1680-05-04-.10
Award Process
Cite as Tenn. Comp. R. & Regs. 1680-05-04-.10
(1)
The DBRC will forward the apparent best evaluated design-builder to the
Commissioner with a recommendation either to:
(a)
Reject all proposals; or
(b)
Award a design-build contract to the best evaluated design-builder; or
(c)
Provided, however, if the DBRC determines after opening the price proposals
that the apparent best evaluated design-builder should be considered
non-responsive, or if after award the best evaluated design-builder declines the
award and forfeits the proposal guaranty, the DBRC may recommend award of
the contract to the next best evaluated design-builder.
(2)
Upon receiving the DBRC’s recommendation, the Commissioner may either:
(a)
Reject all proposals; or
(b)
Award a design-build contract to the best evaluated design-builder; or
(c)
If the DRBC determines after opening the price proposals that the apparent
best evaluated design-builder should be considered non-responsive, or if the
best evaluated design-builder declines the Commissioner’s award, the
Commissioner may award the contract to the next best evaluated design-
builder.
(3)
After the design-build contract has been awarded, the Department will publish the
technical scores and adjusted prices on the Department’s website.
(4)
All short-listed design-builders will be afforded the opportunity for a debriefing with
the Department regarding the relative merits of their technical proposals and price
proposals.