0800-03-03-.04
Installation Requirements
Cite as Tenn. Comp. R. & Regs. 0800-03-03-.04
(1)
Permission to Install.
(a)
All installers of boilers or pressure vessels shall be knowledgeable in the proper
installation of the boiler or pressure vessel they are requesting to install.
BOILER INSPECTIONS
CHAPTER 0800-03-03
(b)
The company or person responsible for the installation of the boiler or pressure vessel
(stamped lethal service) shall obtain an installation permit for the boiler or pressure
vessel prior to any work being performed. An “Application for Permission to Install a
Boiler
or
Pressure
Vessel
(stamped
lethal
service),”
boiler
room
layout
drawings/dimensions, Manufacturer’s Data Report, and a copy of any applicable
local/municipal building or like permit shall be forwarded to the Tennessee Department
of Labor and Workforce Development, Division of Workplace Regulations and
Compliance, Boiler Unit. “Tennessee Special” boilers and pressure vessels are subject
to the requirements of this rule.
(c)
All boiler installations between 400,000-12,500,000 BTU/hr (excluding hot water
heaters) shall meet all the requirements of ASME CSD-1. Boilers 12,500,000 BTU/hr
and over shall meet any additional requirements of NFPA 85. A copy of the “Controls
and Safety Devices” section of the installation application must accompany all
submitted Applications for Permission to Install a Boiler or Pressure Vessel (stamped
lethal service). Failure to comply with the requirements of this rule, without significant
explanation, could delay the permission to install approval or warrant non-acceptance
of the application.
(d)
After the application has been reviewed by the Chief Inspector or Chief Inspector’s
Designee, an installation permit shall be issued.
(e)
All newly installed boilers and pressure vessels (stamped lethal service) shall be
inspected by a Deputy Inspector before the boiler or pressure vessel is put into service.
The company or person performing the installation is responsible for notifying the
Tennessee Department of Labor and Workforce Development, Division of Workplace
Regulations and Compliance, Boiler Unit, when the boiler or pressure vessel (stamped
lethal service) is ready for inspection. The inspection upon installation by permit is
subject to the fees in accordance with Rule 0800-03-03-.14(10).
(f)
A revised application shall be submitted to the Chief Inspector or Chief Inspector’s
Designee by the installer if there is a change to the original application. A copy of the
original installation permit and supplemental documentation shall accompany the
revised application.
(g)
All installation permits shall be issued for a period of twelve (12) months. If the boiler or
pressure vessel (stamped lethal service) is not installed during this period, the
installation permit shall expire and the file shall be closed. When a file has been closed,
the installer shall be required to apply for another installation permit in accordance with
subparagraph (b) of this rule.
(h)
A boiler or pressure vessel may be installed prior to submission of the “Application for
Permission to Install a Boiler or Pressure Vessel (stamped lethal service)” when it has
been determined by the Chief Inspector or Chief Inspector’s Designee that the
installation is an emergency situation. Immediately thereafter, the installer shall submit
an application, layout drawings/dimensions, Manufacturer’s Data Report and a copy of
any applicable local/municipal building or like permit in accordance with subparagraph
(b) of this rule.
(i)
When it is discovered that a boiler or pressure vessel (stamped lethal service) has
been installed without an approved installation permit prior to installation, the Chief
Inspector or Chief Inspector’s Designee shall notify the owner or user. The Chief
Inspector or Chief Inspector’s Designee shall take appropriate action in accordance
with T.C.A. § 68-122-106. The owner or user shall be assessed a special inspection
fee set by the Chief Inspector or Chief Inspector’s Designee in accordance with T.C.A.
§ 68-122-113 and Rule 0800-03-03-.14(10). Any owner or user aggrieved by an order
BOILER INSPECTIONS
CHAPTER 0800-03-03
or act of the Chief Inspector or Chief Inspector’s Designee may, within fifteen (15) days
after notice thereof, appeal from such order or act to the Board.
(2)
Permission to Reinstall.
(a)
Reinstallation of Boilers or Pressure Vessels (Removed from the State). When a
standard boiler or pressure vessel located in this State is moved outside the State for
temporary use or repair, the owner or user shall apply to the Chief Inspector or Chief
Inspector’s Designee for permission to reinstall the boiler or pressure vessel in this
State. After the owner or user files the “Application for Permission to Reinstall” and it is
approved, the Deputy Inspector shall conduct an inspection. When a nonstandard
boiler or pressure vessel is removed from this State, it shall not be reinstalled within
this State without additional approval of the Board.
(b)
Installation of Second-Hand Boilers or Pressure Vessels. Second-hand boilers and
pressure vessels may not be installed unless the Chief Inspector or Chief Inspector’s
Designee approves an “Application for Permission to Reinstall.” After the owner or user
files the “Application for Permission to Reinstall” and it is approved, the Deputy
Inspector shall conduct an inspection.
(c)
Reinstallation of Boilers or Pressure Vessels (Not Second-Hand). The owner or user
shall apply to the Chief Inspector or Chief Inspector’s Designee for permission to
reinstall a boiler or pressure vessel in this State. After the owner or user files the
“Application for Permission to Reinstall” and it is approved, the Deputy Inspector shall
conduct an inspection.
(d)
An owner or user of the boiler and pressure vessel described in subparagraphs (a), (b)
and (c) of this rule is subject to the installation requirements in accordance with Rule
0800-03-03-.04(1), and the Special Inspection fee requirements of Rule 0800-03-03-
.14(10). An “Application for Permission to Reinstall” form must accompany all permit
applications for these installations.
(e)
For reinstalled boilers and pressure vessels with a current certificate of inspection, the
Deputy Inspector shall submit a reinspection report in accordance with Rule 0800-03-
03-.05(10)(b). The comment that the boiler or pressure vessel is “reinstalled” shall be
noted on the reinspection report. The reinspection shall be a non-certificate inspection.
(3)
Safety Appliances.
(a)
No person shall attempt to remove, or do any work on, any safety appliance prescribed
by this Chapter while the appliance is subject to pressure.
(b)
Should any such appliance be removed for repair during an outage of a boiler or
pressure vessel, it shall be reinstalled and in proper working order before the object is
again placed in service.
(c)
No person shall alter any safety or safety relief valve or pressure relief devices in any
manner to maintain a working pressure in excess of that stated on the boiler or
pressure vessel inspection certificate.
(d)
Only the holder of a valid Certificate of Authorization for use of the NB “VR” stamp, or
an owner-user’s maintenance organization approved by the Chief Inspector or Chief
Inspector’s Designee, may repair safety or safety relief valves. An owner-user
maintenance organization shall be limited to repairing such valves for its own use.
(4)
Pressure Reducing Valves.
BOILER INSPECTIONS
CHAPTER 0800-03-03
(a)
Where pressure-reducing valves are used, one (1) or more safety or safety relief valves
shall be provided on the low pressure side of the reducing valve when the piping or
equipment on the low pressure side does not meet the requirements for the full initial
pressure. The safety or safety relief valves shall be located adjoining or as close as
possible to the reducing valve.
(b)
Proper protection shall be provided to prevent injury or damage caused by escaping
vapor or fluid from the discharge of safety or safety valves if vented to the atmosphere.
The combined discharge capacity of the safety or safety relief valves shall be such that
the pressure rating of the lower pressure piping equipment will not be exceeded in case
the reducing valve fails in the open position.
(c)
Use of hand-controlled bypasses around reducing valves is permissible. If a bypass is
used around the reducing valve, the safety valve required on the low pressure side
shall be of sufficient capacity to relieve all the vapor or fluid that can pass through the
bypass without overpressuring the low pressure side.
(d)
A pressure gauge shall be installed on the low pressure side of a reducing valve.
(5)
Location of Discharge Piping Outlets. The discharge of safety valves, blowoff pipes and other
outlets shall be located and supported so as to prevent injury to personnel.
(6)
Application of State Serial Numbers. Upon completion of the installation of a boiler or
pressure vessel, or at the time of the initial certificate inspection of an existing installation, the
inspector shall tag each boiler or pressure vessel in the vicinity of the code stamping with a
Board approved and Department supplied registration tag.
(7)
Accessibility to Code Stamping. Code stamping shall not be concealed by lagging or paint.
The stamping shall be exposed at all times, unless a suitable record is kept of the location of
the stamping so that it may be readily uncovered when desired.
(8)
Restamping of Boilers and Pressure Vessels.
(a)
When the code stamping of a boiler or pressure vessel becomes indistinct, the
inspector shall instruct the owner or user to have it restamped. The owner or user shall
submit a request for authorization of restamping to the Chief Inspector or Chief
Inspector’s Designee on the appropriate “Replacement of Stamped Data Form.” Proof
of the original stamping shall accompany the request.
(b)
If the Chief Inspector or Chief Inspector’s Designee authorizes restamping, it shall be
done only in the presence of an inspector, and shall be identical with the original
stamping.
(c)
The ASME Certification Mark with Certification Designator may be restamped only by
the original manufacturer of the boiler or pressure vessel in the presence of an
inspector of the Authorized Inspection Agency who signed the Manufacturer’s Data
Report or a Deputy Inspector. The witnessing inspector shall file with the Chief
Inspector or Chief Inspector’s Designee the completed and signed “Replacement of
Stamped Data Form” with a facsimile of the stamping applied.
(9)
Working Pressure for Existing Installations. With the approval of the Chief Inspector or Chief
Inspector’s Designee, any inspector may decrease the maximum working pressure on any
existing installation if the condition of the boiler or pressure vessel warrants.
BOILER INSPECTIONS
CHAPTER 0800-03-03
(10) Supports. Each boiler and pressure vessel shall be supported by masonry or structural
supports of sufficient strength and rigidity to safely support the boiler or pressure vessel and
its contents. There shall be no excessive vibration in either the boiler, pressure vessel or its
connecting piping.
(11) Ladders and Runways. When necessary for safety, there shall be a steel runway or platform
of standard construction installed across the tops of adjacent boilers or pressure vessels or at
some other convenient level for the purpose of affording safe access. All walkways shall have
at least two (2) means of exit, each to be remotely located from the other.