1680-05-04-.09
Review Of Technical And Price Proposals
Cite as Tenn. Comp. R. & Regs. 1680-05-04-.09
(1)
Short-listed or otherwise eligible design-builders will each submit a technical proposal
and a price proposal, concurrently, for the project. The technical proposal and price
proposal shall be submitted to the Department in separate sealed envelopes marked
in strict accordance with the requirements and timeline contained in the RFP, or as it
may be amended. Price proposals will be kept in a secure location until read
publicly.
(2)
On the date provided in the RFP, the DBRC will open, review, and score or otherwise
evaluate the technical proposals and any other required technical information in
accordance with the evaluation criteria established in the RFP. As part of the
evaluation of technical proposals, the DBRC may require each design-builder to
make an oral presentation and submit to an interview.
(3)
After evaluating the technical proposals, and on the date and at the time specified in
the RFP, or as it may be amended, the Department will publicly open and read the
total proposed contract amount in the price proposal submitted by each eligible and
responsive design-builder.
(4)
The DBRC may request that an eligible design-builder provide the support
information used to develop its price proposal. This information may include, but is
not limited to, design assumptions, summary of quantities, mobilization assumptions,
and construction staging assumptions.
(5)
In the event all price proposals submitted exceed an acceptable range of the
Department’s cost estimate for the project, the Department, at its discretion, may
determine whether to proceed to request a best and final offer.
(6)
If a best and final offer is requested, the Department will issue a best and final offer
RFP to the eligible design-builders. The best and final offer RFP may or may not
include minor changes in the scope or contract requirements of the original RFP.
(7)
Based upon the proposal from each design-builder and the appropriate selection
method as specified in the RFP, or the best and final offer RFP, if applicable, the
DBRC will determine the best evaluated design-builder.
PROCEDURES FOR THE SELECTION AND AWARD
1680-5-4
OF DESIGN-BUILD CONTRACTS
(8)
The Department shall have the authority to discontinue the design-build selection
process at any time prior to the opening of price proposals, subject to any applicable
obligation to pay a stipend to eligible and responsive design-builders.