510-RICR-00-00-5
510-RICR-00-00-5. RISBC-5 Rhode Island Electrical Code (version Amendment, 07/23/2002 to 01/01/2006)
RHODE ISLAND
STATE BUILDING CODE
Electrical Code
Regulation SBC-5
AUGUST 1, 2002
Replaces Regulation SBC-5-98
Revised April 1, 1998
STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS
Department of Administration
BUILDING CODE STANDARDS COMMITTEE
One Capitol Hill
Providence, Rhode Island 02908-5859
(401) 222-3033
FAX NO (401) 222-2599
State Electrical Code
Regulation SBC-5
AUGUST 1, 2002
The Building Code Standards Committee, in accordance with the rule making authority of
Title 23, Chapter 23-27.3, Section 109.1, paragraph a through c inclusive hereby adopts
the provisions of the National Electrical Code, 2002 edition, as published by the National
Fire Protection Association, as the Rhode Island Electrical Code, together with the
amendments thereto hereinafter set forth to the chapters and sections of said code:
GENERAL
Delete all references to IEC and substitute Rhode Island Electrical Code SBC-5.
Delete all reference to any other International Code (IBC, IRC, IMC, etc.) and refer to
appropriate SBC regulations. (See Amendment 2701.6).
NFPA 70-02 may also be referenced as NEC 02 and are one and the same document.
Article 80 of NFPA 70-02 is specifically not adopted.
ARTICLE 90
90.1
Add the following to 90.1.
E) The installation of all work shall be accomplished by persons licensed
by the State of Rhode Island, Department of Labor and Training,
Division of Professional Regulation of Electricians, Title 5, Chapter 6,
and Telecommunications Chapter 5-70 of the General Laws of the State
of Rhode Island.
90.4 Delete 90.4 and substitute the following:
90.4 Enforcement. This Code is intended to be suitable for mandatory
application by governmental bodies that exercise legal jurisdiction over
electrical installations and for use by insurance inspectors. The Committee
shall have the responsibility for deciding upon the approval of New
Materials and Methods of Construction in accordance with SBC-12. The
Commissioner shall have the responsibility to issue official interpretations
in accordance with SBC-10. The authority having jurisdiction will have the
responsibility for granting special permission contemplated in a number of
the rules.
The authority having jurisdiction may waive specific requirements in this
Code or permit alternate methods where it is assured that equivalent
objectives can be achieved by establishing and maintaining effective safety.
This Code may require new products, constructions, or materials that may
not yet be available at the time the Code is adopted. In such event, the
authority having jurisdiction may permit the use of the products,
constructions, or materials that comply with the most recent previous
edition of this Code adopted by the jurisdiction.
90.6 Delete 90.6 and substitute the following:
90.6 Formal Interpretations. To promote uniformity of
interpretation and application of the provisions of this Code, formal
interpretation procedures have been established and are found in the NFPA
Regulations Governing Committee Projects.
Formal interpretations issued by the NFPA are advisory in nature and are
not binding on the local authority having jurisdiction unless reissued as a
formal opinion by the Commissioner.
90.10 Add the following new Article 90.10:
90.10 Other Provisions. The provisions of Chapter 27 of SBC-1-2002 are herein
incorporated by reference and are considered part of this code. Enclosed
herein is Article 27 effective this date. See SBC-1-2002 for any future
amendments.
110.2 Add the following new paragraph after the FPN:
Except as modified by the authority enforcing this Code, plans,
specifications, schedules and calculations in sufficient detail shall be filed
with the authority enforcing this Code, showing the location, and capacity
of all lighting facilities, and all electrically operated equipment including
power circuits required for all electrical service equipment of the building
or structure. Details shall include available fault current at each protective
device. Details shall include showing all raceways, cables and or circuiting
on plans.
The following revisions are to Chapter 27 of SBC-1-98:
Delete existing Chapter 27 in its entirety and substitute the following:
2701.1 Scope. This chapter governs the electrical components, equipment and
systems used in buildings and structures covered by this code. Electrical
components, equipment and systems shall be designed and constructed in
accordance with the provisions of SBC-5-2002.
2701.2 Permits. Electrical wiring including elevators and other conveyances as
regulated by the Department of Labor and Training, or data,
telecommunications, video and sound installations, shall not be installed in
a building or structure, nor shall alteration of an existing electrical wiring
system be made until a permit has been issued therefor as required in
Section GL 23-27.3-113.3.1.
Exception: Work not covered in SBC-5-2002 section 90.2(b) 1-5
inclusive. As used in section 4 & 5 a “utility” is a company or business
regulated and/or licensed by the Rhode Island Public Utilities Commission.
Subcontractors employed by a utility are not exempt from permit
requirements unless the proposed work is being performed in the public
right-of-way or within public utility easements. It shall be unlawful to use
or allow the use of, or to supply current for, an electrical system in a
building or structure, or to allow the use of, or to supply current for data,
telecommunications, video or audio installations unless the required permits
have been issued and approved by the authority having jurisdiction.
2701.3 Certification. Except for use group R (residential use), construction
documents shall bear the seal of a Registered Professional Engineer who
shall provide the services as required by 23-27.3-128.2.2, except as
modified by the authority enforcing this Code.
2701.4 Re-inspection. An electrical installation from which an electrical service
has been discontinued for a period of thirty (30) days or more shall not have
service restored until the system has been re-inspected and a new certificate
of inspection issued.
Exception: Re-inspection of dwelling units shall only be required if the
electrical service has been discontinued for a period of one year.
2701.5 The following section is taken directly from current R.I. General Laws (RIGL 42-
66.9-1):
2701.5 Emergency generators for Housing for the Elderly. All housing for the
elderly complexes, as defined in § 42-66.1-2 which are serviced by one or more
elevators and/or electrically powered chair lifts, and which include more than one
hundred fifty (150) residential living units in a single building shall be equipped
with emergency generators which shall provide sufficient power to provide
emergency lighting to all common areas and a community room and power to
operate the elevators and a refrigerator in a common area. Generator systems shall
be in accordance with the national electric code and § 23-28.24-9.
2701.6 References. Where this code references other ICC codes, use the
International Building Code, 2000 edition and SBC-5-2002 for the IEC.
References to the International Fire Code (IFC) shall also refer to the R.I. State Fire
Safety Code for enforcement as required by that authority having jurisdiction.
2701.7 Other Codes. The Rhode Island Fire Safety Code contains provisions for
specific wiring methods for fire alarms, signaling systems, and other
building fixtures such as exit signage, emergency lighting, and emergency
and standby power systems among others. Refer to the latest editions of
that code for the latest provisions.
SECTION 2702
EMERGENCY AND STANDBY POWER SYSTEMS
2702.1 Installation. Emergency and standby power systems shall be installed in
accordance with the ICC Electrical Code, NFPA 110 and NFPA 111.
2702.2 Where required. Emergency and standby power systems shall be provided where
required by Sections 2702.2.1 through 2702.2.19.
2702.2.1 Group A Occupancies. Emergency power shall be provided for voice
communication systems in Group A occupancies in accordance with Section
907.2.1.2.
2702.2.2 Smoke control systems. Standby power shall be provided for smoke
control systems in accordance with Section 909.11.
2702.2.3 Exit signs. Emergency power shall be provided for exit signs in
accordance with Section 1003.2.10.5.
2702.2.4 Means of egress illumination. Emergency power shall be provided for
means of egress illumination in accordance with Section 1003.2.11.2.
2702.2.5 Accessible means of egress elevators. Standby power shall be provided
for elevators that are part of an accessible means of egress in accordance with
Section 1003.2.13.3.
2702.2.6 Horizontal sliding doors. Standby power shall be provided for
horizontal sliding doors in accordance with Section 1003.3.1.3.3.
2702.2.7 Semiconductor fabrication facilities. Emergency power shall be
provided for semiconductor fabrication facilities in accordance with Section
415.9.10.
2702.2.8 Membrane structures. Standby power shall be provided for auxiliary
inflation systems in accordance with Section 3102.8.2. Emergency power shall be
provided for exit signs in temporary tents and membrane structures in accordance
with the International Fire Code.
2702.2.9 Hazardous materials. Emergency or standby power shall be provided
in occupancies with hazardous materials in accordance with Section 414.5.4.
2702.2.10 Highly toxic and toxic materials. Emergency power shall be provided
for occupancies with highly toxic to toxic materials in accordance with the
International Fire Code.
2702.2.11 Organic peroxides. Standby power shall be provided for occupancies
with organic peroxides in accordance with the International Fire Code.
2702.2.12 Pyrophoric materials. Emergency power shall be provided for
occupancies with pyrophoric materials in accordance with the International Fire
Code.
2702.2.13 Covered mall buildings. Covered mall buildings exceeding 50,000
square feet (4645 m2) shall be provided with standby power systems which are
capable of operating the emergency voice/alarm communication.
2702.2.14 High rise buildings. Emergency and standby power shall be provided
in high rise buildings in accordance with Chapter 27 and for the items listed below:
1.
Fire command center.
2.
Fire pumps.
3.
Emergency voice/alarm communication systems.
4.
Lighting for mechanical equipment rooms.
5.
Elevators.
2702.2.15 Underground buildings. Emergency and standby power shall be
provided in underground buildings in accordance with Sections 405.9 and 405.10.
2702.2.16 Group I-3 occupancies. Emergency power shall be provided for doors
in Group I-3 occupancies in accordance with Section 408.4.2.
2702.2.17 Airport traffic control towers. Standby power shall be provided in
airport traffic control towers in accordance with Section 412.1.5.
2702.2.18 Elevators. Standby power for elevators shall be provided as set forth
in Section 3003.1.
2702.2.19 Smoke proof enclosures. Standby power shall be provided for smoke
proof enclosures as required by Section 909.20.
2702.3
Maintenance. Emergency and standby power systems shall be maintained
and tested in accordance with the International Fire Code.