R307-209-3
R307-209-3. Applicability
Cite as Utah Admin. Code R307-209-3
(1) Rule R307-209 applies to each portable aggregate processing plant including each concrete batch plant, asphalt plant, and nonmetallic mineral processing plant.
(2) Rule R307-209 does not apply to concrete batch plants, asphalt plants, or nonmetallic mineral processing plants that are subject to an approval order issued under Section R307-401-8.
(3) Rule R307-209 does not apply to a concrete batch plant, asphalt plant, or nonmetallic mineral processing plant that plans to or will operate at a single source longer than 180 operating days or remains at a source longer than 365 calendar days. These sources shall submit a notice of intent and obtain an approval order under Rule R307-401 before beginning actual construction unless the source qualifies for an exemption under Section R307-401-9.