R649-9-11

R649-9-11. General Construction and Inspection Requirements for E and P Recycling Facilities

Last amended: 2025Length: 120 wordsOfficial source

Cite as Utah Admin. Code R649-9-11

(1) Division personnel shall be given a reasonable opportunity for inspection of any E and P recycling facility during the construction and operation of the facility. (2) The division shall be notified at least 72 hours before the installation of leak detection systems or liners. (3) The division shall be notified after completion of facility construction so that a final inspection can be conducted to verify that the facility has been constructed in accordance with the approved application. (4) Failure to meet the requirements and standards for construction and operation of a E and P recycling facility shall be considered as noncompliance and will result in the imposition of corrective actions and compliance schedules or a cessation of operations order.
R649-9-11: R649-9-11. General Construction and Inspection Requirements for E and P Recycling Facilities | Justis AI