the context permits, be construed as
follows:
"Abrasive blasting" means the procedure of removing paint from a surface by forcefully
applying an abrasive material to the paint containing surface.
"HEPA" or "high efficiency particulate air" means a filter capable of filtering out particles
of 0.3 microns or greater from a body of air at 99.97 percent efficiency or greater.
"Hydroblasting" means any abrasive blasting using high pressure liquid as the
propelling force.
"Impenetrable material" means a material that will not allow any spent abrasives, paint,
dust and/or other debris, including all residues generated by wet paint removal
operations, to penetrate through it.
"Lead-based substance" means any paint or other surface coating material containing
more than 0.05 percent lead by weight calculated as lead metal in the dried solid.
"Lead based paint" means any surface coating material that contains more than 0.05
percent lead by weight calculated as lead metal in the dried solid.
"Mechanical paint removal" means the use of any force, including but not limited to
manual, mechanical, electrical or other power, applied to a device to remove paint from
a surface.
"Paint" means any surface coating material.
"Paint stripper" means any chemical and/or caustic substance applied to a surface for
the purpose of removing paint.
"Representative sample" means a sample of any paint, including a sample of each layer
of paint which is on a structure, that may and/or will be removed from a structure.
"Sandblasting" means abrasive blasting.
"Vacuum blasting" means any abrasive blasting in which the spent abrasive, paint, dust
and/or other debris are immediately collected by a vacuum device.
"Wet abrasive blasting" means any abrasive blasting using compressed air as the
propelling force in combination with water to contain the spent abrasive, paint,
particulate, dust and/or other debris generated by the operations.
24.6 Applicability and Exemptions
24.6.1 Applicability
The provisions of this regulation shall apply to all persons engaging in the removal of a
lead based substance from exterior surfaces of buildings and/or other structures, unless
exempted below.
24.6.2 Exemptions
Removal of paint, that is not a lead based substance, from a surface shall be exempted
from this regulation. To qualify for this exemption, a representative sample of any paint,
which is to be removed from any surface, must be tested prior to the initiation of paint
removal and must contain no more than 0.05% lead by weight calculated as lead metal
in the dried solid. The person performing the paint removal operation is responsible for
determining if lead paint is present on the structure. Paint removal operations which are
exempt from the requirements of this regulation must comply with the requirements of
Part 5 of this Subchapter (Fugitive Dust).
24.7 Notification Requirements
A.
The following persons shall be notified in writing, by the person conducting the
removal operation, at least five days prior to the beginning of any lead paint
removal from the exterior surface of any structure:
1.
Adults residing in the structure from which the lead paint is being removed
and/or residing within 50 feet of the structure from which lead paint is
being removed, and,
2.
The owner, agent, and/or property manager of the structure from which
the lead paint is being removed and/or of any building located within 50
feet of the structure from which lead paint is being removed, and,
3.
The owner, agent or manager of any business or organization located in
the structure from which the lead paint is being removed and/or within 50
feet of the structure from which lead paint is being removed, and,
4.
The principal of every school and the chief administrative officer of every
school within 50 feet of the structure from which lead paint is being
removed.
B.
The notification shall include, at a minimum, the following information:
1.
The location of the structure from which the lead paint is to be removed,
2.
The expected start and completion dates for the lead paint removal
project,
3.
The lead paint removal procedure to be used, and,
4.
The name, address and telephone number of the individual or company
responsible for the lead paint removal.
C.
In addition, the notification shall include the following statement: "The paint
which will be removed from this structure contains lead. Exposure to lead is
unhealthful, particularly to young children. Contact the Department of
Environmental Management, Office of Air Resources, at 222-2808 for more
information."
D.
Any and all parties identified in § 24.7(A) of this Part must be notified in writing of
any changes in the information included in the original notice.
24.8 Requirements for Preparation of Work Area:
A.
The following procedures must be followed prior to the initiation of lead paint
removal from any exterior surfaces of buildings:
1.
Remove or cover with an impenetrable material all toys, play equipment
and furnishings within a minimum of 50 feet, and/or any other distance
which spent abrasive, paint, particulate, dust and/or other debris
generated by the removal operations may travel, from a surface from
which lead based paint is being removed.
2.
Place an impenetrable material on the ground, at the paint removal
worksite, to keep any and all spent abrasive, paint, particulate, dust and/or
other debris generated by the paint removal operation from being
deposited on the ground. If a wet removal system is to be used,
procedures must be employed to contain any and all residues generated
by the wet abrasive blasting operations.
3.
The ground sheeting must be attached to ground by staking, weighing
down or any other method to insure that it remains in place during the
paint removal operation.
4.
If abrasive blasting, machine sanding or machine scraping is to be
employed, close all doors and windows on the walls to be blasted or
sanded and securely seal them from the outside. Air conditioning units on
these and adjacent walls must be turned off and covered.
5.
Erect vertical containment shrouds if there is visible movement of abrasive
material, paint, dust and/or other debris beyond ground sheeting.
6.
If a wet removal procedure is to be used, a system must be in place prior
to initiation of the removal which allows liquid waste to be collected from
the ground containment and placed into appropriate containers for proper
disposal.
B.
Site preparation for exterior paint removal from structures other than buildings
must be adequate to prevent spent abrasive material, paint, particulate, dust
and/or other debris from being deposited on the ground or in water or travelling
offsite. Prior to removing paint from structures other than buildings, the person
performing the paint removal work and/or the contractor responsible for the
removal operation must submit a plan, that describes the procedure to be
employed, to the Office of Air Resources for approval. The paint removal
operation must not be initiated until written approval is issued by the Department.
24.9 Requirements for Removal of Lead Paint Using Heat Based
Methods
A.
Open flame burning shall not be used to remove paint from exterior surfaces.
B.
Heat guns and/or any other device used for removal of paint from exterior
surfaces must be operated such that the temperature of the gun and/or other
device does not exceed 1000oF.
24.10 Requirements for Removal of Lead Paint Using Chemical Based
Methods
A.
Flammable paint strippers and paint strippers containing methylene chloride shall
not be used to remove paint from exterior surfaces.
B.
Non-flammable paint strippers which do not contain methylene chloride may be
used for the removal of exterior paint provided that the manufacturer's
instructions for use of the paint stripper are followed.
24.11 Requirements for Removal of Lead Paint Using Mechanical
Methods
A.
Machine sanding and/or machine scraping shall be allowed only if the unit is
controlled by a HEPA vacuum unit which immediately collects any and all spent
abrasive, paint, particulate, dust and/or other debris generated by the operations.
The sanding and/or scraping disk must not be wider than the direct surface upon
which it is being applied.
B.
Exterior surfaces must be misted with water prior to manual scraping. Dry
scraping is not allowed.
24.12 Requirements for Removal of Lead Paint Using Abrasive
Blasting
A.
Dry abrasive blasting shall be allowed only if any and all spent abrasive, paint,
particulate, dust and/or other debris generated by the blasting is immediately
collected by a HEPA vacuum unit. Any person using a vacuum blast system must
comply with the manufacturers' guidelines when using the system.
B.
Hydroblasting or wet abrasive blasting may be used for exterior lead paint
removal provided that a vertical containment system is employed that prevents
any and all fallout generated by the operation from travelling beyond the ground
containment. Additionally, any and all liquid waste generated by the operation
must be adequately contained and handled in accordance with applicable waste
disposal regulations.
24.13 Alternative Procedures for Removal of Paint Containing Lead
The Department may, on a case by case basis, allow an alternative procedure for
removing paint containing lead provided that the person who uses this procedure shall
submit to the Office of Air Resources, in writing, a description of the procedure which
demonstrates to the satisfaction of the Department that the proposed alternative
provides an equivalent control efficiency to the methods which are contained in §§ 24.9,
24.10, 24.11 and 24.12 of this Part. Use of an alternative procedure shall not begin until
a written approval is issued by the Department.
24.14 Requirements for Site Cleanup
A.
At the end of each workday, the following procedures must be followed:
1.
If a dry removal procedure was used, spray any and all spent abrasive,
paint, particulate, dust and/or other debris present on ground sheeting
and/or other containments with a fine mist of water and collect the residue
and place it in an appropriate container.
2.
Visually inspect all areas, including areas that extend beyond the sheeted
area, to determine whether any spent abrasive, paint, particulate, dust
and/or other debris has escaped containment. If any spent abrasive,
paint, particulate, dust and/or other debris generated by the lead paint
removal operation is observed it must be collected and placed in single 6-
mil or double 4-mil plastic bags or another appropriate container.
3.
If bags are used they must not be overloaded. Bags must be securely
sealed and stored in such a way that they are not easily accessible to the
public.
4.
Liquid waste must be collected and stored in appropriate containers.
Containers must be securely sealed and stored in a manner such that they
are not easily accessible to the public.
5.
Plastic sheets used for exterior containments, such as ground sheeting
and vertical shrouds, must be removed and stored in a manner such that
they are not easily accessible to the public.
B.
At the completion of a lead paint removal project, or at the time when all lead
paint that is to be removed from a structure has been removed, the following
procedures must be implemented:
1.
Spray the ground sheeting as specified in § 24.14(A)(1) of this Part. Any
and all residue must be collected and placed in an appropriate container.
Ground sheeting should then be folded from the ends to the middle and
placed into single 6-mil or double 4-mil plastic bags for disposal.
2.
Collect any and all liquid waste in appropriate containers.
3.
As specified in § 24.14(A)(2) of this Part the area must be inspected for
any spent abrasive, paint, particulate, dust and/or other debris which may
have escaped containment and any and all such debris must be collected
and placed in single 6-mil or double 4-mil plastic bags or an appropriate
container.
4.
Any and all bags and containers must be securely sealed. Removal and
disposal must be in accordance with applicable solid and hazardous waste
regulations.