ARSD 74:29:11:22
ARSD 74:29:11:22. Construction quality assurance plan
Cite as S.D. Admin. R. 74:29:11:22
Before construction of mine facilities, the operator shall develop a construction quality assurance plan that addresses all aspects of facility construction. The plan shall include the following:
(1) A description of the responsibilities and authorities of key personnel;
(2) A description of the required level of experience, training, and duties of the contractor, the contractor's employees, and the quality assurance inspectors;
(3) A description of the testing protocols for every major phase of construction, including the frequencies of inspections, field testing, and sampling for laboratory testing;
(4) The sampling and field testing procedures and the equipment to be used;
(5) The calibration of field testing equipment;
(6) The laboratory procedures to be used; and
(7) Documentation to be maintained.
The operator shall submit the construction quality assurance plan at the same time the plans and specifications required in ยง 74:29:11:21 are submitted.