R64-4-8
R64-4-8. Contracting and Project Requirements
Cite as Utah Admin. Code R64-4-8
(1) Following a grant award by the Commission, the department shall assist each grantee in identifying sources and securing additional funding for the project, as outlined in Subsection 73-10g-206(5)(c).
(2) Before receiving funds, a grantee shall fulfill the following requirements, consistent with Subsection 73-10g-206(3) by:
(a) entering a contract with the department that includes the following:
(i) the expectations for the grantee;
(ii) the life expectancy of the project;
(iii) the process to certify completion of the project;
(iv) any applicable design requirements; and
(v) metering and reporting requirements consistent with rules established by DWRi, including specifications for the type of meter to be installed;
(b) filing any necessary change application with DWRi;
(c) if applicable, obtaining a final order from the State Engineer approving the change application; and
(d) if applicable, demonstrating compliance with the requirements of the final order.
(3)(a) Before project implementation, grantees shall submit a Utah State Historical Preservation Office Cultural Resource Review report to the department, pursuant to Section 9-8a-404.
(b) The department may not process a payment reimbursement until the department receives the report.
(4) The department may issue a notice to proceed to a grantee before project construction.
(5) During the life of the project, the department shall:
(a) monitor grant related activities; and
(b) certify project completion.
(6) The department may conduct on-site or virtual project "spot checks" at any time during the life of the project.