1680-07-01-.23
Bond Or Proof Of Solvency Requirements
Cite as Tenn. Comp. R. & Regs. 1680-07-01-.23
(1)
The TDOT Permit Office may require, as a condition of the issuance of a permit under these
rules, that an applicant shall agree to and give bond with surety (unless an applicant shall by
sworn statement furnish satisfactory proof of the applicant’s own solvency to the TDOT
Permit Office) to indemnify the state and/or counties thereof, against damages to roads, or
bridges, resulting from the use thereof by the applicant. The bond, if the TDOT Permit Office
so authorizes, may cover more than one permitted vehicle operated by the same applicant.
(2)
The bond required shall be in a form acceptable to the TDOT Permit Office and in an amount,
as determined by the TDOT Permit Office, sufficient to indemnify the state and/or counties for
the potential damages to roads and bridges resulting from the applicant’s use.
OVERWEIGHT AND OVERDIMENSIONAL MOVEMENTS
CHAPTER 1680-07-01
ON TENNESSEE HIGHWAYS
(3)
A sworn statement furnishing satisfactory proof of the applicant’s solvency shall mean an
audited financial statement, certified by a certified public accountant, showing net assets of
the applicant in an amount, as determined by the TDOT Permit Office, sufficient to indemnify
the state and/or counties for the potential damages to roads and bridges resulting from the
applicant’s use.