ARSD 74:29:11:20

ARSD 74:29:11:20. Authorizing new injection wells within permit area boundary

Last amended: 2007Year: 2026Length: 80 wordsOfficial source

Cite as S.D. Admin. R. 74:29:11:20

The board, through permit conditions, may authorize the department to approve proposed technical revisions, in accordance with ยงยง 74:29:03:16 and 74:29:11:08, to allow the operator to construct and operate new injection wells within the permit area if the following requirements are met: (1) The wells are of similar construction; and (2) The cumulative effect of drilling and operation of additional injection wells is considered by the department during evaluation of the technical revision application and is acceptable to the department.