510-RICR-00-00-9
510-RICR-00-00-9. RISBC-9 Enforcement and Implementation Procedure (version Periodic Refile, 12/19/2001 to 08/01/2007)
RHODE ISLAND
STATE BUILDING CODE
Enforcement and Implementation
Procedure for Projects Under the Jurisdiction of the State of Rhode
Island
Regulation SBC-9
APRIL 1, 1998
Replaces Regulation SBC-9-92
Dated January 1, 1992
STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS
Department of Administration
BUILDING CODE STANDARDS COMMITTEE
One Capitol Hill
Providence, Rhode Island 02908-5859
(401) 222-3032
FAX NO. (401) 222-2599
STATEMENT OF NEED
Pursuant to the State Building Code Chapter 23, Title 27.3, the Building Code Standards
Committee has promulgated Regulation SBC-9, as amended, dated April 1, 1998. In
accordance with section 23-27.3-109.1 paragraphs 1-4 of the Code, the Committee has
the authority to adopt appropriate rules and regulations when necessary to maintain the
State Building Code current with national model codes and standards.
STATE OF RHODE ISLAND
BUILDING CODE STANDARDS COMMITTEE
CHAIRMAN
VICE CHAIRMAN
J. Robert Wahlberg
Gordon Preiss, P.E.
Builder Heavy Construction
Reg. Prof. Engineer
(Mechanical)
EXECUTIVE COMMITTEE
Russell Brown
Building Official
Daniel Paquette
Builder
Donald Gagnon
Minimum Housing Inspector
Members
Frank Canario
Mark Lowenstein
Public Health Official
Representative of the Disabled
James Carlson
Frank Montanaro
Public Member
State Representative
John Cronin
Dana Newbrook
Plumber
Architect
Steve Durkee
Ronald Travers
Architect
Building Official
Thomas Lynch
Joseph Walsh
Builders Trades Council
Electrical Inspector
John Gaskell
William Lepore
Electrical Engineer
Electrical Contractor
Randall Collins
Donald Jacques
Landscape Architect
Representative of the Disabled
William Howe
Thomas Coffey
Fire Official
Legal Counsel
Richard Hanson
Joseph A. Cirillo
Public Member
State Building Commissioner
Executive Secretary
ENFORCEMENT AND IMPLEMENTATION PROCEDURES FOR
PROJECTS UNDER THE JURISDICTION
OF THE STATE OF RHODE ISLAND
REGULATION SBC-9
APRIL 1, 1998
SECTION 1 ADMINISTRATION
1.1
TITLE
As authorized by Chapter 23-27.3 of the General Laws of Rhode Island, 1956 as
amended, and in accordance with Sections 23-27.3-108.2 and 23-27.3-109.1 of the State
Building Code, the Building Code Standards Committee has promulgated the following
rules and regulations for enforcement and implementation of this Code by the State
Building Commissioner as to any structures or buildings or parts thereof that are owned
or are temporarily or permanently under the jurisdiction of the State of Rhode Island or
any of its departments, commissions, agencies or authorities and as to any structures or
buildings or parts thereof that are built upon any land owned by, or under the jurisdiction
of the State of Rhode Island or any of its departments, commissions, agencies or
authorities.
All other existing provisions shall remain in effect; amend section 1, 2, and 3 as follows:
1.2
ENFORCEMENT
The provisions of Title 23, Chapter 27.3, Article 1, Administration and Enforcement,
shall apply to all projects under the jurisdiction of the State Building Commissioner.
1.3
DESIGN AND CONSTRUCTION PROCEDURES
The following provisions of section 23-27.3-128.0 shall be enforced for design and
construction control for projects under the jurisdiction of the Commission.
SBC9-1
23-27.3-128.0 Design and Construction Procedures
23-27.3.-128.1 Scope: The provisions of this section shall define the responsibility
required of the owner, architect, engineer, contractor and Building Official during the
design, construction and testing process for new or renovated buildings or structures.
128.1.1. Owners Responsibilities:
1. The owner shall be responsible for providing the services as required in section 23-
27.3-128.3 (1) (3).
2. When the owner retains, or is required by the building official to retain the services of
an architect or engineer who shall provide the services as required in Sections 23-
27.3-128.2.2.
3. The building official shall require the owner to certify to the requirements of items 1
or 2 prior to the issuance of a permit to the owner or his agent.
23-27.3-128.2 Architect/Engineer Responsibilities:
23-27.3-128.2.1 Drawings and Specifications: All drawings, specifications and
computations for new construction, alteration, repair, or expansion work involving the
practice of professional engineering or architecture as defined by Rhode Island State
Law, shall be prepared by professional engineers or registered architects as licensed or
registered by the State of Rhode Island. All said drawings, computations and
specifications required for a building permit application for such work must be prepared
by or under the direct supervision of a professional engineer or registered architect and
bear his signature and seal in accordance with the Rhode Island statutes and regulations
governing the professional licensing or registration of engineers or architects and shall
signify to the best of his knowledge that the drawings, computations and specifications
shall meet the applicable provisions of this code and acceptable engineering practices and
all applicable laws and ordinances.
SBC9-2
23-27.3-128.2.2 Responsibilities: A professional engineer or registered architect on
behalf of the owner shall be responsible for the following:
1. Review of the shop drawings, samples and other submittals of the contractor as
required by the construction contract documents submitted for permit and approval for
conformance to the design concept.
2. All change orders to the contract documents shall be submitted to the Building
Official after approval by the professional engineer or registered architect.
3. Review and approval of the testing procedures listed in Section 23-27.3-128.4 and
Appendix A. The engineer or architect shall notify the owner, building official and
contractor of any deviations and the required corrective measures taken.
4. Insure special engineering or architectural inspection of critical construction
components requiring controlled materials or construction specified in the accepted
engineering practice standards as listed in Appendix A.
5. The professional engineer or registered architect or his representative shall provide the
necessary professional services and be present on the construction site on a regular and
periodic basis to determine that, generally, the work is proceeding in accordance with the
documents approved for the permit.
23-27.3-128.2.3 Reporting: The professional engineer or registered architect shall submit
periodically in a form at regular construction inspection intervals acceptable to the
building official, a progress report together with pertinent comments. At the completion
of construction, the engineer or architect shall submit to the building official a report as to
the satisfactory completion and the readiness of the project for occupancy (accepting any
items not endangering such occupancy or operation and listing pertinent deviations from
the approved permit documents).
23-27.3-128.3 Construction Contractor Responsibilities: The actual construction of the
work shall be the responsibility of the owner or the contractor designated as his agent and
who shall:
SBC9-3
1. Perform all work in accordance with the construction documents on file with the
building official.
2. Perform all work in a safe and satisfactory manner in accordance with all applicable
local, state and federal statutes and regulations.
3. Upon completion of the construction shall certify to the best of his knowledge and
belief that such work has been done in substantial accord with items 1 and 2 above and
with all pertinent deviations.
128.4 Testing Required: The referenced standards listed in the appendices or the test of
this Code contain many field or agency tests which are required for the proper installation
or erection of any buildings or structure and its component structural, electrical,
mechanical, plumbing assemblies. It shall be the responsibility of the engineer or
architect to specify the tests as required by this code and its standards; the owner or the
contractor shall then secure the services of a laboratory to perform said test. The
engineer or the architect shall file the periodic test reports and report any deviations or
any corrective measures to be taken as required 23-27.3-128.2.2 (3).
Examples of Testing Required – among others:
1. Soil testing for loading conditions and water levels.
2. Concrete testing for strength i.e. slump test, cylinders, core tests, etc.
3. Structural steel testing for welds, bolts and rivets in accordance with industry
standards.
23-27.3-128.5 Building Official’s Responsibilities: The building official shall be
responsible for carrying out the duties and responsibilities as outlined in Article I of this
Code with regard to the issuing of permits, the maintenance of records, the performance
of inspections and any other administrative procedures except as may be specifically
exempt herein. Nothing contained in this section shall have the effect of waiving or
limiting the building official’s authority to enforce this Code with respect to examination
of the contract documents, including the plans, computations and specifications, and
related field inspections.
SBC9-4
23-27.3-128.5.1 Waiver of Plan Examination:- The examination of plans may be waived
when the plans for the erection or alteration of a building are prepared by a professional
engineer or architect and said professional engineer or architect has stated in writing that
he has supervised the preparation of the architectural, structural, electrical, plumbing and
mechanical design contract documents and that he will review and approve all working
drawings for said construction and that said document shall conform to all provisions of
this Code and all rules and regulations adopted under its provisions.
23-27.3-128.5.2 Waiver of Detailed Field Inspection:- The building official may waive
the detailed department field inspection when the professional engineer or architect
certifies that the construction work will be built under his field observations and in
accordance with the approved contract documents, and that he will certify to the best of
his knowledge, information and belief that the construction is in substantial, accordance
with said documents and that he will submit a report in compliance with Section 23-27.3-
128.2.3.
23-27.3-128.5.3: The building official may utilize this inspection waiver, in whole or in
part, but he must cause sufficient plan review and construction inspection by the building
official or staff to insure that:
1. The proposed usage and facilities are in conformance with the zoning ordinances and
this Code:
2. The contractor is maintaining the required construction safety; and
3. The professional engineer or registered architect is, in fact, providing the necessary
inspections; and
4. State approvals for septic systems, wetlands, and fire safety code provisions have
been submitted prior to the issuance of a permit by the building official.
23-27.3-128.5.4 Building Permit Issuance or Requirements:
This special professional service requirement shall be determined prior to the issuance of
any permits and shall be a prerequisite for the permit issuance. Refusal by the owner to
provide such service as required by the building official shall result in the denial of their
permit. However, the owner may file an appeal as provided in Sections 23-27.3-127.1 or
23-27.3-127.2.
SBC9-5
23-27.3-128.5.5 Fees and Costs: All fees and costs related to performance of special
professional services shall be borne by the owner.
23-27.3-128.6 Special Technical Services: When application for unusual designs or
magnitude of construction are filed, the building official may refer such plans and
specifications to the State Building Commissioner, or he may in his discretion, retain a
professional engineer or architect, for advice and recommendations as to said plans and
specifications, safety design and compliance with this Code. The building official may
also employ a professional engineer or architect to observe the construction in the field to
insure compliance with the approved plans and permit. Upon completion of the work the
architect or engineer employed, shall file with the building official a report to the effect
that to the best of his knowledge and belief, the building has been erected in accordance
with accepted engineering practice and in conformity to all the statutory provisions
governing building construction for the designated use group classification of the
building structure, in respect to use, fire grading, floor and occupancy loads. All fees and
costs related to the performance of special technical services shall be borne by the owner.
SECTION 2 APPEALS
2.1 GENERAL
Anyone aggrieved by a decision of the Commissioner may appeal to the State Board of
Appeals in accordance with the provisions of section 23-27.3.127.1 of the State Building
Code. No fee shall be charged to any state agency, department, commission or authority
for an appeal.
SBC9-6
SECTION 3.0 FEES STATE BUILDING PERMITS
NEW BUILDINGS, ADDITIONS, ALTERATIONS, STRUCTURES, ETC.
PERMIT FEE SCHEDULE
VALUATION
FEE FACTOR
FEE
FROM
0
TO
Less than $1000.00
$30.00
$30.00 Min.
$1000
$10,000
X
.03*
$30.00-$300.00
$10,001.00
$100,000
X
.012*
$120.00-$1,200.00
$100,001.00 No Limit
X
.01*
Note 1:
State owned properties leased to other than State Departments,
Commissions, Agencies or authorities are subject to the above schedule.
Note 2:
Projects occupied for or by State departments or agencies are subject to
the following modifications of the fee schedule.
a.
Individual projects performed exclusively by “in-house” forces shall be
subject to a minimum/maximum permit fee of $25.00.
Work performed exclusively by any outside contractor will be subject to
the permit schedule noted above.
b.
Working without a permit – An administrative fee of $50.00 shall be
charged whenever any work is performed without prior obtaining of a
permit.
c.
All fees shall be paid by check, money order or state form A-12T.
*
Multiply the cost of construction times (x) the permit fee factor.
SBC9-7 Effective 4/1/98
PLAN REVIEW FEES
The following shall be charged for performing plan reviews in order to determine code
compliance on behalf of local municipalities. Applications for plan reviews shall be
accompanied by a letter of authorization from the local building official and the required
plan review fee.
BUILDING VALUATION*
FEE
$0- $500,000.00
(.0020) (.20%) of building
valuation but not less than
$100.00
over $500,000.00
$1,000.00 plus .001 (.10%) of
building valuation over $500,000.00
(not charged to State Agencies)
*Based upon latest available BOCA Valuation Data Report
HEARING FEES
State Board of Standards and Appeals Hearing
Application Fee (not charged to state agencies)…$100.00
a.
Stenographic costs for hearing held on behalf of municipalities without
appeal boards shall be paid by each municipality.
DEMOLITION OR MOVING
(No revision of wrecking permits allowed)
Each residential building, accessory building or structure of use
group R3 or R4………………………………………………..$50.00
All other buildings or structures………………………………$100.00
SBC9-8 Effective 4/1/98
SPECIAL ENGINEERING FEES
Special engineering fees shall be a multiple of direct personnel costs as negotiated by the
Commissioner on each program or project requiring said services.
CODE BOOKS:
State Building Code SBC-1 – 1997…………………………………$55.00
Rhode Island Amendments only – 1997…………………………….$10.00
One and Two Family Dwelling Code SBC-2 – 1997………….……$35.00
Rhode Island Amendments only – 1997……………………….……$4.00
Plumbing Code SBC-3 – 1997………………………………………$50.00
Rhode Island Amendments only 1997………………………………$3.00
Mechanical Code SBC-4 – 1997……………………………….……$50.00
Rhode Island Amendments only – 1997…………………………….$3.00
Electrical Code SBC-5 – 1997………………………………….…...$40.00
Rhode Island Amendments only – 1997…………………………….$3.00
Rhode Island Energy Code SBC-8………………………………….$15.00
Rhode Island Amendments only…………………………………….$2.00
Rhode Island Accessibility Regulations SBC-14, 15 and 16………. $20.00
All other regulations are available at no cost.
*Cost includes state sales tax.
SBC9-9
Effective 4/1/98
STATE BUILDING CODE REGULATION – 1998
The following list includes all regulations promulgated by the State Building Code Standards Committee.
All regulations are available for a fee at the State Building Commission.
1.
Building Code…………………………………………SBC-1
2.
One and Two Dwelling Family
Dwelling Code………………………………………...SBC-2
3.
Plumbing Code………………………………………..SBC-3
4.
Mechanical Code……………………………………...SBC-4
5.
Electrical Code………………………………………..SBC-5
6.
Manufactured Buildings and Building Components….SBC-6
7.
ANSI A225.1
Manufactured Home
Installation Standard…………………………………..SBC-7
8.
State Energy Code…………………………………….SBC-8
9.
Enforcement and Implementation
Procedures for Projects Under
the Jurisdiction of the State
of Rhode Island……………………………………….SBC-9
10.
Code Interpretations…………………………………..SBC-10
11.
Certification of Building Officials,
Building, Electrical, Plumbing and
Mechanical Inspectors………………………………..SBC-11
12.
New Materials and Methods
of Construction……………………………………….SBC-12
13.
State Building Code
For Existing Schools………………………………….SBC-13
14.
Accessibility for Individuals with
Disabilities for Residential Use
Groups R-2 and R-3…………………………………..SBC-14
15.
Accessibility for Individuals with
Disabilities in State and Local
Government Facilities………………………………...SBC-15
16.
Accessibility for Individuals with
Disabilities…………………………………………….SBC-16
17.
Public Buildings Accessibility
Meeting Standards…………………………………….SBC-17
18.
Native Lumber………………………………………...SBC-18