650-RICR-20-00-1
650-RICR-20-00-1. Red Book (version Periodic Refile, 10/09/2003 to 11/23/2008)
Rhode Island Coastal Resources Management Program
Section 300.3.
Residential, Commercial, Industrial,
and Recreational Structures
A. Definitions
1. Residential buildings include houses, and
other structures as defined as a building in Section
R-115 of the Council of American Building
Officials (CABO) Building Code, and the
pertinent sections thereto which are used primarily
for human habitation which are built on a
shoreline feature or its contiguous area.
Rev. Pg. 11/7/2002
Page 1
Section 300.3
2. Commercial and industrial structures and
operations on a shoreline feature, its contiguous
area, or within tidal waters include all buildings
and alterations to such features related to the
manufacturing and interchange of goods or
commodities, or any other business activity.
3. Recreational structures include swim floats,
beach pavilions that are constructed for
recreational purposes on a shoreline feature, its
contiguous area, or in tidal waters.
4. Associated residential structures including
but not limited to decks, porches, walls,
boardwalks, swimming pools, roads, driveways,
and shall in-clude other structures integral to or
ancillary to a residential building including minor
grading, filling or excavation typically 10 cubic
yards or less.
5. Structural Lot Coverage is that part of a lot
or parcel that is covered by roofed structures of at
least 200 square feet in size. Structural Lot
Coverage is calculated in square feet and is either
equal to the total square footage occupied by one
or more foundations, or, in the case of cantilevered
structures, the total square footage occupied by the
structure and calculated as if a foundation
supported the cantilevered portions of the
structure. Structural foundations shall be broadly
interpreted to include sona-tubes, pilings, concrete
blocks, columns, or other types of foundation
material which provide structural support to a
structure which is covered by a roof.
B. Policies
1. It shall be the policy of the Council to
undertake all appropriate actions to prevent,
minimize or mitigate the risks of storm damage to
property and coastal resources, endangerment of
lives and the public burden of post-storm disaster
assistance consistent with policies of the State of
Rhode Island as contained in the Hazard
Mitigation Plan element of the State Guide Plan
when considering applications for the construction
of
residential,
commercial,
industrial
and
recreational structures, including utilities such as
gas, water and sewer lines, in high hazard areas.
2. It is the Council’s policy to require a public
access plan, in accordance with Section 335, as
part of any application for a commercial or
industrial development or redevelopment project
in or impacting coastal resources.
In accordance with Section 120, a variance from
this policy may be granted if an applicant can
demonstrate that no significant public access
impacts will occur as result of the proposed
project.
C. Prerequisites
1. Applicants proposing new construction
and/or alterations to existing structures shall
obtain a letter from the local authorities certifying
that proposed activities conform to the local
zoning ordinance, or that if relief from an
ordinance is required that it has been obtained and
that the decision authorizing the appropriate relief
is final.
This letter must be submitted to the CRMC
with the application.
2. Applicants proposing new construction
and/or alterations to existing structures shall
demonstrate that all applicable requirements of the
RISBC including those pertaining to construction
within flood hazard zones will be met.
This demonstration shall be made by
submitting to the CRMC at the time of application
a building official's form properly completed and
signed by the local building official.
3. Applicants proposing to build, repair or
alter an individual sewage disposal system (ISDS)
shall obtain a permit from the Department of
Environmental Management and shall submit to
the CRMC copies of the approved application and
the approved plans. The plan submitted must bear
a DEM/ISDS approval stamp.
4. Persons proposing activities that may
impact the function of an existing ISDS and which
by the rules and regulations of the Department of
Environmental Management requires the issuance
of a permit, shall obtain the necessary permits and
Rhode Island Coastal Resources Management Program
submit copies of these permits to the CRMC at the
time of application.
5.
Applicants for industrial, commercial and
recreational structures shall demonstrate that all
state safety codes, fire codes, and environmental
requirements have or will be met.
6.
Applicants
shall
demonstrate
that
connections to public water supplies and sewer
systems shall be authorized by the appropriate
authorities when:
a) such connections are proposed by the
applicant;
b) where on-site water withdrawal and/or
sewage disposal will have a significant
adverse environmental or public health
impact.
7. Applicants for commercial, industrial, and
recreational structures shall demonstrate that
adequate transportation and utility services to
support the proposed operations and related
activities are available.
D. Prohibitions
1. Industrial operations and structures are
prohibited in Type 1 and 2 waters or on shoreline
features abutting these waters.
2. The mining and extraction of minerals,
including sand and gravel, from tidal waters and
salt ponds is prohibited. This prohibition does not
apply to dredging for navigation purposes, channel
maintenance, habitat restoration, or beach
replenishment.
E. Standards
1. General:
(a) See standards given in "Filling,
Removing, or Grading of Shoreline
Features" (Section 300.2), as applicable.
3. Solid waste disposal and minerals
extraction is prohibited on shoreline features and
their contiguous areas.
(b) See standards given in "Sewage
Treatment and Disposal" (Section 300.6),
as applicable.
4. The use of fill for structural support of
buildings in flood hazard V zones is prohibited.
5. (a) New decks and structures, and expanded
structures
associated
with
residential
properties,
or
non-water
dependent
commercial uses, are prohibited in or over
tidal waters.
(c) Commercial and Industrial docks,
wharves and piers shall be designed and
certified by a registered professional
engineer.
2. Residential, commercial, industrial, and
recreational buildings:
(b) Decks associated with commercial
properties are prohibited in or over type 1
waters.
Decks
associated
with
commercial properties are prohibited in or
over Type 2 waters unless such use is
reserved in connection with a water
dependent use. Decks associated with
commercial properties are prohibited in or
over Type 3, 4, 5, and 6 waters unless (i)
the deck is to accommodate a designated
priority use for that water area; (ii) the
applicant has examined all reasonable
alternatives
and
the
council
has
determined that the selected alternative is
the most reasonable; and (iii) the deck is
the minimum necessary to support the
priority use.
(a) Excavation and grading shall be
restricted to those activities and areas
necessary for the construction of the
building and/or appurtenant structures
(see Section 300.2).
(b) Applicants shall be required to reduce
the inflow of pollutants carried by surface
runoff in accordance with the policies and
standards contained in Section 300.6 and
as detailed in the most recent version of
the Rhode Island Stormwater Design and
Installation Standards Manual.
F. Flood Zone Construction
6. See Section 110 (specifically Table 1A) for
a listing of additional prohibitions.
In many instances lands under the jurisdiction
Rev. Pg. 11/7/2002
Page 2
Section 300.3
Rhode Island Coastal Resources Management Program
of the CRMC are by virtue of their topographic
position subject to flooding. The Federal
Emergency Management Agency has evaluated
the risk of flooding and has established 100 year
return frequency elevations of the flood waters
(i.e. the Base Flood Elevation, (BFE) for all of the
State's coastal communities. The approximate
limits of the flood zones and the associated Base
Flood Elevations are shown on the FEMA's Flood
Insurance Rate Maps, which are commonly
available at each communities building official's
office.
In recognition that structures located within
Flood Hazard Zones must be designed to meet
more severe conditions than those not, the Rhode
Island State Building Code, (RISBC) contains
specific requirements for flood zone construction.
(Reference RISBC-8)
The CRMC requires all applicants proposing
construction within flood hazard zones to
demonstrate that all applicable portions of the
RISBC and more specifically RISBC-8 are to be
met.
This demonstration shall be made by
submitting to the CRMC at the time of application
a building official's form properly completed and
signed by the local building official.
G. Guidelines for Construction in Flood
Hazard Zones
In addition to the requirements of the RISBC,
the CRMC suggests that applicants incorporate the
following items into their proposed designs:
1. For construction in wave velocity (V)
zones as defined by Federal Flood Insurance Rate
Maps:
(a) If timber pilings are used, they should
meet the American Society for Testing and
Materials (ASTM) standards for Class B piles
and shall have a minimum tip diameter of 8
inches. Wooden pilings should be treated
with a wood preservative. Bracing between
piles is recommended.
(b) Pilings in ocean fronting areas should
penetrate no less than 10 feet below mean sea
level.
(c) Floor joists should be secured with
hurricane clips where each joist encounters a
floor beam. These metal fasteners or straps
should be nailed on the joist as well as on the
beam.
(d) To secure the exterior wall to the floor
joists, galvanized metal strap connections
should be used connecting the exterior wall
studs to the joists.
(e) Roof trusses or rafters should be
connected to the exterior wall with galvanized
metal straps.
2. For construction in coastal stillwater (A)
Flood Zones.
(a) Items a, b, c, d, e as listed for V zone
construction
should,
if
applicable,
be
employed.
(b) Parallel concrete walls or pilings rather
than fill should be used to elevate habitable
residential structures when six (6) feet or more
clearance exists between the existing grade
and the flood plain elevation.
In areas subject to minimal wave action in
a 100-year storm event, discontinuous
reinforced-concrete foundation walls which
allow sufficient free flow of flood waters may
be substituted for parallel concrete walls or
pilings.
Rev. Pg. 11/7/2002
Page 3
Section 300.3