815-RICR-30-00-1. Standards for Electric Utilities (version Amendment, 09/21/2004 to 09/21/2004)
Rules Prescribing Standards for Electric Utilities
STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS
DIVISION OF PUBLIC UTILITIES AND CARRIERS
RULES PRESCRIBING STANDARDS FOR ELECTRIC UTILITIES
Date of Public Notice: June 18, 2004
Date of Public Hearing: July 26, 2004
Effective Date: September 21, 2004
The following rules and regulations, after due notice and an opportunity
for hearing, are hereby adopted and filed with the Secretary of State this 1st
day of September, 2004, to become effective twenty (20) days after filing, in
accordance with the provisions of R.I.G.L. §42-35-4 and §39-3-33 (1990
Reenactment).
These rules and regulations supersede the Rules Prescribing Standards
for Electric Utilities that have been in effect since May 1995.
Date September 1, 2004
Thomas F. Ahern, Administrator
1
RULES PRESCRIBING STANDARDS FOR ELECTRIC UTILITIES
I. APPLICATION OF RULES
A. These rules shall apply to every public utility as hereinafter defined doing
business as such, or authorized to do so, within the State of Rhode Island.
B. These rules shall be amended or repealed, and applications therefore shall
be made, in accordance with provisions of Title 42, Chapter 35 of the General
Laws of 1956 entitled "Administrative Procedures".
II. DEFINITIONS
A. The term "Division" means the Rhode Island Division of Public Utilities and
Carriers.
B. The term "Administrator" means Public Utility Administrator of the Division
of Public Utilities and Carriers.
C. The term "public utility" shall mean and apply to every corporation,
company, person, association of persons, their lessees, trustees, or receivers
appointed to any court whatsoever, that now or hereafter may own, lease,
operate, manage or control any electric plant or equipment or any part of any
electric plant or equipment, within this State, for the production, transmission,
delivery or furnishing of electricity, light, heat or power, either directly or
indirectly, to or for the public.
D. The term "electric plant" shall mean all real estate, fixtures, equipment and
personal property owned, controlled, operated or managed in connection with
or to facilitate the production, generation, transmission, delivery or furnishing
of electric energy.
E. The term "customer" shall mean and apply to every corporation, company,
person, association of persons, their lessees, trustees or receivers appointed by
any court whatsoever, that now or hereafter may be supplied with electric
service by any public utility as herein defined.
F. The term "service" shall mean, in its broadest and most inclusive sense, the
furnishing of electricity to a customer by a public utility.
G. The term "meter", without other qualification, shall mean a device or
appliance for the measurement of electrical quantities to be used as a basis for
determining charges by a public utility for furnishing or rendering electric
service to a customer.
2
H. The term "creep" means the motion of the rotor of a meter with normal
operating voltage applied and the load terminals open-circuited.
III. SERVICE PROVISIONS
A. Filing of Rates Schedules.
Schedules showing all rates, tolls and charges by a public utility shall be filed
and kept open to public inspection in accordance with the provisions of Title
39, Chapter 3, Section 10 of the General Laws of 1956.
B. Application for Service.
An Applicant desiring service under a public utility's filed rate schedules may
be required to make application in writing, in accordance with the forms
prescribed by the public utility.
C. Information to Customers - Rate Selection.
1. Each public utility shall, upon request, provide a customer with such
information and assistance as is necessary to enable the customer to secure
the most advantageous rate or rates. Further, each utility shall inform the
applicant of any service connection and/or installation charge to be applied to
the bill. Each customer shall be responsible for selecting, and taking service at
the most advantageous rate or rates.
2. Each public utility shall, upon request, explain to a customer the method of
reading meters and how the billing is calculated.
3. Where special charges for construction, maintenance, replacement costs,
expenses or overtime work are not specifically set forth in a utility's tariff, the
utility shall, before performing non-emergency work, provide the applicant or
customer with an estimate of charges to be levied, in writing if requested.
4. In addition, the utility shall make available free information concerning the
utility's programs, services, rights and responsibilities, and complaint
procedures for the general public.
D. Deposits.
1. A public utility, as security for prompt payment of a customer's
indebtedness to it, may require a cash deposit or other collateral satisfactory to
it before rendering, or as a condition of continuing to render service to such
customer. This deposit shall not be more than the estimated bill for two times
the normal billing period. Interest shall be paid on deposits held six (6)
months or more in accordance with applicable rate schedules or the terms and
conditions of the public utility. Deposits, plus accrued interest thereon, less
3
any amount due the public utility, will be refunded upon termination of
service. When a deposit is applied against an account that has been
terminated, interest shall cease to be accumulated on the balance at the date
of termination.
E. Meter Reading and Bill Forms.
1. The metering equipment for each service shall be such as to register the
number of kilowatt-hours (kwh) delivered during any period, and to the extent
applicable, the number of Kilo-Var Hours (KvarH) and the Kilowatt (Kw) and
Kilo-Volt Amperes (Kva) demand.
2. All service meters shall be read at regular intervals and on the
corresponding day of each meter reading period insofar as practicable within
regularly scheduled work days.
3. Bills shall be rendered at regular intervals and shall show the date of the
current meter reading and the amount or quantity of service for the billing
period; and shall also show any applicable discount or penalty date.
4. Each public utility shall keep an accurate account of all charges for service
billed each customer and shall maintain records showing information from
which each bill rendered may be readily computed.
F. Customer Complaints.
1. Each public utility shall make a full and prompt investigation of customer
complaints made either directly or through the Division. A record of
complaints received, other than those of a minor nature shall be kept for at
least two years and shall show the name and address of the complainant, the
date and character of the complaint and the disposition thereof.
2. Each public utility shall endeavor to keep its appointments. In the event
cancellation of appointment is unavoidable, every reasonable effort should be
made to promptly notify the customer.
3. During an abnormal service outage the utility shall make reasonable efforts
to inform the general public about the areas affected, the progress of service
restoration, and anticipated restoration schedules when available. Information
for the general public shall be made through advisories to the news media.
Business offices shall make similar information available to callers, using
appropriate communications systems.
G. Change in Character of Service.
1. If a change in character of service to a customer is brought about for the
convenience or benefit of the public utility, the public utility shall pay such
4
part of the cost of changing the equipment of the customer affected as shall be
determined by mutual agreement. An equitable settlement would normally be
on the following basis: Payment by the public utility to the customer of:
a) The cost of the customer's electrical utilization and equipment that is made
obsolete, less proper allowance for depreciation.
b) The cost of installing the new equipment and removing the old, less the
salvage value of such equipment as the customer retains.
c) The cost of making the necessary change in customer's wiring.
H. Discontinuance of Service
1. By Customer: A customer shall be required to give at least twenty four (24)
hour notice of its intention to discontinue service in accordance with the
provisions of the applicable rate or terms and conditions of service and shall be
responsible for all charges until expiration of such notice period.
2. By the Public Utility:
a) Non-Payment of Bills. In accordance with the provisions of the applicable
rate or terms and conditions of service, a public utility may require that bills be
paid within a specified time after presentation. On and after thirty (30) days
from the date of presentation service may be discontinued for non-payment
provided written notice to the customer has been deposited in the U.S. mail at
least ten (10) days prior to the date of discontinuance. In lieu of the
discontinuance, or upon reconnection, the public utility may require payments
at less than monthly intervals. If service is discontinued for non-payment, the
public utility may make a reasonable charge for reconnection. Service must
not be discontinued on a Friday, a Saturday, or the day before a holiday.
b) For Violation of Rules: No public utility shall discontinue service to a
customer for violation of any rule unless it shall first have deposited in the U.S.
mail written notice to the customer at least ten (10) days prior to the date of
discontinuance advising the customer of the particular rule that has been
violated, except that service may be discontinued immediately when
continuance of the service would endanger life or property, or when ordered to
do so by any governmental agency or official having jurisdiction.
c) For Fraudulent Use of Service: A public utility may discontinue service
without notice whenever a fraudulent use of the service by the customer is
detected.
5
IV. QUALITY OF ELECTRIC SERVICE
A. Standard Frequency - The standard frequency for alternating current
distribution systems shall be sixty (60) Hertz, with permissible variations not
exceeding maximum and minimum values of 60.3 and 59.7 Hertz.
B. Service Voltage - The following service voltage standards shall be
maintained at the point where the electrical system of the supplier and the
electrical system of the user are connected.
Table I [These values are ANSI C84.1 (1989). Values shall change if ANSI
adopts new standards.]
Established Standard
Service Voltage
Minimum Voltage Maximum Voltage
Type of Service
120
114
126
Single Phase
120/240
114/228
126/252
Single or Polyphase
208Y/120
197Y/114
218Y/126
Single or Polyphase
240
228
252
Single or Polyphase
480Y/277
456Y/263
504Y/291
Single or Polyphase
480
456
504
Single or Polyphase
600
570
630
Single or Polyphase
2400
2340
2520
Single or Polyphase
4160Y/2400
4050Y/2340
4370Y/2520
Single or Polyphase
12470Y/7200
12160Y/7020
13090Y/7560
Single or Polyphase
For distances exceeding a 2-mile radius from any distribution sub-station
serving the customer, the minimum permissible voltage shall not be less than
97% of the minimum values shown in Table I.
C. Momentary Fluctuations - Momentary fluctuations of voltage and/or
frequency at the customer's service shall not be construed as non-compliance
with this Section IV, Subsection 2 and for the purposes of these Rules a
momentary fluctuation of voltage and/or frequency shall be defined as a
change in voltage and/or frequency not exceeding a three (3) second time
interval of a non-periodic recurring cycle; provided, however, that fluctuations
in frequency and/or voltage having continuous and/or recurring periodic time
cycles shall not be considered as compliance with this Section IV; and the
public utility shall immediately initiate and complete all necessary action to
eliminate and/or correct the cause of such fluctuations, if found to originate
directly or indirectly within the public utility's system.
D. Abnormal Conditions - These Rules shall not apply to temporary conditions
due to acts of God, windstorm, fire, strikes, insurrections, construction and/or
maintenance or other disruptions of service beyond the immediate control of
the public utility; provided, however, that all public utilities shall initiate
immediate action and proceed without delay and perform all necessary work to
restore its system and/or customers' services to normal operating conditions.
6
E.
Special Provisions - No public utility shall be required to maintain service
voltage according to Table I, at any point beyond the point where the electrical
system of the supplier connects to the electrical system of the user if the wire
or cables of the customer are (i) inadequate or undersized (ii) not capable of
delivering the customer's normal requirements for electricity, or (iii) not in
conformance with the requirements of the National Electric Code or any
applicable statute, ordinance, rule or regulation of any authority having
jurisdiction.
V. VOLTAGE SURVEYS AND RECORDS
A. Each public utility shall make a sufficient number of voltage tests for the
areas (cities, villages and rural areas) served to indicate compliance with
voltage requirements contained in Table 1.
B. All voltage test records shall be retained by the public utility for at least two
(2) years and shall be available for inspection by the Division.
VI. INTERRUPTIONS OF SERVICE
A. Each public utility shall use all reasonable means to avoid interruption of
service but should an interruption occur, service shall be re-established within
the shortest time practicable, consistent with safety requirements.
B. Each public utility shall make a record of all interruptions of service of
more than five (5) minutes' duration affecting the entire distribution system of
a single community or the entire distribution circuit serving a division of a
community and shall include in such record the date and time of interruption,
approximate number of customers affected, the date and time of service
restoration, and, when known, the cause of such interruption. Reports with
reference to such service interruption shall be made monthly to the Division on
Form E-1.
C. Each utility shall notify the Commission (or a designated member of the
staff) by telephonic means of any major interruption of service when the
interruption results in 1000 or more customer hours between normal working
hours increasing to 3000 or more customer hours after normal business hours.
A company having less than 5,000 customers will notify the Commission when
outages exceed 100 customer hours during normal working hours and
increasing to 200 customer hours after normal business hours.
D. When service is interrupted to perform work on lines or equipment, such
work shall be done at a time causing minimum inconvenience to customers
consistent with the circumstances. Customers seriously affected by such
interruption shall, whenever reasonably possible, be notified of the time and
expected duration of the service interruption.
7
VII. METER ACCURACY AND TESTING
A. Inspection of Meters.
1. Meters removed from service. All meters removed from service, which are to
be reinstalled, shall be inspected and tested for correctness. In addition, worn
or damaged parts shall be replaced.
2. Meter installations. All polyphase meters and demand devices shall be
tested before installation to ensure accuracy of operation when installed. In
connection with installation an electrical check shall be made of all instrument
transformer connections.
B. Test and Calibration of Meters.
1. Polyphase Meters. All polyphase meters shall be tested at loads and
adjusted to tolerances as follows:
Test Load in Rated
Power Factor
To Tolerance of
Meter Capacity
100%
1.0
Plus/Minus 1%
10%
1.0
Plus/Minus 1%
100%
0.5
Plus/Minus 2%
Meters also shall be checked for "creep" at no load and rated voltage.
2. Demand Devices. All indicating and recording demand devices shall be
adjusted as follow:
(a) Zero Adjustment
No demand device that fails to reset properly to zero shall be placed in service
or allowed to remain in service without adjustment.
(b) Up-Scale Check
Tests to determine the accuracy of a demand device shall be made at a point
approximately mid-scale. No demand under test having an error in indication
or registration of more than 2% plus or minus (in terms of full scale deflection)
shall be placed, or allowed to remain, in service without readjustment.
8
(c) Time Cycle Devices.
All motors used to maintain a timing cycle where such timing cycle directly
affects meter registration, shall be tested to insure operation at the proper
speed.
C. Test Schedules for all Watthour Meters and Demand Devices
1. New Meters. The manufacturer's test on all new meters will be accepted as
a first test on a meter and so recorded if built to the EEI-AEIC-NEMA or ANSI
standard for Polyphase meters.
2. All alternating current watthour meters and demand devices in service shall
be tested in accordance with the following requirements.
(a) Meters up to and including 12KVA shall be tested in accordance with either
subparagraph (i) or (ii) below. The Schedule initially adopted by the public
utility shall not be changed without notifying the Division.
(i) Periodic Test Schedule. Watthour meters may be tested on periodic
basis by which every meter shall be tested at least once every twelve (12)
years.
(ii) Selective Test Plan. Watthour meters may be tested under a selective
plan as follows.
(a) Selective Test Population. This shall include those single-phase
common or residential type meters of 0-12 KVA capacity. It shall
not include those specific meter groups known to be adversely
affecting overall meter accuracy, if these meters are placed on a
fixed retirement program not exceeding five (5) years. Meters
removed due to a fixed retirement program need not be tested by
the utility.
(b) Sample Test Group. A Sample Test Group representing a
cross-section of the meters in the Selective Test Population on
company lines shall be selected at random and tested each year.
The Sample Test Group shall be at least 1% of meters in the
Selective Test Population, but not less than 500 meters. For a
company having less than five thousand meters, the Sample Test
Group shall be at least 2% of meters in the Selective Test
Population, but not less than 40 meters.
(c) Cumulative Sample Test Group. The Cumulative Sample Test
Group includes the Sample Test Group of the current year plus
those of the immediately preceding years to a maximum of five
Sample Test Groups.
9
(d) Number of Meters to be Tested. The percentage of meters in the
Cumulative Sample Test Group which displays a weighted average
accuracy outside the limits of 98% to 102% shall be used to
determine from the test Ratio Curve (Fig. 1.) the minimum number
of meters to be tested (Total Meter Test Group) in the ensuing year.
(e) Supplemental Test Group. The Supplemental Test Group is the
difference between the Total Meter Test Group and the Sample Test
Group.
Supplemental = (Total) - (Sample)
Tests of meters which are part of the Selective Test Population and
which are returned to the shop for maintenance may be credited
toward completion of the Supplemental Test quota. Additional
meters selected to fill the Supplemental Test quota shall be either:
Meters in service without a test, or meters of specific types which
are contributing a greater than average percentage of the meters
outside the limits of 98% to 102%.
Specific meter groups known to be adversely affecting over-all
meter accuracy, if placed on a fixed retirement program not
exceeding five years may be excluded from the Selective Test
Population. Meters removed due to a fixed retirement program
need not be tested by the utility.
Such meters on a retirement program shall be junked at a uniform
annual rate to eliminate them from Company lines in five years or
less from the start of the program. If the retirement rate is not
maintained, all remaining meters in the group must become part of
the Selective Test Population and subject to the Selective Test
Procedure.
b) Meters in excess of 12KVA and not exceeding 100 KVA shall be tested on a
periodic basis by which every meter shall be tested at least once every six (6)
years.
c) Meters in excess of 100 KVA shall be tested on a periodic basis by which
every meter shall be tested at least once every (5) years.
d) In lieu of the periodic and selective test plans described in subparagraphs
C.2(a), C.2(b) and C.2(c) above, a utility may, after notifying the Division,
implement a statistical sample testing program based on the provisions of the
most current version of ANSI/ASQC Z1.9, American National Standard
Sampling Procedures and Tables for Inspection by Variables for Percent
10
Nonconforming or on the provisions of a comparable nationally recognized
statistical sampling methodology.
e) Integrated demand meters shall be subject to the same periodic tests or
sample tests as the meters with which they are associated.
f) For the purpose of subparagraph C.2(b) the KVA rating of a Self-contained
AC Watthour Meter is the product of the rated voltage in Kilo-volts, the rated
test amperes and the number of stators. The KVA rating of an instrument
transformer classed watthour meter is the product of the primary voltage in
Kilo-volts, the nameplate rating of the current transformers, and the number of
stators.
3.
All meters over 12 KVA capacity removed from service and not yet due for
testing must be tested and recalibrated before being put back into service.
These tests may be included as a part of the periodic or statistical sampling
test populations.
4. Request Tests.
a) All request tests must be made with the meter in its service location
whenever practicable to do so.
b) Tests by public utility. When requested by a customer, each public utility
shall test the accuracy of the customer's meter within fifteen (15) days from the
time the request is made. If the meter has been tested during the preceding
thirty-six (36) months, a public utility may require the deposit of a fee of
Twenty-five dollars ($25) for such a test. If on testing the meter is found to be
fast by more than 2%, the deposit shall be promptly refunded. If the meter is
not found to be fast by more than 2% the public utility shall retain the amount
deposited for the test. A customer may be represented in person or by an
agent when the public utility conducts the test on the customer’s meter. A
report giving the name of the customer requesting the test, the date of the
request, the location, the type, make size, the serial number of the meter, the
date tested, and the result of the test shall be supplied to such customer
within a reasonable time after the completion of the test.
c) Tests by Division. Upon written application to the Division by a customer, a
test will be made of the customer's meter in the presence of the Division's
representative as soon as practicable. Each application to the Division for test
of a meter shall be accompanied by a fee of twenty-five dollars ($25). If upon
testing, the meter is found to be fast by more than 2%, the Division shall
return to the customer the amount of fee paid by the customer to the Division.
When notified of an application submitted to the Division by a customer for a
referee test as herein provided, the public utility shall not knowingly remove,
interfere with, or adjust the meter to be tested without the written consent of
the customer and approved by the Division.
11
5. Reporting Requirements.
a) For utilities that test according to the periodic test schedules or selective
tests plans described in subparagraphs C.2(a), C.2(b) and C.2(c), reports of
periodic and sample tests of meters shall be reported to the Division on Form
E-2 and Form E-2A once a year, or on the public utility's Standard Meter Test
Report Form.
b) For utilities that implement the statistical sample testing program as
described in subparagraph C.2(d), reports of in-service and request tests of
watthour meters shall be made each year and filed with the Division not later
than the 15th day of March the following year. All reports of in-services tests
are to include the number of meters tested, the number of meters found
outside of limits, and the size of the population. Where appropriate, the
reports should break down the population of meters by type and be
accompanied by appropriate performance parameters for that type.
6.
A complete record of the latest test made on a meter shall be retained in
the public utility's files for three years.
D. Billing Adjustments
1. Calculation of Error. The accuracy of registration of the meter and its
performance in service shall be determined by its average error, as follows:
a) The average error shall be the weighted average of its error at light load with
a weighting of one and its error at heavy load with a weighting of four.
b) Any adjustment of charges that is made in accordance with this rule shall be
based on such average error.
2. Adjustments.
a) Fast Polyphase Meters. Whenever a polyphase meter is found to be fast in
excess of 2% of the correct amount, the Company shall refund to the customer
an amount equal to the charge for the excess kilowatt hours billed for the
twelve (12) month period immediately preceding such test, unless the time
when the error first developed, or occurred can be definitely fixed, in which
case the amount to be refunded shall be calculated from that time. Under no
circumstances will an adjustment of a customer's bill be made if there is
evidence that the meter has been tampered with.
b) Slow Polyphase Meters. Whenever a polyphase meter is found to be slow in
excess of 2%, the Company may make a charge to the customer for the
unbilled kilowatt hours supplied for the previous twelve (12) months or since
the last test, whichever is the shorter period. However, where there is evidence
that the meter has been tampered with, the Company may charge the
12
customer for all unbilled kilowatt-hours supplied since the estimated data of
the tampering.
c) Non-Registration. If a meter is found which does not register, the bill for the
period of non-registration shall be based upon information recorded prior or
subsequent to the period of non-registration and by any other pertinent
information supplied by the customer or known to the public utility.
E. Testing Facilities and Equipment:
1. Single Polyphase Standards.
a) Laboratory Standards. Every public utility shall have available one or more
laboratory standards for the sole purpose of checking working standards. All
standards shall be certified at least once each year in a laboratory acceptable
to the Division. Each standard shall be accompanied by calibration tables
noting the corrections at various working loads. These calibration tables when
superseded shall be kept on file in the office of the public utility for a period of
two (2) years.
b) Each public utility shall have an adequate number of working standards for
testing customers' meters. These working standards shall be compared to
laboratory standards at least once every twelve (12) months. Each working
standard shall be accompanied by a calibration table noting the corrections at
various working loads. These calibration tables, when superseded shall be
retained by the public utility for a period of two (2) years. If comparisons with
the laboratory standards show the working standard to be in error by 1% or
over, it shall be recalibrated and/or replaced. In case a public utility does not
maintain a reference watthour standard, the working standards must be
checked every twelve (12) months in a laboratory acceptable to the Division.
VIII. EQUIPMENT AND FACILITIES
A. Standard Practice
In determining standard practice, the Division will be guided by the
provisions of the NATIONAL ELECTRICAL SAFETY CODE, the NATIONAL
ELECTRIC CODE, and such other relevant codes as shall be approved by the
American Standards Association, except as any of the foregoing may in any
particular case be modified by statute, ordinance, orders, rules or regulations
by governmental bodies or agencies having jurisdiction.
B. Construction and Maintenance
Each public utility shall construct, install, operate and maintain its
plant, structures, equipment and lines in accordance with standard practice as
defined in paragraph 1 above, and insofar as practical, in such a manner as
13
best to accommodate the public, and to prevent interference with service
furnished by other public utilities.
C. Joint Pole Construction
Except as otherwise permitted by the Division for cause shown, all
installations making use of poles either for single or joint occupancy shall
conform to standard practice, and current joint-owned pole agreement between
various utility companies.
D. Safety Instructions
Each public utility shall adopt comprehensive instructions for the safety
of employees, and shall supply a copy thereof to each employee before
assignment to duty in generating stations, substations, on overhead or
underground lines, and shall be satisfied that such employees have been
properly informed of safe practices and are cognizant of all hazards involved, as
per OSHA standards, 29 CFR Sec. 1910.260, et seq., as the same from time to
time are amended.
E. Resuscitation
Each public utility shall instruct its employees engaged in electrical work
in the practice and use of accepted rules for resuscitation from electrical shock,
as per OSHA standards 29 CFR Sec. 1910.260, et seq., as the same from time
to time are amended. Copies of such rules shall be furnished to each such
employee. Electrical work as used herein shall be construed to mean work on
live electric conductors and equipment energized at potential exceeding 150
volts line to ground.
F. Accidents
Each public utility shall report to the Division as soon as possible after each
accident happening in connection with the operation of its property, facilities or
service, wherein any person shall have been caused an injury requiring
hospitalization in excess of 24 hours. The first report may be preliminary, but,
if so, shall be followed later by as full a statement as possible of the cause and
details of the accident and the precautions taken, if any, to prevent similar
accidents. In case of fatal accidents, immediate notice shall be given by
telephone to the Division, (Form E-3, Appendix "D").
14
15
IX. RECORDS AND REPORTS
A. Station Records
1. Each public utility shall keep sufficient records of the operation of its
generating units and distribution supply feeders to show the characteristics
and the performance of each.
2. Unless sufficient information is furnished by the public utility supplying the
energy, each public utility purchasing electric energy shall maintain adequate
instruments and meters to obtain complete information as to such purchases.
B. Preservation of Records
All records required by these rules shall be preserved by the public utility for
a period of two (2) years unless otherwise specified herein or other controlling
rules or regulations require a longer period of retention. Such records shall be
kept within the State of Rhode Island at the office or offices of the public utility
and shall be open at all reasonable hours for examination by the Division.
C. Reports to Division
Each public utility shall file periodic reports with the Division on the following
forms, which will be furnished by the Division upon request:
Form
No.
Title
Period
Appendix
E-1 Interruption of
Service Report
Monthly "A"
E-2 Periodic Meter Test
Report
Annually "B"
E-2A Selective Meter Test
Report
Annually "C"
E-3 Utility Accident
Report
As
Required
"D"